Challenges in the FPSO Supply Chain: Round Table

By George Backwell
Monday, June 30, 2014
FPSO: File photo

FPSOs play a key role in deepwater oil and gas production. A 'DW Monday' analysis of FPSO projects found cost overruns of nearly 40% and average project delays exceeding one year for some. In response to this DW recently brought together 20 companies from across the FPSO supply chain in a round table session to identify the challenges facing the sector:

  • Capital cost escalation: “Where you do save is to look at the whole development, not just the production system” – Major E&P Company
  • Variance in guidelines from operators: “There are so many standards and requirements that this drives the cost up considerably” – EPC Contractor
  • Variance in regulations worldwide: “US regulation requirements in the Gulf are a driving factor behind cost increases” – Equipment Supplier
  • Poor presentation of specification by operators: “Requirements are presented in stacks of documents. This is very difficult for contractors to deal with and makes the process side of the business much more expensive” – Major E&P Company
  • Over-engineering and scope creep: “Scope creep happens all the time in every project. This may be necessary but it will always delay the construction process” – Shipyard
  • Supply chain concerns: “It’s a highly complicated supply chain, [but] major clients that come to us understand the problems” – FPSO Leasing Contractor
  • Local content requirements: “Changing of specifications [for] local content are major concerns. Local content is an understandable requirement but partners need to be consistent” – Offshore Contractor
  • Contracting challenges: “Nobody else signs 15 year contracts. We don’t enjoy the upside when rates are high and operators complain when we demand higher dayrates at the end of the contract” – FPSO Leasing Contractor

The team also identified potential solutions to these challenges – which they will discuss in the next 'DW Monday'.

Douglas-Westwood's  earlier paper 'FPSO Industry Must Re-Think Supply Chain' is at: http://bit.ly/TIRrul

Source: DW Monday

Maritime Reporter April 2015 Digital Edition
FREE Maritime Reporter Subscription
Latest Maritime News    rss feeds

People & Company News

BIMCO Welcomes EU Decision on Migrants

BIMCO has stated today that it appreciates the new efforts by EU leaders to reduce increasing reliance on merchant shipping to rescue the growing numbers of

Long Beach, Los Angeles ports host forum to gather input

More than 100 cargo owners, trucking firm leaders, longshore labor, marine terminals and other goods movement industry representatives turned out Wednesday for

Arctic Nations to Fight Climate Change Despite Russia Tensions

The eight Arctic Council nations pledged on Friday to do more to combat climate change that is shrinking the vast frigid region, with countries trying to put

Offshore

Falklands' Oil Drilling at Isobel Deep Suspended

Oil explorers drilling in the waters north of the Falkland Islands have suspended work on the second well of their 2015 current six-well drilling campaign after a technical problem.

Arctic Nations to Fight Climate Change Despite Russia Tensions

The eight Arctic Council nations pledged on Friday to do more to combat climate change that is shrinking the vast frigid region, with countries trying to put

OSV Technology: Notable Designs & Deliveries

Though the market for Offshore Support Vessels (OSVs) is soft, advances in technology, fit and finish in  the sector is unrivaled in any other maritime niche over the past five years.

Naval Architecture

OSV Technology: Notable Designs & Deliveries

Though the market for Offshore Support Vessels (OSVs) is soft, advances in technology, fit and finish in  the sector is unrivaled in any other maritime niche over the past five years.

Incat Crowther Designs Commercial Security Vessel

Incat Crowther has received a contract to design an offshore commercial oilfield security vessel for Veecraft Marine and its client, UTM Dredging Ltd, the designer announced today.

SDARI Inks Agreement for INTERSCHALT Loading Software

INTERSCHALT maritime systems AG, a maritime software and services provider of loading computers on board containerships, signed a cooperation agreement with the

Consulting

Long Beach, Los Angeles ports host forum to gather input

More than 100 cargo owners, trucking firm leaders, longshore labor, marine terminals and other goods movement industry representatives turned out Wednesday for

Salvage and Wreck Removal Conference

HINODE Events and Services Pvt Ltd., have announced the 4th Annual Conference on Salvage and Wreck Removal in India to be held on Wednesday, July 8, 2015 at Visakhapatnam on India's East Coast.

Technip dividend FY 2014

At the Annual General Meeting, held today, Technip’s shareholders approved the proposed €2.00 per share dividend for the 2014 financial year and decided to offer

Offshore Energy

Falklands' Oil Drilling at Isobel Deep Suspended

Oil explorers drilling in the waters north of the Falkland Islands have suspended work on the second well of their 2015 current six-well drilling campaign after a technical problem.

Four Petrobras Platforms Halt Output Due to Oil Leak

Four Petrobras oil platforms off the northeast coast of Brazil have halted production after a leak of about 7,000 liters of oil was detected coming from a pipeline linking them,

Huat Retires as Non-Ex Dir. of ST Engineering

Singapore Technologies Engineering Ltd (ST Engineering) today announced the retirement of Mr Quek Poh Huat as non-executive Director of the Company at its Annual General Meeting on 23 April 2015.

 
 
Maritime Careers / Shipboard Positions Maritime Contracts Naval Architecture Pod Propulsion Port Authority Salvage Ship Simulators Shipbuilding / Vessel Construction Sonar Winch
rss | archive | history | articles | privacy | contributors | top maritime news | about us | copyright | maritime magazines
maritime security news | shipbuilding news | maritime industry | shipping news | maritime reporting | workboats news | ship design | maritime business

Time taken: 0.1650 sec (6 req/sec)