Ship Agents Count the Cost of Avoidable Errors

Press Release
Monday, November 12, 2012

International Transport Intermediaries Club (ITIC) has emphasised how avoidable errors can prove expensive for ship agents.



In the latest issue of its Claims Review, ITIC recounts how a ship agent at a tidal port in Japan was asked to provide a tide table to enable the owner of a ship to calculate the permissible drafts for the dates that its ship was due to berth at the port. The ship agent duly scanned the tide table and sent it electronically to the owner. The ship arrived at the port with a draft of 8.56 m, but was informed by the port authorities that the permissible draft was only 7.8 m.



It emerged that the agent had inadvertently sent the owner the tide table for 2012 instead of 2011. The two tide tables were kept together in the same file and, during the scanning process, the corner of the tide table had folded over, thereby obscuring the year. The excess draft meant that the ship could only discharge for about four hours in the morning and two hours in the afternoon. The ship had to shift anchorage three times during the four days it took to discharge, which was twice as long as it should have taken.



The owner claimed the pilotage and towage costs involved in shifting to the anchorage three times, plus two days’ hire, additional bunker consumption, and additional stevedoring, for a total of $143,000. It was agreed by the owner that some of the costs would have been incurred in any event, and the claim for additional costs was settled at $120,000.



In another case reported by ITIC, shipowners appointed a port agent for a bunker call by their vessel. The agent failed to complete the required customs formalities in time to book the berth, a mistake which went unnoticed until the vessel was approaching the port. After being notified by the agent of the mistake, the shipowner decided to divert the vessel to another port around 500 km north of the original port as the bunker berth at the first port was not due to become free for another five days. The ship agent also operated within the second port and the bunkering proceeded without incident.



When the time came to settle invoices totalling $26,000 from the various service providers in the second port, the owners refused to pay, claiming that these additional costs had been incurred as a result of not being able to call at the original port. The costs were in fact the normal charges relating to bunker calls, such as tugs, security charges and pilotage, and would have been payable by the owners in any event, even if the vessel had been able to call at the original port. However, the vessel had been delayed by two days and it had incurred estimated costs that exceeded this amount for fuel and other services, as a result of having to travel 500 km to the second port.



Rather than enter into a dispute with the owners, the ship agent paid the port costs for the bunker call, and was reimbursed by ITIC.
    

 

Maritime Reporter October 2013 Digital Edition
FREE Maritime Reporter Subscription
Latest Maritime News    rss feeds

People & Company News

Henderson, Hanes & Associates Opens Doors in Miami

Ocean Engineering/ Naval Architecture Firm Brings Innovation to the Mega Yacht Community The Miami-based ocean engineering and naval architecture firm of Henderson & Associates, Inc.

DOF Installer Sells Offshore Vessel

DOF Subsea AS subsidiary, DOF Installer ASA, reported the sale of one of its three sister ships, an anchor handling tug supply (AHTS) vessel, to an international buyer.

Scanjet Secures 30-ship Tank Management Order

Scanjet Group has followed up its Tank Management order from Stolt-Nielsen with a series of contracts for its ITAMA Intelligent Tank Management concept including Tankcleaning,

Ports

Port City Plans for New Cargo Taxes Angers Kenya Govt, Shippers

Proposals by a local authority to impose new taxes on cargo at Kenya's main port has drawn opposition from the government and shippers, saying it will hike import

DP World Mulls Senegal Free Zone

DP World  is looking to develop a free zone in Senegal, Chairman Sultan Ahmed bin Sulayem said on Wednesday. Sulayem was speaking at an African investment event in Dubai.

Skangass Builds LNG Terminal in Pori, Finland

With investment support from the Finnish Government of 185 million NOK Skangass has decided to build a new import terminal for LNG. The terminal will be completed in 2016.

Maritime Safety

US Aircraft Carrier Crew Rescues Fishermen

Sailors and Marines aboard the U.S. Navy aircraft carrier USS Theodore Roosevelt (CVN 71) assisted two fishermen aboard a fishing vessel engulfed in flames off the east coast of Florida, Sept.

NAVTOR, AWT Agreement Marks Next Step in E-navigation

NAVTOR has signed an agreement with maritime weather routing specialist Applied Weather Technology (AWT) that will see the two companies integrating their services

Maritime Reporter @ 75: The Daily Cartoon

Maritime Reporter & Engineering News was founded by John J. O'Malley (1905-1980) in 1939, and today ranks as the world's largest audited trade publication in the world serving the maritime industry,

Vessels

Austal Launches Trenton (JHSV 5)

Second Joint High Speed Vessel to be launched at Austal in 2014 On September 30, 2014, Austal USA successfully completed the launch process of Trenton (JHSV

DOF Installer Sells Offshore Vessel

DOF Subsea AS subsidiary, DOF Installer ASA, reported the sale of one of its three sister ships, an anchor handling tug supply (AHTS) vessel, to an international buyer.

Chinese Manufacturing Expansion Affects Shipping Demand

The expansion of the Chinese Manufacturing Industry continued in September at unchanged pace as compared to the month before, BIMCO reports. The manufacturing industry

Insurance

YoungShip Young Corporation Award 2014

For its efforts to promote young employee development, marine insurer GARD has been awarded the 2014 YoungShip Young Corporation Award. The shipping industry

Coast Guard: Investigations Underway in Cutter Collision

The Coast Guard is conducting a series of formal investigations after Tuesday’s collision involving a Coast Guard cutter and a fishing vessel off the coast of Puerto Rico.

P&I Clubs

Coast Guard: Investigations Underway in Cutter Collision

The Coast Guard is conducting a series of formal investigations after Tuesday’s collision involving a Coast Guard cutter and a fishing vessel off the coast of Puerto Rico.

The Great Lakes Ballast Water Challenge Explained

Skuld P&I Club in a members advisory explores the regulatory framework and practical issues that exist in both Canada and the USA with input from BLG of Montreal and Chalos & Co of New York.

Consulting

DMR Examines Container Terminal Congestion Issues

Container port congestion has been hitting the headlines recently, but the reasons for it vary widely and in many cases it is only a short term issue. Certain world

IMO Takes Important Step Towards Electronic Certificates

In the future, the IMO member States should accept the use of electronic certificates. This is the request of the Facilitation Committee (FAL) and, hence, the road is paved for less paperwork,

ISS Chile Advising on Oil spill at Quintero Bay

Inchcape Shipping Services (ISS) Chile is advising of an oil spill at Quintero Bay, Nr Valparaiso, Chile, following an incident on Thursday 24th September at

 
 
Maritime Careers / Shipboard Positions Maritime Contracts Maritime Standards Naval Architecture Navigation Pipelines Pod Propulsion Port Authority Shipbuilding / Vessel Construction Winch
rss | archive | history | articles | privacy | terms and conditions | contributors | top maritime news | about us | copyright | maritime magazines
maritime security news | shipbuilding news | maritime industry | shipping news | maritime reporting | workboats news | ship design | maritime business

Time taken: 0.4521 sec (2 req/sec)