Signal Completes Upgrade of The Noble Homer Ferrington

Tuesday, December 07, 2004
Signal International, LLC has completed a major refurbishment and upgrade of Noble Drilling’s Homer Ferrington semi-submersible drilling rig. The work was completed at Signal International’s East Facility in Pascagoula, Miss.

Prefabrication started in February 2004 in anticipation of the rig’s arrival in July. The drill-ready rig departed on schedule and within budget after 109 working days.

The scope of work included:

· Fabrication and installation of fully outfitted main, mid and upper deck extensions

· Fabrication and installation of a forward and aft lifeboat platform

· Fabrication, installation and outfitting of a 42 person, 3 level quarters addition

· Installation of 2 each 60’ center column blisters

· Removal of the existing helideck and replacement with an upgraded new unit

· Total steelwork, included: removals - 200 tons, fabrication - 280 tons, installation - 530 tons

· Scaffolding, containment, blasting and painting under main deck, columns and diagonal braces

· Installation and connection of fourth mud pump

· Provision of full project electrical support (- more -)

· Prefabrication and installation of:

· New riser tensioner system

· Flare boom piping and new flare boom

· Complete zero discharge piping system and misc. piping systems

· Load-out and tie-down of the rig on a heavylift transport vessel Planning, organizing and controlling of the project were executed through a fully integrated (customer/contractor/subcontractor) process. This resulted in the on-time and on-budget delivery of a world-class high-performance mobile offshore drilling unit.

Maritime Reporter October 2014 Digital Edition
FREE Maritime Reporter Subscription
Latest Maritime News    rss feeds

Ship Repair & Conversion

Seaspan Shipyard's Prompt Response to Canadian Coast Guard

Seaspan Shipyard’s long-standing relationship with the Canadian Coast Guard was proudly showcased in recent days, with simultaneous repair and maintenance work

Energy Storage System Ordered for LNG Battery Hybrid Ferry

Norwegian hybrid to be the first LNG battery ferry to operate on commercial routes Corvus Energy, Siemens AS and Fjord1 have announced the award of the contract for the Fannefjord LNG hybrid ferry.

N-KOM Recognized for Shipyard Safety, Security

Nakilat-Keppel Offshore & Marine (N-KOM) received the Safety & Security Award at the inaugural edition of The Maritime Standard (TMS) Middle East & Indian Subcontinent Awards,

Environmental

Deepwater Semi-Sub COSL Prospector Delivered

COSLProspector, the fourth deep-water semi-submersible drilling rig built by CIMC Raffles for China Oilfield Services Limited (COSL), has been delivered in Yantai, Shandong Province.

New Tidal Wave Energy Device Completes Sea Trials

In the continuing quest to harvest efficient, renewable energy from the power of the world’s tides, an organization called Sustainable Marine Energy’s announced

Europe Stockpiling Low Cost, Surplus LNG

Demand from top Asian buyers drops sharply; Asian, European gas price spreads converge. Europe set to becoming dumping ground for LNG. Europe is set to become

 
 
Maritime Careers / Shipboard Positions Maritime Security Maritime Standards Navigation Offshore Oil Pipelines Pod Propulsion Port Authority Shipbuilding / Vessel Construction Winch
rss | archive | history | articles | privacy | terms and conditions | contributors | top maritime news | about us | copyright | maritime magazines
maritime security news | shipbuilding news | maritime industry | shipping news | maritime reporting | workboats news | ship design | maritime business

Time taken: 0.1975 sec (5 req/sec)