Harris Pye Completes Brazilian Offshore Project

press release
Thursday, February 23, 2012

In just 90 days, the Harris Pye Group successfully completed the survey and upgrade of Diamond Offshore Drilling Inc’s (DODI) dynamically positioned drillship, the Ocean Clipper. All work was completed within schedule.


Totalling 247,235 man hours and utilising a 600-plus workforce, the contract was one of the largest offshore oil and gas projects for the South Wales headquartered company.  Despite the time-critical schedule, extraordinarily high man hours and large workforce, safety standards were superb and there were no serious accidents or injuries to any personnel. The upgrade encompassed accommodation, cranes, steelwork (for which 250 tons of steel were supplied); major pipe renewal in excess of 2 miles (3225metres) of piping); painting; and the removal and replacement of transformers and motors; and four major electrical tasks along with many other, not necessarily less complex, but smaller electrical tasks.  Activity was split between dry dock and alongside.


A highly comprehensive list of tasks successfully completed within a tight schedule:


• New watertight door status indication panels
• Power supplies to two new mud transfer pumps
• Change out of galley transformers (additional to other transformer tasks)
• Switchboard cleaning
• New power supply to bow crane
• New power supply and communications to Seatrax crane
• Power supply to new accommodation module
• Disconnection and re-connection of several HVAC units
• Installation of transformers and distribution boards for the new electrical room (again in addition to other transformer task)
• Installation of mud agitator panels, associated junction boxes, level sensors and all power and control cabling
• Modifications to wiring of A/C compressor and air handler cabling
• Disconnection and re-connection of all four propulsion motors
• And a number of smaller tasks to assist our client.

 

“In total we used upwards of 60 electricians, through day and night shifts to complete all tasks as required. We also had a small team of men who continuously maintained all of our temporary supplies to transformers, welding sets, lighting etc.”  Non-electrical tasks undertaken (some naturally overlap with the electrical) provide further insight into the complexity of the time-constricted contract:
 

• Hydro blasting and painting of the outside hull, sponson tanks ballast tanks, mud tanks and moonpool area, and various other areas around the vessel
• Structural conversion of the existing flume tanks to mud pits, including installation of agitators, mud mixing and transfer pumps, new mud pipelines; and fabrication and installation of a new mud gas separator
• Fabrication of new crane pedestals and crane boom rests, and the removal of old cranes and installation of replacements
• Hull removals of the sponson tanks in order to remove old electrical transformers, and install new transformers. This included removal, repair and re-installation of the main propulsion motors
• Removal, overhaul by 3rd party and re-installation of vessel thrusters motors
• General dry docking works such as propeller works, tail-shaft works, rudders, sea valve overhauls, and anode renewals
• Fabrication and installation of stainless steel pipework for new hydraulic pressure unit and upgrade of ancillary equipment
• Steel renewals and modifications in all relevant areas such as sponson tanks, main deck, rig floor, ballast tanks, flume tanks and accommodation modules
• Piping fabrication and renewals/installation of high pressure piping systems, and sea water cooling systems
• Accommodation refurbishment of the mess room, cabins, and alleyways
• HVAC (heating, ventilation, air conditioning) upgrades that included the removal of old, and installation of new, air handling units
• Management and co-operation with 3rd party suppliers

 

Originally built by Mitsubishi in 1977, Ocean Clipper has a rated drilling depth of 25,000ft and, in 1999, made a name for herself by setting a new record in the Gulf of Mexico in more than 7,200ft of water – she is rated to 7,900ft.  She currently has a five-year commitment to Petrobras.
 

Maritime Reporter July 2015 Digital Edition
FREE Maritime Reporter Subscription
Latest Maritime News    rss feeds

People & Company News

On USCG Anniversary, Gov. McAuliffe Urges Hurricane Preparedness

Gov. Terry McAuliffe encouraged Virginians to get ready for hurricane season and provided an update on the commonwealth’s preparations Friday at a press conference

Optimized Tug-Barge System Designs by Robert Allan

Optimized Tug-Barge System Designs by Robert Allan Ltd. by David R. Connand Robert G. Allan, P.Eng. Some veteran Mississippi pushboats and barges have been

WKCTC to Host Open House for ILM Institute

West Kentucky Community and Technical College will host an open house and ribbon cutting for the Inland Logistics and Marine Institute August 10 from 4 ­– 6 p.

Ship Repair & Conversion

UK Navy Chooses Effer Crane Again

Cranes manufacturer Effer informs its marine crane has recently been installed aboard the U.K. Royal Navy’s patrol vessel HMS Mersey.   The new 5s 275M crane,

Fire-stricken Icebreaker Overhauled

SENER concludes the Almirante Irizar icebreaker engineering works for re-outfit and overhaul   SENER reports it has completed the engineering works relating to

Engine Refit for Mersey Pilot Boat

James Troop supplies two new Volvo Penta engines to upgrade Mersey pilot boat   Merseyside-based engine specialist James Troop & Co has secured a deal to supply

Offshore

Fratelli Neri Orders Damen Tug

One of the largest Italian tug owners, Fratelli Neri S.p.A, ordered its first Damen tug, an ASD 3212, on 21 July 2015.   The vessel will be the first ASD tug

NOIA Applauds Senate Passage of OPENS Act

NOIA President Randall Luthi issued the following statement on the Senate Energy and Natural Resources Committee’s passage of the OPENS Act, which will open new

Shell Moves Ahead in Arctic with Exploratory Well

Shell Oil's icebreaker MSV Fennica weaved through nine remaining protesters hanging from the St. Johns Bridge and made its way toward the Pacific Ocean.   Authorities

Energy

Optimized Tug-Barge System Designs by Robert Allan

Optimized Tug-Barge System Designs by Robert Allan Ltd. by David R. Connand Robert G. Allan, P.Eng. Some veteran Mississippi pushboats and barges have been

U.S. Drillers Add Rigs Despite Crude Collapse

U.S. energy firms added 5 oil rigs this week after putting 21 rigs into service last week, the most in over a year, despite a collapse in U.S. crude prices from recent highs in June,

West Africa's August Crude Exports to Asia to Slip

West African crude oil exports to Asia were expected to fall to 1.84 million barrels per day (bpd) in August, Reuters data and a survey of traders showed.     Slower

Naval Architecture

Optimized Tug-Barge System Designs by Robert Allan

Optimized Tug-Barge System Designs by Robert Allan Ltd. by David R. Connand Robert G. Allan, P.Eng. Some veteran Mississippi pushboats and barges have been

Fire-stricken Icebreaker Overhauled

SENER concludes the Almirante Irizar icebreaker engineering works for re-outfit and overhaul   SENER reports it has completed the engineering works relating to

ClassNK Releases Guidelines for CNG Carriers

Classification society ClassNK has released its Guidelines for Compressed Natural Gas (CNG) Carriers.   Global economic and population growth is bringing about

 
 
Maritime Careers / Shipboard Positions Maritime Contracts Maritime Security Naval Architecture Navigation Pod Propulsion Salvage Ship Electronics Ship Repair Shipbuilding / Vessel Construction
rss | archive | history | articles | privacy | contributors | top maritime news | about us | copyright | maritime magazines
maritime security news | shipbuilding news | maritime industry | shipping news | maritime reporting | workboats news | ship design | maritime business

Time taken: 0.1926 sec (5 req/sec)