Production Shutdown on Kristin

Thursday, January 08, 2009
File The Kristin platform in the Norwegian Sea (Photo: Trond Sigvaldsen)
The Kristin platform in the Norwegian Sea (Photo: Trond Sigvaldsen)

StatoilHydro announced that production on the Kristin field in the Norwegian Sea has now been shut down and the platform staff is being temporarily reduced until the lifeboat systems have been tested and found to be functional.

“A defect has been discovered in the release mechanisms of the new lifeboat type installed on the Kristin platform,” said Eileen Buan, head of operations on the Kristin field. “We are therefore carrying out a controlled production shutdown and reducing the platform staff as quickly and safely as possible.”

Kristin is producing around 10 million cubic metres of gas per day and around 10,000 cubic metres of condensate per day. Production capacity is 125,000 barrels of condensate and a good 18 million cubic metres of rich gas per day. StatoilHydro’s gas customers will not be affected by the shutdown.

The staff will be reduced from around 90 to 16 people, which is an absolute minimum level, and safety around the platform will be enhanced. This situation will be maintained until the tests have been run and the lifeboats are found to be functional. The test equipment is underway to the platform and the tests will be carried out as soon as possible.

Helicopter is the primary evacuation solution in the event of an accident or dangerous situation on offshore installations, but the lifeboat capacity must be sufficient to be able to evacuate all personnel onboard during all weather conditions. Lifeboats of the same FF1000S type are also installed on the Veslefrikk B platform in the North Sea. A test carried out on Wednesday revealed a faulty release mechanism on two of the three lifeboats on Veslefrikk B. This test result led to production shutdown and temporary staff reduction on the Kristin platform.

Changes in the technical arrangements for the release mechanism are currently being considered. Until the solution has been found and the changes have been tested and verified, none of the three lifeboats on Veslefrikk B will be used. Veslefrikk B is connected by a bridge to Veslefrikk A, where the lifeboat capacity is intact. The staff on the field has been reduced, however production is maintained.

Veslefrikk has lifeboat capacity on Veslefrikk A and can therefore maintain its production.

Email AddThis Feed Button Share
Maritime Reporter May 2013 Digital Edition
FREE Maritime Reporter Subscription
Latest Maritime News    rss feeds

Offshore

Megan Bel Joins National Ocean Industries Association Staff

Megan Bel joined the staff of the National Ocean Industries Association (NOIA) as Senior Director, Government and Political Affairs. She comes to NOIA from the

Tidewater to Acquire Troms Offshore Supply

US Firm, Tidewater, agrees with HitecVision to purchase Norway's Troms offshore, including 5 large PSV's. Tidewater say that the acquisition of Troms Offshore,

Vestdavit Secures Besiktas Seismic Chase Boat Davit Orders

Norway-based boat handling system and specialized davit supplier Vestdavit was contracted to supply work boat and man overboard davits for four specially designed

 
 
mobi | rss feeds | archive | history | articles | privacy | contributors | top news | about us | copyright