Gjøa Hull Safely Through Gulf of Aden

Sunday, September 20, 2009
Photo courtesy StatoilHydro

The hull of the North Sea Gjøa platform is on its way to Norway from the Samsung shipyard in South Korea. At the weekend an EU naval force provided a military escort as the hull passed through the notorious Gulf of Aden.

The result of 1.7 million hours worked in South Korea, the Gjøa platform hull is now on its way to Stord via the Suez Canal.

The long voyage to Stord is estimated to take 40-45 days. At the weekend the hull was transported through the Gulf of Aden, where shipping has recently been subject to attacks by Somali pirates who hijack vessels.

This particular transport was given a high-priority classification due to its vulnerability and importance. The vessel is slow-moving and lies low in the water, making it easy to board. StatoilHydro and subcontractor Dockwise were therefore given a military escort through the Gulf of Aden by the EU forces in the area. The escort was initially undertaken by the Belgian frigate Louise-Marie, and then by the Swedish corvette Malmø.

“The protection we were given in the form of a dedicated escort was crucial to being able to, and wanting to pass through the Gulf at this time. We are very pleased with the cooperation we have enjoyed with the authorities and with the protection provided by the Belgian and Swedish vessels,” said Kjetel Rokseth Digre, director for the Gjøa construction project.

The development of Gjøa, Vega and Vega Sør, which is currently the biggest development project on the Norwegian continental shelf, is opening up a new part of the North Sea for oil and gas production. Vega and Vega Sør will be developed using subsea installations connected to the Gjøa platform.

The hull now on its way to Stord is one of the major building bricks on the project. After arrival it will be moored until Christmas while awaiting assembly with the topsides.
 

Maritime Reporter October 2014 Digital Edition
FREE Maritime Reporter Subscription
Latest Maritime News    rss feeds

Offshore

Fourth Rig Delivered to Perforadora Central

Keppel AmFELS LLC, a wholly owned US subsidiary of Keppel Offshore & Marine Ltd (Keppel O&M), has delivered the jackup rig, Coatzacoalcos, to Mexico’s Central Panuco S.

Woodside to Pick up Moroccan Acreage

Woodside advises that it has entered into a contract for an exclusive Reconnaissance Licence (RL) with the Office National des Hydrocarbures et des Mines, the

Strategy Can Maximize UKCS potential

Companies operating in the North Sea require a cultural shift to make the most of the its potential, according to a new report from Deloitte, the business advisory firm.

Maritime Security

Subsea Defense & the Changing Paradigm of Submarine Programs

Technology and dynamic mission profiles have driven change in the defense industry, Hydro Group Plc Managing Director Doug Whyte, explores the changing paradigm of submarine programs,

Bollinger Delivers 11th FRC to the US Coast Guard

Bollinger Shipyards, Inc. has delivered the William Trump, the 11th Fast Response Cutter (FRC) to the United States Coast Guard.   The announcement was made by Bollinger Chief Operating Officer,

US Navy Evaluating SEWIP for LCS

The U.S. Navy is evaluating a scaled-down version of the Surface Electronic Warfare Improvement Program (SEWIP) system for potential incorporation on future Littoral Combat Ships (LCS),

 
 
Maritime Careers / Shipboard Positions Maritime Contracts Maritime Security Maritime Standards Naval Architecture Navigation Pipelines Port Authority Ship Electronics Ship Repair
rss | archive | history | articles | privacy | terms and conditions | contributors | top maritime news | about us | copyright | maritime magazines
maritime security news | shipbuilding news | maritime industry | shipping news | maritime reporting | workboats news | ship design | maritime business

Time taken: 0.1167 sec (9 req/sec)