Graig Supervises Building of Wind Power Installation Vessel

Monday, November 12, 2001
Graig Shipping has provided a full support package for the supervision of the building of the first of a series of unique high technology Wind Turbine Installation Vessels. The 130 metre long vessels bring together proven technologies to provide a system which will support a new offshore industry, harnessing wind power for electricity generation.

Working with Graig's advice and support, UK-based engineering firm Mayflower Energy Ltd has ordered one ship and has an option for a second vessel from China's Shanhaiguan yard. "Chinese shipyards are now first choice for new vessel types," says Hugh Williams, CEO of Graig. "Not only are they competitive on pricing, but they are flexible and willing to adapt to new technology and new designs. We are very happy that we have been able to help Mayflower find the right yard, the right designer and the right classification society to get this new offshore industry off to a good start." Graig advised Mayflower on choice of yards, introduced Denmark's Knud E Hansen as the designer and DNV as a suitable class society, and assisted in yard negotiations. Graig's China-based supervision team will now oversee the building and delivery of the first vessel, which is due to enter service in February 2003.

"The UK government has plans which will require the installation of 1,300 new 2MW offshore turbines over the next ten years," says David Donnelly, Chairman of Mayflower Energy. "There are also plans for major installations around other European coasts. We expect demand for this type of specialist vessel to be very high, and we are happy that Graig has helped us to contract with a Chinese shipyard for the construction of this technologically advanced vessel to install the turbines."

The TIV-I vessels will be 130.5m loa, 38 m beam, and will be equipped with six jack up legs, a 300 tonne crane and a 50 tonne crane. Capable of carrying and installing ten turbines and housing a full engineering crew of up to fifty persons, the vessels will be powered by four 1.5 MW thrusters, giving a sea speed of 10.5 knots. To be flagged in the Isle of Man, the vessel will be classed DNV +1A1, self elevating Units.

Maritime Reporter February 2015 Digital Edition
FREE Maritime Reporter Subscription
Latest Maritime News    rss feeds

Technology

COMPIT to Showcase Smarter Ships, Systems & Solutions

The 14th International Conference on Computer and IT Applications in the Maritime Industries (COMPIT) will take place from 11th to 13th May 2015 in Ulrichshusen, Germany.

China's Maritime Advances Worry US

The Director of U.S. National Intelligence, James Clapper, has expressed his concern at the progress of China in maritime zones it shares with its neighbors, accused

Davie Building LNG-powered Ferries

Canadian shipbuilder Davie held a keel laying ceremony for MV Armand-Imbeau II, marking the beginning of the hull assembly for this first of two sisterships under

Coatings & Corrosion

Tall Ship Docked for Repairs

The largest brig to be built in the U.K. in a century sailed into in a Greenock dry dock yesterday for general maintenance and essential winter repairs.   The

 
 
Maritime Careers / Shipboard Positions Maritime Security Maritime Standards Naval Architecture Navigation Pipelines Port Authority Salvage Ship Electronics Shipbuilding / Vessel Construction
rss | archive | history | articles | privacy | terms and conditions | contributors | top maritime news | about us | copyright | maritime magazines
maritime security news | shipbuilding news | maritime industry | shipping news | maritime reporting | workboats news | ship design | maritime business

Time taken: 0.1115 sec (9 req/sec)