Harris Pye Completes Brazilian Offshore Project

press release
Thursday, February 23, 2012

In just 90 days, the Harris Pye Group successfully completed the survey and upgrade of Diamond Offshore Drilling Inc’s (DODI) dynamically positioned drillship, the Ocean Clipper. All work was completed within schedule.


Totalling 247,235 man hours and utilising a 600-plus workforce, the contract was one of the largest offshore oil and gas projects for the South Wales headquartered company.  Despite the time-critical schedule, extraordinarily high man hours and large workforce, safety standards were superb and there were no serious accidents or injuries to any personnel. The upgrade encompassed accommodation, cranes, steelwork (for which 250 tons of steel were supplied); major pipe renewal in excess of 2 miles (3225metres) of piping); painting; and the removal and replacement of transformers and motors; and four major electrical tasks along with many other, not necessarily less complex, but smaller electrical tasks.  Activity was split between dry dock and alongside.


A highly comprehensive list of tasks successfully completed within a tight schedule:


• New watertight door status indication panels
• Power supplies to two new mud transfer pumps
• Change out of galley transformers (additional to other transformer tasks)
• Switchboard cleaning
• New power supply to bow crane
• New power supply and communications to Seatrax crane
• Power supply to new accommodation module
• Disconnection and re-connection of several HVAC units
• Installation of transformers and distribution boards for the new electrical room (again in addition to other transformer task)
• Installation of mud agitator panels, associated junction boxes, level sensors and all power and control cabling
• Modifications to wiring of A/C compressor and air handler cabling
• Disconnection and re-connection of all four propulsion motors
• And a number of smaller tasks to assist our client.

 

“In total we used upwards of 60 electricians, through day and night shifts to complete all tasks as required. We also had a small team of men who continuously maintained all of our temporary supplies to transformers, welding sets, lighting etc.”  Non-electrical tasks undertaken (some naturally overlap with the electrical) provide further insight into the complexity of the time-constricted contract:
 

• Hydro blasting and painting of the outside hull, sponson tanks ballast tanks, mud tanks and moonpool area, and various other areas around the vessel
• Structural conversion of the existing flume tanks to mud pits, including installation of agitators, mud mixing and transfer pumps, new mud pipelines; and fabrication and installation of a new mud gas separator
• Fabrication of new crane pedestals and crane boom rests, and the removal of old cranes and installation of replacements
• Hull removals of the sponson tanks in order to remove old electrical transformers, and install new transformers. This included removal, repair and re-installation of the main propulsion motors
• Removal, overhaul by 3rd party and re-installation of vessel thrusters motors
• General dry docking works such as propeller works, tail-shaft works, rudders, sea valve overhauls, and anode renewals
• Fabrication and installation of stainless steel pipework for new hydraulic pressure unit and upgrade of ancillary equipment
• Steel renewals and modifications in all relevant areas such as sponson tanks, main deck, rig floor, ballast tanks, flume tanks and accommodation modules
• Piping fabrication and renewals/installation of high pressure piping systems, and sea water cooling systems
• Accommodation refurbishment of the mess room, cabins, and alleyways
• HVAC (heating, ventilation, air conditioning) upgrades that included the removal of old, and installation of new, air handling units
• Management and co-operation with 3rd party suppliers

 

Originally built by Mitsubishi in 1977, Ocean Clipper has a rated drilling depth of 25,000ft and, in 1999, made a name for herself by setting a new record in the Gulf of Mexico in more than 7,200ft of water – she is rated to 7,900ft.  She currently has a five-year commitment to Petrobras.
 

Maritime Today


The Maritime Industry's original and most viewed E-News Service

Maritime Reporter June 2016 Digital Edition
FREE Maritime Reporter Subscription
Latest Maritime News    rss feeds

People & Company News

NORDEN’s Dry Cargo Head Bonderup Resigns

Ejner Bonderup, Executive Vice President and member of the Executive Management in Dampskibsselskabet NORDEN A/S, has resigned from his position to take up a position in another shipping company.

Baltic Index Up for Eighth Straight Session

The Baltic Exchange's main sea freight index, tracking rates for ships carrying dry bulk commodities, continued its rise on Friday, for an eighth consecutive session,

Asia Tankers-VLCC Rates Expected to Soften

MidEast rates slip from two-week high on June 28; raft of new ships and repaired vessels weigh on rates. Freight rates for very large crude carriers (VLCCs)

Ship Repair & Conversion

Gibdock Overhauls Solstad Cutter Propulsion System

Gibraltar’s Gibdock shipyard has completed an extensive package of work on Solstad Shipping’s Normand Cutter. The 127m long, 10,979grt construction support vessel

Solstad CSV Gets Propulsion Overhaul at Gibdock

Gibraltar’s Gibdock shipyard has completed its scope of work on Solstad Shipping’s Normand Cutter, a 127-meter-long, 10,979grt construction support vessel (CSV)

Tanker Allision on the Piscataqua River

The U.S. Coast Guard says it is continuing to monitor the condition of the chemical tanker Chem Venus, after it allided with three unoccupied, moored sailboats

Offshore

US Oil Drillers Add Rigs for 4th Week in 5

U.S. drillers this week added oil rigs for a fourth week in five, according to a closely followed report Friday, in the best month of producers returning to the

Norsafe Secures Contract with VARD Group

Norsafe informs it has signed a new contract with VARD Group, and will supply lifeboats complete with davit systems to a series of 15 new vessels.    Topaz Energy

India’s Potential in Offshore Wind Power

The Global Wind Energy Council (GWEC) launched a new report: “Supply Chain, Port Infrastructure and Logistics Study” for offshore wind development in the states of Gujarat and Tamil Nadu in India.

Energy

US Oil Drillers Add Rigs for 4th Week in 5

U.S. drillers this week added oil rigs for a fourth week in five, according to a closely followed report Friday, in the best month of producers returning to the

First Alaskan North Slope Cude Export Planned for Nicaragua

Alaskan North Slope (ANS) crude will be shipped to Nicaragua for the first time in July, two trade sources said on Friday, underscoring a shift in oil flows to and from the U.

India's Iran Oil Imports Surge in June

India's Iran oil imports rose about 39 percent in June year on year, preliminary data obtained by Reuters shows.   In the first half of 2016 India's Iran oil

Naval Architecture

Ingalls to Build US Warship LH8

Huntington Ingalls Industries (HII) announced that its Ingalls Shipbuilding division has been selected to build the U.S. Navy’s next large-deck amphibious assault warship, LHA 8.

ClassNK Sets up Industry's first Digital Archive Center

ClassNK has established ClassNK Archive Center (NKAC), the maritime industry’s first onshore digital archive center that fully complies with IMO Goal-based ship

Dassault Systèmes’ 3DEXPERIENCE Platform Extends Interoperability on Large Assets

Dassault Systèmes (Euronext Paris: #13065, DSY.PA), the 3DEXPERIENCE Company, world leader in 3D design software, 3D Digital Mock Up and Product Lifecycle Management (PLM) solutions,

 
 
Maritime Careers / Shipboard Positions Maritime Contracts Maritime Security Maritime Standards Naval Architecture Navigation Port Authority Ship Simulators Shipbuilding / Vessel Construction Winch
rss | archive | history | articles | privacy | contributors | top maritime news | about us | copyright | maritime magazines
maritime security news | shipbuilding news | maritime industry | shipping news | maritime reporting | workboats news | ship design | maritime business

Time taken: 0.1353 sec (7 req/sec)