Signal International announced the delivery of the Frontier Driller semisubmersible rig which underwent a major upgrade and modernization at its East Bank yard in Pascagoula, Miss.

The scope of work encompassed starting with a veteran semisubmersible rig; renovating and outfitting it with updated drilling and marine equipment to render the rig capable of drilling deeper wells.

Major tasks such as construction of new derrick (single lift), new BOP handling structure, addition of winch decks (four corners), new riser decks, new ROV deck, raised mud pit roof, converted chain lockers to bulk mud tanks, and new cement deck. Large structures required major lifts of 50 tons – to larger lifts of 300+ tons; all done safely as planned and scheduled by the yard.

The helicopter deck was set and secured (crane released for other work) in record time - less than one work shift. New forward and aft lifeboat decks were set and secured in less than one shift, as safety, planning, engineering and production personnel cooperated to expedite the tasks.
 
To meet the customer’s requirements, all pipe systems were re-newed, modified or completely replaced and tested, and the complete renewal of the rig’s HVAC systems. The entire electrical system on the Frontier Driller was completely re-powered, including all four mains all new SCR and MCC and switchboards and 100% new cable. All columns, under deck, exterior and interior spaces were cleaned and painted in accordance with industry practices.

The final phase of this project consisted of fabricating and installing one thousand tons of steel, adding two pontoon sponsons and four columns to the huge rig in 61 days. Signal fabricated one new column, while subcontracting and managing the fabrication of the remaining components. The three fabricated columns were each received in three unfinished sections. Each column was assembled and outfitted with ladders, man-ways and vent piping, then blasted and painted internally and externally in accordance with client specifications.

Maritime Reporter August 2014 Digital Edition
FREE Maritime Reporter Subscription
Latest Maritime News    rss feeds

Offshore

Halliburton to Settle US Gulf Spill Claims for $1.1b

Halliburton Co said it reached a $1.1 billion settlement for a majority of claims against the company for its role in the BP oil spill in the Gulf of Mexico in 2010.

RDS Wins Engineering and Design Contract for Sea Lion

Rig design and engineering specialist RDS has been awarded a front-end engineering design (FEED) contract by AMEC for Premier Oil’s Sea Lion development in the North Falklands Basin.

Joe Barton: Lift Oil Export Ban

A senior U.S. Congressman from Texas has come out in full support of the United States lifting the 40-year old ban on crude oil exports, putting him at odds with

 
 
Maritime Contracts Maritime Security Naval Architecture Navigation Pipelines Pod Propulsion Port Authority Salvage Ship Repair Sonar
rss | archive | history | articles | privacy | terms and conditions | contributors | top maritime news | about us | copyright | maritime magazines
maritime security news | shipbuilding news | maritime industry | shipping news | maritime reporting | workboats news | ship design | maritime business

Time taken: 0.1439 sec (7 req/sec)