Arduous GoM Drill Rig Salvage Accomplished

Press Release
Friday, April 12, 2013
The Jack-up Rig: Photo credit Inland Salvage Inc.

Inland Salvage successfully delivers salvaged jack-up drill rig which sank last winter in the Gulf of Mexico.

In mid-December 2012 a retired jack-up drill rig under tow from Fourchon, LA to be dismantled in Texas began taking on water. Despite being in the crowded waters of the oilfield, the tow captain was able to maneuver the sinking rig into a little used section of the Vermillion Block where the seas finally washed over the main deck and forced the rig to the ocean floor.

Inland Salvage Incorporated (ISI), based in Harvey, LA, was awarded the salvage contract and began dedicating assets towards the effort, teaming up with Titan Salvage of Pompano Beach Fl. Titan's naval architects began performing stability calculations while ISI and Titan personnel mobilized to the wreck site onboard a 185 class lift boat which could remain on location even during the Gulf's winter storms.

The Salvage Master, Gordon Olson, determined it would be best to approach the salvage from two fronts. One dive team would work to restore buoyancy to the barge and mud mat, while the second team would attempt to reestablish control of the now submerged jacking system.  Salvage Engineers developed an external hydraulic supply and control unit that was connected to the existing jacking system by divers working in the confined spaces of the rig. At the same time, divers penetrated into the barge tanks to install salvage pumps and restore the rig's dewatering system for the mud mat.

With the work complete and a break in the weather, the process of raising the barge using its own jacking system began. The hydraulic repairs were successful and the barge slowly moved up the rig's legs. As the main deck broke the waters surface, the salvors began pumping the barge to lessen the load on the hydraulic jacks, which continued until the barge was completely jacked up out of the water.

It was decided to set the jack up onto a receiver barge that could safely survive the trip to the scrap yard. The rig was jacked high enough above the water to allow an ocean going receiver barge to be floated underneath of it. Once the floating vessel was in position, the jacks began lowering the rig onto the receiver deck. The rig's mud mat was then raised up under the receiver barge and the tow was underway. The barge and rig combination safely arrived at its destination where the process was reversed and the jack up rig successfully delivered.
 


 

Maritime Reporter November 2014 Digital Edition
FREE Maritime Reporter Subscription
Latest Maritime News    rss feeds

Contracts

Wärtsilä to Begin Building LNG Terminal in January

Wärtsilä has been given full notice to proceed (NTP) from Manga LNG Oy for the supply of a liquefied natural gas (LNG) import terminal in Tornio, Northern Finland.

Polarcus Awarded 3D Project Off West Africa

Polarcus Limited has signed a letter of intent with Perenco Oil & Gas Gabon S.A. for a 3D marine seismic acquisition project offshore West Africa.   The project,

Boskalis, VolkerWessels Win Offshore Wind Farm Work

Royal Boskalis Westminster N.V., in partnership with Volker Stevin International (VolkerWessels), has been awarded a contract by Iberdrola Renewables Offshore Deutschland

Offshore

DNV GL Targets Safer Approach to Subsea Lifting

The completion of a joint industry project (JIP) to improve existing standards and regulations around subsea lifting operations has resulted in a new recommended practice (RP).

Polarcus Awarded 3D Project Off West Africa

Polarcus Limited has signed a letter of intent with Perenco Oil & Gas Gabon S.A. for a 3D marine seismic acquisition project offshore West Africa.   The project,

Boskalis, VolkerWessels Win Offshore Wind Farm Work

Royal Boskalis Westminster N.V., in partnership with Volker Stevin International (VolkerWessels), has been awarded a contract by Iberdrola Renewables Offshore Deutschland

Salvage

NZ Report: Human Error to Blame for Rena Grounding

New Zealand's Transport Accident Investigation Commission (TAIC) published its final report into the grounding of containership Rena in October 2011. The TAIC’s

Workboats: Communications is Key Operational Tech

As we close out yet another year, I am constantly amazed at how much things change on the waterfront and the boats that ply the adjacent waters. Similarly, I like

Report: Dire Conditions in Indian Shipbreaking Yards

Report by Indian research institute reveals poor enforcement of occupational health and safety provisions   The working and living conditions at the shipbreaking yards of Alang,

Subsea Salvage

Wrecked Bulker’s Bow Refloated, Scuttled off S.Africa

TITAN Salvage, Crowley Maritime Corp.'s Houston-based marine salvage, emergency response and wreck removal company, has refloated and scuttled the largest section of the wrecked bulk carrier, Smart.

Mermaid Wins Subsea Contract in Gulf of Thailand

Mermaid has secured a 2-year contract for its dive support vessel, ‘Mermaid Commander’, to provide subsea construction support in the Gulf of Thailand for a

Lifting Costa Concordia

Ropes made with Dyneema help Titan Salvage, Micoperi on historic salvage operation   The largest and most complex maritime salvage operation ever carried out was concluded this summer.

 
 
Maritime Security Maritime Standards Navigation Pipelines Pod Propulsion Salvage Ship Simulators Shipbuilding / Vessel Construction Sonar Winch
rss | archive | history | articles | privacy | terms and conditions | contributors | top maritime news | about us | copyright | maritime magazines
maritime security news | shipbuilding news | maritime industry | shipping news | maritime reporting | workboats news | ship design | maritime business

Time taken: 0.2411 sec (4 req/sec)