Panama Canal PAC-4 Work Begins

Tuesday, January 26, 2010

Work on the second largest contract of the Panama Canal Expansion Program has begun. The Panama Canal Authority (ACP) issued consortium FCC-ICA-Meco the Notice to Commence the fourth and final dry excavation (PAC-4) contract.

PAC-4 is the most complex expansion project after the design and build of the new set of locks. The dry excavation included in PAC-4 will create an access channel linking the new Pacific locks with the Canal's existing Gaillard Cut (the narrowest stretch of the Panama Canal).

The ACP awarded the PAC-4 contract to FCC-ICA-Meco, a Spanish, Mexican and Costa Rican joint venture, following the consortium's lowest bid submission of $267.8m and its compliance with the requirements established in the request for proposal specifications. The ACP issued the Notice after receiving FCC-ICA-Meco's performance and payment bonds and signing the contract.

The scope of work will include 26 million cubic meters of unclassified excavation, the installation of a backfilled cellular cofferdam water barrier and the construction of an earth-rock filled dam that will create part of the access channel's eastern bank. The work is scheduled to conclude during the third quarter of 2013.

Expansion will build a new lane of traffic along the Panama Canal through the construction of a new set of locks which will double capacity and allow more traffic and longer, wider ships.

Maritime Reporter October 2014 Digital Edition
FREE Maritime Reporter Subscription
Latest Maritime News    rss feeds

News

Update: Explosion in the Gulf of Mexico

An explosion occurred aboard a production platform Thursday at West Delta 105, operated by Fieldwood Energy, resulting in one fatality and three injured. The Bureau

Bouchard Vessels Honored by SCA

Forty-three Bouchard Transportation Co., Inc. vessels have been honored by The Chamber of Shipping America (CSA) with Certificates of Environmental Achievement.

Cost to Fuel Ships Falls

For a ship that burns 24 tonnes of fuel per day while steaming, fuel costs are reduced by as much as $1 million a year if current price level stay put. Assuming

 
 
Maritime Careers / Shipboard Positions Maritime Security Maritime Standards Navigation Offshore Oil Port Authority Salvage Ship Electronics Shipbuilding / Vessel Construction Sonar
rss | archive | history | articles | privacy | terms and conditions | contributors | top maritime news | about us | copyright | maritime magazines
maritime security news | shipbuilding news | maritime industry | shipping news | maritime reporting | workboats news | ship design | maritime business

Time taken: 0.1874 sec (5 req/sec)