Panama Canal PAC-4 Work Begins

Tuesday, January 26, 2010

Work on the second largest contract of the Panama Canal Expansion Program has begun. The Panama Canal Authority (ACP) issued consortium FCC-ICA-Meco the Notice to Commence the fourth and final dry excavation (PAC-4) contract.

PAC-4 is the most complex expansion project after the design and build of the new set of locks. The dry excavation included in PAC-4 will create an access channel linking the new Pacific locks with the Canal's existing Gaillard Cut (the narrowest stretch of the Panama Canal).

The ACP awarded the PAC-4 contract to FCC-ICA-Meco, a Spanish, Mexican and Costa Rican joint venture, following the consortium's lowest bid submission of $267.8m and its compliance with the requirements established in the request for proposal specifications. The ACP issued the Notice after receiving FCC-ICA-Meco's performance and payment bonds and signing the contract.

The scope of work will include 26 million cubic meters of unclassified excavation, the installation of a backfilled cellular cofferdam water barrier and the construction of an earth-rock filled dam that will create part of the access channel's eastern bank. The work is scheduled to conclude during the third quarter of 2013.

Expansion will build a new lane of traffic along the Panama Canal through the construction of a new set of locks which will double capacity and allow more traffic and longer, wider ships.

Maritime Today


The Maritime Industry's original and most viewed E-News Service

Maritime Reporter July 2016 Digital Edition
FREE Maritime Reporter Subscription
Latest Maritime News    rss feeds

News

Cambodia Urged ASEAN to Avoid Words That Escalate Tension

Cambodia advised a grouping of South East Asian nations to avoid using words that "would escalate tension between China and the Philippines" in a weekend statement,

Technip Bags Woodside's Subsea Contract

Technip has been awarded a large(1) subsea contract by Woodside to support the development of the Greater Enfield Project offshore Western Australia, at a water

Keel Laying for Russia's Second Nuclear Icebreaker

Today the Baltic Shipyard in St Petersburg (part of United Shipbuilding Corporation) laid the keel of Ural, Project 22220’s second series-produced nuclear icebreaker.

 
 
Maritime Careers / Shipboard Positions Maritime Contracts Maritime Security Maritime Standards Naval Architecture Navigation Salvage Ship Repair Sonar Winch
rss | archive | history | articles | privacy | contributors | top maritime news | about us | copyright | maritime magazines
maritime security news | shipbuilding news | maritime industry | shipping news | maritime reporting | workboats news | ship design | maritime business

Time taken: 0.0796 sec (13 req/sec)