Hywind Power Line in Place

Wednesday, August 12, 2009

The 13-kilometre submarine cable to carry electricity from the Hywind floating wind turbine has now been installed and tested in the sea north-west of Stavanger.

Once generation starts, the power will come ashore in Røyrvika near Skudeneshavn on the island of Karmøy and be delivered to local grid operator Haugaland Kraft.

This pilot project, based on StatoilHydro’s own concept, ranks as the world’s first full-scale floating wind turbine. It arrived on location 10 kilometres from land in late June.

“We’ve worked this summer on mooring the floater to the three seabed anchor points as well as laying and testing the cable,” said Sjur Bratland, StatoilHydro’s venture manager for Hywind.

“It’s very satisfying that both these operations have now been completed with positive results.”

From the operational base at Skudeneshavn, the group has closely monitored the work carried out by contractors Nexans and Siemens to ensure safe and accurate execution, he reports.

The rotor blades, which are about 80 metres in diameter, were tested for the first time in July. Further testing will continue until the official opening on 8 September.

Plans call for the Hywind unit to start generating electricity in late September or early October, and for testing to continue over a two-year period.

The goal is to obtain information and data which can be used for continued development of the concept and to help reduce costs so that floating wind power can compete in the electricity market.

Maritime Reporter July 2015 Digital Edition
FREE Maritime Reporter Subscription
Latest Maritime News    rss feeds

Offshore

BSEE Updates Hurricane Reporting Requirements

BSEE is providing updated guidance for the current and future hurricane seasons through a Notice to Lessees (NTL) released July 27, 2015. NTL 2015-G02 clarifies

Offshore Wind Shift to Drive Vessel Services Cooperation

Evolving procurement processes for U.K. Round 3 offshore wind farms will require a greater number of work streams, personnel with new and differing skills, and

ABB hands over Germany’s DolWin1

DolWin1 integrates 800 megawatts (MW) of clean energy into the German transmission grid ABB, the leading power and automation technology group, has successfully

 
 
Maritime Careers / Shipboard Positions Maritime Contracts Maritime Standards Naval Architecture Navigation Port Authority Salvage Ship Simulators Sonar Winch
rss | archive | history | articles | privacy | contributors | top maritime news | about us | copyright | maritime magazines
maritime security news | shipbuilding news | maritime industry | shipping news | maritime reporting | workboats news | ship design | maritime business

Time taken: 0.2189 sec (5 req/sec)