Marine Link
Tuesday, March 19, 2024
SUBSCRIBE

Army Corps News

18 Mar 2024

First Tow Through Lock 2 Kicks Off Navigation Season on the Mississippi

The first tow of 2024 goes through Lock and Dam 2 in Hastings, Minn., on March 17. (Photo: U.S. Army Corps of Engineers)

The first towboat of 2024 passed through Lock and Dam 2, in Hastings, Minn. on Sunday, signaling the start of this year's navigation season on the Mississippi River.The U.S. Army Corps of Engineers' St. Paul District said it considers the first tow to arrive at Lock and Dam 2 as the unofficial start of the Mississippi River navigation season, because it means all of its locks are accessible to commercial and recreational vessels.On Sunday, Marquette Transportation Company's Joseph Patrick Eckstein traveled through the lock with 12 barges en route to St.

11 Mar 2024

Callan Marine Awarded Houston Dredging Contract

General Arnold (Photo: Callan Marine)

Galveston-based dredging contractor Callan Marine has been awarded a $136 million contract from Port Houston to dredge segment 1C of the Houston Ship Channel Expansion, under the port's Project 11 program.Callan will use its recently christened 32-inch cutter suction dredge, the General Arnold, among the newest, largest and most environmentally friendly cutter suction dredge in the U.S. fleet for the undertaking. The dredge features four EPA Tier 4 engines developing a combined 24…

13 Feb 2024

Solana Beach Dredging On Track

A split-hull trailing suction hopper dredge, linked to a tugboat, operates Jan. 31 off the shore of Solana Beach, Calif. (Photo: Stephen Baack / USACE)

A dredging and sand replenishment project at Southern California's Solana Beach is about halfway complete, the U.S. Army Corps of Engineers said.The project, which reduces coastal storm damage and erosion along a 7,200-foot-long stretch of shoreline, includes construction of a 150-foot-wide beach fill using 700,000 cubic yards of compatible sediment.Operations started Jan. 17 and are on schedule to wrap up in mid-March, according to Caleb Lodge, coastal engineer with the Corps' Los Angeles District.“They’re doing about seven or eight loads a day…

01 Feb 2024

Coastal Virginia Offshore Wind Farm Gets Final Federal Blessing

© Fokke Baarssen / Adobe Stock

Dominion Energy, the developer of Coastal Virginia Offshore Wind (CVOW) farm, has secured the last two major federal approvals needed to begin the construction of the 2.6 GW project.The approvals are keeping the largest offshore wind farm in the United States on schedule to generate clean, renewable energy to power up to 660,000 homes once fully constructed.The Bureau of Ocean Energy Management (BOEM) provided its final approval of CVOW's Construction and Operations Plan (COP), which authorizes construction offshore.The U.S.

26 Jan 2024

Orion Joins Dredging Contractors of America

(Photo: Chip Worley / U.S. Army Corps of Engineers)

Houston based dredging and marine construction contractor Orion Group Holdings – Marine Group has become a member of trade group the Dredging Contractors of America (DCA).Orion has a near 100-year legacy and today ranks among market leaders in the provision of dredging services to keep waterways serviceable and to expand ports and other marine infrastructure throughout the United States, territories and Caribbean. The company works to create beneficial marsh habitats, dredging…

28 Dec 2023

Great Lakes Bags $173.7 Million in New Dredging Contracts

File photo: Great Lakes' hopper dredge Padre Island in Galveston Channel in August 2023. (Credit: Luke Waack / U.S. Army Corps of Engineers)

Great Lakes Dredge & Dock Corporation on Thursday announced the receipt of five dredging contracts totaling $173.7 million. The projects are in Texas, New Jersey, Florida and Louisiana.The Sabine-Neches Waterway Channel Improvement Project-Phase 1 (Capital, Texas, $62.8 million) includes dredging for channel deepening along the Sabine-Neches Waterway from Sabine Bank Channel to Sabine Pass Channel. The construction of the Sabine-Neches Waterway will generate widespread economic benefits for Southeast Texas…

14 Dec 2023

Upper Miss Navigation Season Draws to a Close

The last tow of the 2023 navigation season: The towboat Thomas Erickson departed Lock and Dam 10, near Guttenberg, Iowa, Dec. 3, with 15 barges. (Photo: U.S. Army Corps of Engineers, St. Paul District)

The 2023 navigation season has drawn to a close on the Upper Mississippi River.A 15-barge tow pushed by the towboat Thomas Erickson, the last of the season, departed Lock and Dam 10, near Guttenberg, Iowa, December 3, the U.S. Army Corps of Engineers, St. Paul District said.The 2023 season commence March 12, when the towboat Phillip M Pfeffer broke its way through the ice of Lake Pepin to travel to St. Paul, Minnesota.With the 2023 navigation season in the rearview, St. Paul District staff will remain busy this coming winter with maintenance projects at Lock and Dam 2…

13 Dec 2023

Tacoma, Seattle Ports Ink Deals for Navigation Improvement Projects

(Photo; The Northwest Seaport Alliance)

Pacific Northwest seaports Seattle and Tacoma have signed design agreements with the U.S. Army Corps of Engineers (USACE) for a pair of waterway navigation improvement projects.The Seattle Navigation Improvement Project, authorized by Congress in 2018, and the Tacoma Harbor Navigation Improvement Project, authorized in 2022, are part of a comprehensive modernization initiative for The Northwest Seaport Alliance (NWSA) gateway that began nearly a decade ago.Containerships navigating in the trans-Pacific trade are increasing in size…

04 Dec 2023

Marine News' Top Vessels of 2023

Empire State (Photo: MARAD)

The November edition of Marine News magazine highlighted a selection of the most notable American newbuilds delivered of 2023—from a first-of-its-kind green towboat, to the lead vessel in a series of game-changing ships to train U.S. mariners.Empire StateAs the lead vessel in a series of five new training ships being constructed to serve America's state maritime academies, Empire State is easily one of the most important U.S.-built vessels delivered in recent memory.Built by Philly Shipyard for the U.S.

06 Nov 2023

Navigating Sustainability: Charting a Way Forward

© Aaron Kohr / Adobe Stock

You can feel it in the air, and increasingly on the water: a steady increase in momentum toward a global economy that prioritizes sustainability. Government stakeholders at all levels, and shipping customers across industries, are setting ambitious goals and high expectations for environmental performance, and that includes the transportation of U.S. and global commerce on the waterways.For the tugboat, towboat and barge industry, which moves nearly 700 million tons of cargo on America’s rivers, coastal waters and Great Lakes annually, it’s both an exciting and challenging time.

01 Nov 2023

Cashman Wins $29 Million Contract for Baltimore Dredging

(File photo: Cashman Dredging & Marine Contracting Co. LLC)

Quincy, Mass. based Cashman Dredging & Marine Contracting Co. LLC, has secured a contract to perform maintenance dredging in Baltimore, Md.The $29,131,250 firm-fixed-price contract was awarded by the U.S. Army Corps of Engineers' Baltimore District. Cashman was one of three bidders for the project.The project, which involves the removal of 1,400,000 cubic yards (cy) from deep-draft federal navigation channels, is estimated to wrap up by March 31, 2024.Dredging depth varies by…

19 Oct 2023

Mississippi River Lowered Near Minneapolis for Dam Maintenance

(Photo: Patrick Loch / USACE)

The U.S. Army Corps of Engineers, St. Paul District, and the Minnesota Department of Natural Resources, have lowered the Mississippi River water elevations between Lower St. Anthony Falls and Lock and Dam 1, both in Minneapolis, from October 13.Corps officials plan to maintain the lower river elevations through October 30, to allow Twin Cities Hydro, LLC, to inspect and repair the rubber dam atop the spillway at Lock and Dam 1, also known as the Ford Dam.To access the rubber dam, the water levels need to be lowered approximately one foot below the spillway crest for approximately two weeks.

16 Oct 2023

Massachusetts Offshore Wind Farm Dodges Lawsuits over Environmental, Fishing Concerns

Credit: Avangrid

A U.S. judge has rejected challenges to federal environmental permits and construction approvals for a $4 billion offshore wind farm near Massachusetts, which commercial fishing groups have claimed will harm whales and impair their businesses.U.S. District Judge Indira Talwani in Boston last Thursday tossed the final two federal district court lawsuits directly challenging the Vineyard Wind project roughly 15 miles south of Martha’s Vineyard, which would be the first commercial…

12 Oct 2023

Inland Waterways: US Making Progress on Infrastructure

(Photo: Michel Sauret / USACE)

The United States’ vast network of navigable inland rivers is vital to the nation’s economy, serving as an aquatic superhighway for the efficient shipment of critical commodities like agricultural goods, energy products, building materials and industrial chemicals to destinations within the U.S. and to deepwater ports for export. The Waterways Council, Inc. (WCI), which advocates for a modern, efficient and well-maintained inland waterways, often describes the network as “the…

26 Oct 2023

New 'Multi Cat' Workboats Delivered to Great Lakes Dredge & Dock

(Photo: Great Lakes Dredge & Dock Corporation)

Houston-based dredging contractor Great Lakes Dredge & Dock Corporation announced it has taken delivery of the Cape Hatteras and the Cape Canaveral, the two Damen 3013 Multi Cats built by Conrad Shipyard in Morgan City, La.“This is a milestone for our company and the U.S. dredging industry,” said Chris Gunsten, Great Lakes’ senior vice president of project services and fleet engineering. “The Multi Cat brings step change safety improvements to Great Lakes’ dredge pipeline operations, which was a prime driver for the investment.

26 Sep 2023

Inland Dredging Co Awarded Brownsville Dredging Job

© masterskuz55 / Adobe Stock

Dyersburg, Tenn. based Inland Dredging Co. has been awarded a contract from U.S. Army Corps of Engineers' Galveston District for channel pipeline dredging in Brownsville, Texas.The company beat out three other bidders to secure the $10,433,550 firm-fixed-price contract.Work is estimated to be completed by June 19, 2024.

25 Sep 2023

USACE Working to Prevent Saltwater from Rising Up the Mississippi

Col. Cullen Jones, USACE New Orleans District commander, briefs media Sept. 15, 2023, on current steps the Corps plans to take to augment the existing underwater sill constructed by USACE in the Mississippi River to help slow progression of the saltwater wedge moving upriver from the Gulf of Mexico. (Photo: Ryan Labadens / U.S. Army)

The U.S. Army Corps of Engineers, New Orleans District is working to delay upriver progression of salt water from the Gulf of Mexico by augmenting the sill initially constructed in July 2023.Construction is underway to increase the existing underwater sill from a depth of -55 feet to a depth of -30 feet. A 620-foot-wide navigation lane will be kept to a depth of -55 feet to ensure deep-draft shipping continues along the nation’s busiest inland waterway.USACE initially constructed…

21 Sep 2023

Dredging Expected During Desperate Times

Rock Island District's local maintenance crew from the Mississippi River Project Office in Pleasant Valley, Iowa, performs mechanical dredging with a three-yard crane bucket mounted on a barge in Pool 16. (Photo: Kelcy Hanson / USACE)

Maintaining a nine-foot channel on the Mississippi River is part of the U.S. Army Corps of Engineers Rock Island District’s critical navigation mission, especially during low-water conditions. Although early spring snowmelt caused flooding throughout the upper Midwest this past year, water levels receded quickly, causing large amounts of material to settle in the channel.To aid in channel maintenance, geological surveyors regularly monitor water levels throughout the District.

19 Sep 2023

Conrad to Build New Spud Barge

(File photo: USACE)

Gulf Coast shipbuilder Conrad Shipyard was awarded a contract to build a new steel spud barge for the U.S. Army Corps of Engineers.Conrad was the sole bidder for the contract, which was awarded by the Corps' Philadelphia district. Under the $9,106,800 firm-fixed-price award, Conrad will design, construct, test, and deliver the new barge.Work will be performed in Morgan City, La., with an estimated completion date of April 14, 2025.

15 Sep 2023

Great Lakes Awarded USACE Dredging Work in Georgia

© Yaniv / Adobe Stock

Houston-based dredging contractor Great Lakes Dredge & Dock has been awarded a contract from the U.S. Army Corps of Engineers to perform maintenance dredging in Saint Marys, Ga.Great Lakes was one of two bidders for the project, securing the $18,645,500 firm-fixed-price contract from USACE's Jacksonville District.Work is estimated to be completed by June 28, 2024.

14 Sep 2023

USACE Awards Contract for Monongahela River Locks and Dam 3 Removal

(Photo: U.S. Army Corps of Engineers)

The U.S. Army Corps of Engineers Pittsburgh District awards a nearly $30 million contract to remove the Monongahela River Locks and Dam 3 in Elizabeth, Pa.The district awarded the dam removal contract to the Pittsburgh-based Joseph B. Fay Company.The work is part of the Lower Monongahela River project, which includes the construction of the larger lock chamber at Locks and Dam 4 at river mile 41.5 near Charleroi and the replacement of the fixed-crest dam with a gated dam at Locks and Dam 2 in Braddock…

06 Sep 2023

Port of Corpus Christi Promotes CFO Kent Britton to CEO

Kent Britton (Photo: Port of Corpus Christi)

The Port of Corpus Christi on Wednesday named Chief Financial Officer Kent Britton as its new chief executive officer to head the largest U.S. oil-export port by volume.The appointment comes nearly four months after Sean Strawbridge, the previous chief executive, abruptly resigned after he was questioned about his business expenses.Strawbridge has said all his expenses were in compliance with port policies and state statutes, and have all cleared the internal review process and…

29 Aug 2023

Eastern Gets Green Light to Build USACE Hopper Dredge

(Image: Eastern Shipbuilding Group)

Florida-based Eastern Shipbuilding Group announced on Tuesday it has received a notice to proceed after winning a contract to design and build a new hopper dredge for the U.S. Army Corps of Engineers (USACE).The 6,000-cubic-yard-capacity diesel-electric dredge will be constructed at Eastern’s Allanton and Port St. Joe facilities and is scheduled for delivery in 2027, the builder said.The new medium-class hopper dredge (MCHD) will be based at the Corps’ Philadelphia District, replacing the 57-year-old McFarland…

Subscribe for
Maritime Reporter E-News

Maritime Reporter E-News is the maritime industry's largest circulation and most authoritative ENews Service, delivered to your Email five times per week