Gjøa Gets its Sea Legs

Tuesday, December 29, 2009
Photo courtesy Statoil

During the last few days the deck and hull of the Gjøa platform have been mated together in the fjord outside the Norwegian town of Stord. There were exacting requirements for precision and weather conditions during the operation, which was a success.

The four-legged hull rose from the sea in the sea off Stord and spiked the deck of the new North Sea giant, Gjøa. Four guide pins had to meet their respective slots in a deck the size of a football field, with a tolerance of just 1 inch in all directions.

The guide pins are designed to take the load should the platform list, so that it can be towed to shore before the deck is welded to the hull, allowing mechanical testing and commissioning of the platform to start sooner.

During the night, the ballast tanks in the hull were filled with water in order to submerge the structure to a depth of 115 ft. Only 16.5 ft of the hull protruded from the water when the barge carrying the platform deck was towed from the quay. The barge carrying the platform deck was maneuvered into place between the columns of the hull.

Slowly but surely, the ballast water was discharged; the hull rose towards the deck and they were mated into one. When the operation was completed, the draught of the hull was 42.6 ft. The mated platform was then towed to the quay, so that the work of mechanical completion could continue.

“I am impressed by this operation. It was well-planned, safe and efficient and carried out with the utmost precision,” says Kjetel Rokseth Digre, project manager for Gjøa.

The mating was carried out by Aker Stord, who are constructing the platform for Statoil.
During the past couple of months, more than 2,000 people have worked continuous shifts on Gjøa in order to make it ready for towing to the field in April. By carrying out the mating between Christmas and New Year when most workers are on vacation, a large number of inoperative staff onshore has been avoided.

“It was extremely important for us to get this done now. We now have a complete platform structure to work on, and we are doing everything in our power to get Gjøa ready by the agreed date,” said Digre.

Statoil is operator during the development phase of the Gjøa field. The plan is for the platform and the field to be handed over in October 2010, to GDF Suez E&P Norge AS, who will be operator during the production phase. Gjøa will be GDF Suez’s first operatorship for a field in operation.

Maritime Reporter October 2015 Digital Edition
FREE Maritime Reporter Subscription
Latest Maritime News    rss feeds


US Senators Introduce Bill to Limit Offshore Drilling

A group of U.S. Senators on the West Coast have introduced a bill Wednesday aiming to prohibit offshore drilling on the outer continental shelf of California, Oregon and Washington.

Danish-South Korean Co-operation Strengthened

The Danish-South Korean Green Growth Alliance met for roundtable talks yesterday. The Minister for Business and Growth's meeting with the South Korean Minister

Seadrill Hopes to See Market Turn in 2017

Offshore rig driller Seadrill is facing another two years in the doldrums but hopes the international rig market could turn around in 2017.   Rig rates have more

Maritime Careers / Shipboard Positions Maritime Standards Naval Architecture Offshore Oil Port Authority Ship Electronics Ship Repair Shipbuilding / Vessel Construction Sonar Winch
rss | archive | history | articles | privacy | contributors | top maritime news | about us | copyright | maritime magazines
maritime security news | shipbuilding news | maritime industry | shipping news | maritime reporting | workboats news | ship design | maritime business

Time taken: 0.2645 sec (4 req/sec)