Graig Supervises Building of Wind Power Installation Vessel

Monday, November 12, 2001
Graig Shipping has provided a full support package for the supervision of the building of the first of a series of unique high technology Wind Turbine Installation Vessels. The 130 metre long vessels bring together proven technologies to provide a system which will support a new offshore industry, harnessing wind power for electricity generation.

Working with Graig's advice and support, UK-based engineering firm Mayflower Energy Ltd has ordered one ship and has an option for a second vessel from China's Shanhaiguan yard. "Chinese shipyards are now first choice for new vessel types," says Hugh Williams, CEO of Graig. "Not only are they competitive on pricing, but they are flexible and willing to adapt to new technology and new designs. We are very happy that we have been able to help Mayflower find the right yard, the right designer and the right classification society to get this new offshore industry off to a good start." Graig advised Mayflower on choice of yards, introduced Denmark's Knud E Hansen as the designer and DNV as a suitable class society, and assisted in yard negotiations. Graig's China-based supervision team will now oversee the building and delivery of the first vessel, which is due to enter service in February 2003.

"The UK government has plans which will require the installation of 1,300 new 2MW offshore turbines over the next ten years," says David Donnelly, Chairman of Mayflower Energy. "There are also plans for major installations around other European coasts. We expect demand for this type of specialist vessel to be very high, and we are happy that Graig has helped us to contract with a Chinese shipyard for the construction of this technologically advanced vessel to install the turbines."

The TIV-I vessels will be 130.5m loa, 38 m beam, and will be equipped with six jack up legs, a 300 tonne crane and a 50 tonne crane. Capable of carrying and installing ten turbines and housing a full engineering crew of up to fifty persons, the vessels will be powered by four 1.5 MW thrusters, giving a sea speed of 10.5 knots. To be flagged in the Isle of Man, the vessel will be classed DNV +1A1, self elevating Units.

Maritime Reporter April 2015 Digital Edition
FREE Maritime Reporter Subscription
Latest Maritime News    rss feeds

Technology

Chinese Submarine to Pakistan: Raising Nuclear Tensions in South Asia

Pakistan, a country plagued by economic and political insecurity, to conclude the deal of eight conventional submarines during Chinese President Xi Jinping's visit to Islamabad on Monday (April 20),

Variable Bore Rams is 35

Variable Bore Rams, Inc. (VBR), one of the largest original equipment manufacturer (OEM) ram and BOP component providers in the world, is celebrating its 35th

Taylor to Chair NOIA Board

The National Ocean Industries Association (NOIA) Board of Directors has elected Cindy B. Taylor as Chair and Kevin McEvoy as Vice Chairman for the upcoming 2015-2016 term.

Coatings & Corrosion

Hempel CEO Jullien Plans Retirement

Pierre-Yves Jullien, CEO of Hempel A/S since 2005, has decided to retire after nearly 40 years in the Group. He will step down from his role as CEO on March 31, 2016 at the latest.

AIDA Cruises’ New Flagship Receives Signature Paint Job

At the Mitsubishi shipyard in Nagasaki, Japan, the new flagship of AIDA Cruises is now receiving its beaming smile.   At the end of March, preparatory work began

 
 
Maritime Standards Naval Architecture Navigation Pipelines Pod Propulsion Port Authority Salvage Ship Electronics Ship Repair Ship Simulators
rss | archive | history | articles | privacy | contributors | top maritime news | about us | copyright | maritime magazines
maritime security news | shipbuilding news | maritime industry | shipping news | maritime reporting | workboats news | ship design | maritime business

Time taken: 0.1092 sec (9 req/sec)