Harris Pye Completes Brazilian Offshore Project

press release
Thursday, February 23, 2012

In just 90 days, the Harris Pye Group successfully completed the survey and upgrade of Diamond Offshore Drilling Inc’s (DODI) dynamically positioned drillship, the Ocean Clipper. All work was completed within schedule.


Totalling 247,235 man hours and utilising a 600-plus workforce, the contract was one of the largest offshore oil and gas projects for the South Wales headquartered company.  Despite the time-critical schedule, extraordinarily high man hours and large workforce, safety standards were superb and there were no serious accidents or injuries to any personnel. The upgrade encompassed accommodation, cranes, steelwork (for which 250 tons of steel were supplied); major pipe renewal in excess of 2 miles (3225metres) of piping); painting; and the removal and replacement of transformers and motors; and four major electrical tasks along with many other, not necessarily less complex, but smaller electrical tasks.  Activity was split between dry dock and alongside.


A highly comprehensive list of tasks successfully completed within a tight schedule:


• New watertight door status indication panels
• Power supplies to two new mud transfer pumps
• Change out of galley transformers (additional to other transformer tasks)
• Switchboard cleaning
• New power supply to bow crane
• New power supply and communications to Seatrax crane
• Power supply to new accommodation module
• Disconnection and re-connection of several HVAC units
• Installation of transformers and distribution boards for the new electrical room (again in addition to other transformer task)
• Installation of mud agitator panels, associated junction boxes, level sensors and all power and control cabling
• Modifications to wiring of A/C compressor and air handler cabling
• Disconnection and re-connection of all four propulsion motors
• And a number of smaller tasks to assist our client.

 

“In total we used upwards of 60 electricians, through day and night shifts to complete all tasks as required. We also had a small team of men who continuously maintained all of our temporary supplies to transformers, welding sets, lighting etc.”  Non-electrical tasks undertaken (some naturally overlap with the electrical) provide further insight into the complexity of the time-constricted contract:
 

• Hydro blasting and painting of the outside hull, sponson tanks ballast tanks, mud tanks and moonpool area, and various other areas around the vessel
• Structural conversion of the existing flume tanks to mud pits, including installation of agitators, mud mixing and transfer pumps, new mud pipelines; and fabrication and installation of a new mud gas separator
• Fabrication of new crane pedestals and crane boom rests, and the removal of old cranes and installation of replacements
• Hull removals of the sponson tanks in order to remove old electrical transformers, and install new transformers. This included removal, repair and re-installation of the main propulsion motors
• Removal, overhaul by 3rd party and re-installation of vessel thrusters motors
• General dry docking works such as propeller works, tail-shaft works, rudders, sea valve overhauls, and anode renewals
• Fabrication and installation of stainless steel pipework for new hydraulic pressure unit and upgrade of ancillary equipment
• Steel renewals and modifications in all relevant areas such as sponson tanks, main deck, rig floor, ballast tanks, flume tanks and accommodation modules
• Piping fabrication and renewals/installation of high pressure piping systems, and sea water cooling systems
• Accommodation refurbishment of the mess room, cabins, and alleyways
• HVAC (heating, ventilation, air conditioning) upgrades that included the removal of old, and installation of new, air handling units
• Management and co-operation with 3rd party suppliers

 

Originally built by Mitsubishi in 1977, Ocean Clipper has a rated drilling depth of 25,000ft and, in 1999, made a name for herself by setting a new record in the Gulf of Mexico in more than 7,200ft of water – she is rated to 7,900ft.  She currently has a five-year commitment to Petrobras.
 

Maritime Reporter September 2014 Digital Edition
FREE Maritime Reporter Subscription
Latest Maritime News    rss feeds

People & Company News

Decade Old India Shipping Summit Makes History

In ten years, India Shipping Summit held consistently in Mumbai, has sailed on a robust growth course despite the worldwide witnessing recessionary waves buffeting any endeavors to grow and gain.

Liebherr to Deliver RTGs to Mayotte and Manila

Liebherr confirms orders for variable speed RTGs and electric RTGs. DPWorld Asian Terminals Inc. has placed an order with Liebherr Container Cranes for a further 5 RTGs at its Manila facility.

U.S. Navy Contracts 12 Rapid Response Skimmers

Kvichak Marine won a US Navy contract for 12 30-ft.Rapid Response Skimmers (RRS) for delivery over the next 18 months, with options for up to 30 additional skimmers to be delivered through 2019.

Ship Repair & Conversion

Moore Stephens Expects Vessel Operating Cost to Rise

Vessel operating costs are expected to rise by almost three per cent in both 2014 and 2015, according to a new survey by international accountant and shipping consultant Moore Stephens.

Maritime Reporter @ 75: The Daily Cartoon

Maritime Reporter & Engineering News was founded by John J. O'Malley (1905-1980) in 1939, and today ranks as the world's largest audited trade publication in the world serving the maritime industry,

Mitsubishi Super Skiving System

Mitsubishi Heavy Industries, Ltd. (MHI) has completed development of the "Mitsubishi Super Skiving System" for machining internal gears with high speed and outstanding precision.

Energy

Decade Old India Shipping Summit Makes History

In ten years, India Shipping Summit held consistently in Mumbai, has sailed on a robust growth course despite the worldwide witnessing recessionary waves buffeting any endeavors to grow and gain.

Areva-Siemens Raises Claim Over Finnish Reactor Delays

The French-German consortium Areva-Siemens , the supplier of Finland's much-delayed Olkiluoto-3 nuclear reactor, has increased its claim against Finnish utility Teollisuuden Voima (TVO),

16 Die in Coal Mine Accident in China

Sixteen workers were killed after a coal mine collapsed in China's far western region of Xinjiang, the official Xinhua news agency reported on Saturday, highlighting

Naval Architecture

Rederij Groen Takes Delivery of 7-Waves

Rederij Groen’s entire SRSV fleet built by Damen Maaskant Shipyards Stellendam. Dutch offshore services company Rederij Groen has taken delivery of the 7-Waves,

New Research Vessel Delivered on the Great Lakes

The new oceanographic research and fisheries assessment vessel, Arcticus, completed her sea trials and was delivered to the U.S. Geological Survey's Great Lakes Science Center on October 17.

New Standard for LNG Cargo Containment Systems

Wilhelmsen Technical Solutions (WTS) said it has successfully completing the gas trial for the first LNG carrier built to a Boil Off Rate (BOR) of 0.08% per day.

 
 
Maritime Careers / Shipboard Positions Maritime Contracts Offshore Oil Pipelines Pod Propulsion Port Authority Ship Repair Shipbuilding / Vessel Construction Sonar Winch
rss | archive | history | articles | privacy | terms and conditions | contributors | top maritime news | about us | copyright | maritime magazines
maritime security news | shipbuilding news | maritime industry | shipping news | maritime reporting | workboats news | ship design | maritime business

Time taken: 0.2292 sec (4 req/sec)