Navy Issues Stop Work Order for LCS 3

Monday, January 15, 2007
The first Littoral Combat Ship, Freedom (LCS 1) is shown under construction in Marinette, Wis. Photo Credit: Lockheed Martin Corporation

Navy Issues Stop Work Order for LCS 3 The Navy issued a stop work order Jan. 12 to Lockheed Martin Corp. Maritime Systems & Sensors unit, Moorestown, N.J., for the construction of the third Littoral Combat Ship (LCS). This stop work order will take effect immediately and is for a period of 90 days.

The stop work order was issued because of significant cost increases currently being experienced with the construction of LCS-1 and LCS-3, under construction by Lockheed Martin. “I determined that at this point in time it was critical to stop work on LCS-3 to assess the LCS program and ensure we understand the program’s cost and management processes before we move forward. It is essential that we complete LCS 1 and get it to sea so we can evaluate this new ship design” said Secretary of the Navy Donald Winter. The Navy is working closely with the contractor to identify the root cause of the costs growth. The Navy is reviewing the overall acquisition strategy for the LCS program and is working closely with the contractors to keep this program on track. The contract for LCS-3 was awarded June 26, 2006, for $197.6 million, and the ship is being constructed at Bollinger Shipyard, Lockport, La.

"The Littoral Combat Ship program remains of critical importance to our Navy. With its great speed and interchangeable warfighting modules, the ship will provide unprecedented flexibility, allowing us to combat almost any specific threat -- from enemy mines to submarines to even pirates. It will help us defend our nation not just in the deep blue, but up close in the coastal regions of the world where our enemies like to hide and where so many of our friends and partners strive to prosper," said Chief of Naval Operations Adm. Mike Mullen. source: NavNews

Maritime Reporter May 2015 Digital Edition
FREE Maritime Reporter Subscription
Latest Maritime News    rss feeds

LNG

Construction Starts on Crowley’s 2nd LNG ConRo Ship

Construction begins on Crowley’s second Commitment Class, LNG-powered ConRo ship for use in the Puerto Rico trade   Shipbuilder VT Halter Marine, Inc. has officially

Hoegh LNG Bags FSRU Deal in Chile

Oslo-based Höegh LNG said it has signed an Floating Storage and Regasification Unit (FSRU)contract with Chilean Octopus LNG for the Penco-Lirquén LNG import terminal to be located in Concepción Bay,

CNPC Eyes Myanmar for LNG Terminal

China's biggest oil and gas company China National Petroleum Corp.(CNPC ) has expressed interested in  a terminal in Kyaukphyu in Myanmar  to receive imported Liquefied natural gas (LNG).

 
 
Maritime Careers / Shipboard Positions Maritime Contracts Maritime Security Maritime Standards Navigation Offshore Oil Pipelines Ship Repair Shipbuilding / Vessel Construction Sonar
rss | archive | history | articles | privacy | contributors | top maritime news | about us | copyright | maritime magazines
maritime security news | shipbuilding news | maritime industry | shipping news | maritime reporting | workboats news | ship design | maritime business

Time taken: 0.1613 sec (6 req/sec)