Lincoln Ahead Of Schedule

Wednesday, December 27, 2006
USS Abraham Lincoln (CVN 72) left the dry dock on Dec. 18, ahead of schedule and under budget becuase Puget Sound Naval Shipyard and Intermediate Maintenance Facility (PSNS & IMF) cut the time of ship tank maintenance by more than half. Partnering with Ship’s Force and the Lincoln Project Team, the Tank Value Stream Team accomplished the goal. Through the Lean Continuous Improvement process, the teams completed 18 tanks in 89 days.

“Value Streams are main branches of maintenance work that have been identified individually for process improvement through lean technology,” explains Mark Winkler, the team leader. “The goal is to provide improved products and cost performance to the customer. Tank maintenance is one such value stream.” Lincoln's Commanding Officer, Capt. Andrew McCawley, and the ship’s crew turned out to congratulate the Tank Value Stream Team on their success at a recognition ceremony in Hangar Bay 2 onboard the ship Dec. 15. “I want to thank you on behalf of Lincoln and congratulate you on your accomplishment,” said McCawley. “This really is significant. I’d like to offer you a ship’s perspective on what you’ve done for Abraham Lincoln. You have inspired the crew through your dedication and staying on schedule while overcoming every challenge. You have also added to the quality of life of the crew and increased the material readiness of the ship.”

In August of this year, Abraham Lincoln returned from a six month deployment to the Western Pacific. The Everett, Wash. based aircraft carrier also participated in Iraqi Freedom in 2003 and Operation Unified Assistance in 2005. The ship and crew have been highly successful in their missions. “Those successes are as much yours as the crew who has been deployed,” Captain McCawley told the hundreds of people assembled. “You have produced the material readiness and capability that Abraham Lincoln possesses. Your victory here today is Abraham Lincoln's success tomorrow.” Capt. Dan Peters, Commander, Puget Sound Naval Shipyard & Intermediate Maintenance Facility, expressed his pride in the remarkable achievements.

“I’m proud to stand before you and express my appreciation for what this team has accomplished,” stated Peters. “Members of the Tank Value Stream made a commitment to tackle this extraordinary task of significantly reducing cost and schedule with top shelf enthusiasm and professionalism. You rose to the challenge and far exceeded expectations.” “It’s not possible to have this kind of success without teamwork,” Capt. Peters continued. “You, Ship’s Force, the project team, and our maintenance partners together make these significant improvements possible.” “What you succeeded in accomplishing has just raised the bar for the rest of the maintenance world,” concluded Peters, speaking to the workers and Ship’s Force packing the hangar bay at the end of the celebration ceremony. “Now we have to prove that this wasn’t a one-time success, that it is a sustainable process.” Source: NavNews

By Mary A. Mascianica, Puget Sound Naval Shipyard Public Affairs

Maritime Reporter September 2015 Digital Edition
FREE Maritime Reporter Subscription
Latest Maritime News    rss feeds


Northern Fleet to Conduct Anti-terrorist Exercises

The sailors of the Northern Fleet will conduct anti-terrorism exercises at Novaya Zemlya. During the exercise, the coast will be a landing. The landing will

ADF’s New Amphibious Capability Demonstrated

Australia’s newest military capability, the Amphibious Ready Element, has demonstrated its capacity in waters off the North Queensland coast during the Sea Series of exercises.

Michelle Obama to Christen Navy's Newest Submarine

U.S. First Lady Michelle Obama will join builder General Dynamics Electric Boat, a wholly owned subsidiary of General Dynamics, in christening Illinois (SSN-786), the U.


Finland Scraps LNG Terminal Plan

Finnish gas utility Gasum has abandoned its plans to build the Finngulf liquefied natural gas  (LNG) import terminal in Finland with an offshore pipeline connection

MARAD Backs Emissions Reduction Projects

The U.S. Department of Transportation’s Maritime Administration (MARAD) announced it will provide more than $1 million to support the development of two new emission-reducing maritime solutions.

Becker Marine, Kotug Sign MOU for LNG Hybrid Barge

Press release - Becker Marine Systems and KOTUG signed a Memorandum of Understanding to launch a LNG Hybrid Barge in the Port of Rotterdam with effect from June 2017.

Maritime Contracts Maritime Security Naval Architecture Pipelines Port Authority Ship Electronics Ship Repair Ship Simulators Shipbuilding / Vessel Construction Winch
rss | archive | history | articles | privacy | contributors | top maritime news | about us | copyright | maritime magazines
maritime security news | shipbuilding news | maritime industry | shipping news | maritime reporting | workboats news | ship design | maritime business

Time taken: 0.2564 sec (4 req/sec)