W&D Raises New Facility After Fire

Tuesday, October 14, 2008

October 11, 2008, marks three months since a fire destroyed Washburn & Doughty’s building and the yard is pleased to announce that progress on clean-up and construction is moving steadily ahead.

The Sheridan Corporation of was awarded the contract to construct Washburn & Doughty’s new facility. has begun to pour concrete for the foundation and steel for the new building has begun to arrive. Phase 1 of the project, which is the 185’ x 80’ , is scheduled for completion at the end of 2008.

After extensive surveys, it was determined that much of 94, a 121’Intercon Tug in the building at the time of the fire, was salvageable. Notably, the engine room was spared the brunt of the fire’s heat and machinery in this space emerged with only minor damage. This area stayed relatively cool due to the fact that the engine room sides and bottom are isolated from exterior spaces by wing tanks and inner-bottom tanks. To maintain full warranties, all machinery and equipment are being surveyed and reconditioned as necessary by their manufacturers.

In addition, a crew from Amex is currently sandblasting and priming the hull to return it to pre-fire condition. Washburn & Doughty personnel will resume construction once this work is complete, which is scheduled for the week of Oct. 13.

Hull 95, a 92’ Z Drive Tug in the building at the time of the fire, suffered significantly more damage. Plywood in the engine room fueled the fire in that area, damaging machinery beyond repair.  Furthermore, when the keel blocks burned out from underneath this vessel, it settled on its bow creating serious distortion in the hull and 30’ of keel. Despite this damage, certain units are salvageable and personnel are currently making this determination.

Hulls 96 and 97, two 98’ Z Drive Tugs, are underway to the east of Washburn & Dought’s former building. Harry C. Crooker & Sons, Inc. quickly leveled this site to expedite construction and the project got a jump-start by fabricating units off-site at Northeast Doran of Skowhegan, .

Maritime Reporter June 2014 Digital Edition
FREE Maritime Reporter Subscription
Latest Maritime News    rss feeds

People & Company News

Panama's Alfonso Castillero Moves to Liberian Registry

The Liberian Registry informs that Alfonso Castillero, former Director-General of the Panama Registry, has joined their organization as Vice-President. Castillero

Bulk Grain Carrier Aground in Lake St. Claire

The Coast Guard informs it is responding to a 36,563 dwt 656-foot freighter that is hard aground in the downbound shipping channel of Lake St. Clair. Coast Guard

Costa Concordia Arrives Genoa for Demolition

Crowley Maritime Corp. subsidiary TITAN Salvage and project partner Micoperi has confirmed that the Costa Concordia – the Concordia-class cruise ship that wrecked off Giglio Island,

 
 
Maritime Careers / Shipboard Positions Maritime Standards Naval Architecture Offshore Oil Pod Propulsion Port Authority Salvage Ship Electronics Ship Repair Ship Simulators
rss | archive | history | articles | privacy | terms and conditions | contributors | top maritime news | about us | copyright | maritime magazines
maritime security news | shipbuilding news | maritime industry | shipping news | maritime reporting | workboats news | ship design | maritime business

Time taken: 0.2238 sec (4 req/sec)