LCS 1 Begins Final Dockside Testing

Thursday, July 10, 2008

The propulsion plant of the nation's first Littoral Combat Ship, Freedom (LCS 1), has completed testing in preparation for dock trials. The ship is now ready to begin dock trials -- the final stage of testing before underway trials.

The 378-foot Freedom is powered by an innovative, combined diesel and gas turbine propulsion plant, with steerable water jet propulsion. This system will power the ship at cruise speeds out to ranges exceeding 3,500 nautical miles and will also allow the ship to sustain sprint speeds over 40 knots. Dock trials includes a series of demonstrations of propulsion, navigation, communication and other systems conducted to ensure the ship is ready for sea trials.

There has been rapid progress on Freedom since the beginning of the year. In February, LCS 1's four 750-kilowatt Fincantieri Isotta Fraschini diesel generators were lit off and its three-megawatt electrical power plant was successfully tested. In March and April, initial testing of the two Fairbanks Morse diesel engines occurred. The two Rolls-Royce MT30 gas turbine engines -- the largest and most powerful ever installed on a Navy ship -- were successfully lit off and tested in May, as were the steerable Rolls-Royce Kamewa water jets.

Over the next few weeks, dockside testing of the ship's engines and other systems will conclude at Marinette Marine in preparation for underway trials. Freedom will be delivered to the U.S. Navy in 2008 and will be home ported in .

Maritime Today

The Maritime Industry's original and most viewed E-News Service

Maritime Reporter November 2015 Digital Edition
FREE Maritime Reporter Subscription
Latest Maritime News    rss feeds


EuronavSells Suexmax Cap Laurent

Euronav NV announced the sale of its Suezmax Cap Laurent for $22.25 million. The 1998-built 146,145-dwt vessel was wholly owned by Euronav.    The vessel was

Seajacks Scylla Delivered

Seajacks Scylla, touted as the world's largest and most advanced wind farm installation and offshore construction vessel, has been delivered by the Samsung Heavy Industries Shipyard in Geoje,

It's All in the Planning

Continuing voracious demand for mined materials in China, India and other developing nations has led to an associated requirement for increased bulk terminal capacity

Maritime Careers / Shipboard Positions Maritime Contracts Maritime Standards Navigation Pipelines Port Authority Salvage Ship Repair Shipbuilding / Vessel Construction Winch
rss | archive | history | articles | privacy | contributors | top maritime news | about us | copyright | maritime magazines
maritime security news | shipbuilding news | maritime industry | shipping news | maritime reporting | workboats news | ship design | maritime business

Time taken: 0.0717 sec (14 req/sec)