Harris Pye Completes Brazilian Offshore Project

press release
Thursday, February 23, 2012

In just 90 days, the Harris Pye Group successfully completed the survey and upgrade of Diamond Offshore Drilling Inc’s (DODI) dynamically positioned drillship, the Ocean Clipper. All work was completed within schedule.


Totalling 247,235 man hours and utilising a 600-plus workforce, the contract was one of the largest offshore oil and gas projects for the South Wales headquartered company.  Despite the time-critical schedule, extraordinarily high man hours and large workforce, safety standards were superb and there were no serious accidents or injuries to any personnel. The upgrade encompassed accommodation, cranes, steelwork (for which 250 tons of steel were supplied); major pipe renewal in excess of 2 miles (3225metres) of piping); painting; and the removal and replacement of transformers and motors; and four major electrical tasks along with many other, not necessarily less complex, but smaller electrical tasks.  Activity was split between dry dock and alongside.


A highly comprehensive list of tasks successfully completed within a tight schedule:


• New watertight door status indication panels
• Power supplies to two new mud transfer pumps
• Change out of galley transformers (additional to other transformer tasks)
• Switchboard cleaning
• New power supply to bow crane
• New power supply and communications to Seatrax crane
• Power supply to new accommodation module
• Disconnection and re-connection of several HVAC units
• Installation of transformers and distribution boards for the new electrical room (again in addition to other transformer task)
• Installation of mud agitator panels, associated junction boxes, level sensors and all power and control cabling
• Modifications to wiring of A/C compressor and air handler cabling
• Disconnection and re-connection of all four propulsion motors
• And a number of smaller tasks to assist our client.

 

“In total we used upwards of 60 electricians, through day and night shifts to complete all tasks as required. We also had a small team of men who continuously maintained all of our temporary supplies to transformers, welding sets, lighting etc.”  Non-electrical tasks undertaken (some naturally overlap with the electrical) provide further insight into the complexity of the time-constricted contract:
 

• Hydro blasting and painting of the outside hull, sponson tanks ballast tanks, mud tanks and moonpool area, and various other areas around the vessel
• Structural conversion of the existing flume tanks to mud pits, including installation of agitators, mud mixing and transfer pumps, new mud pipelines; and fabrication and installation of a new mud gas separator
• Fabrication of new crane pedestals and crane boom rests, and the removal of old cranes and installation of replacements
• Hull removals of the sponson tanks in order to remove old electrical transformers, and install new transformers. This included removal, repair and re-installation of the main propulsion motors
• Removal, overhaul by 3rd party and re-installation of vessel thrusters motors
• General dry docking works such as propeller works, tail-shaft works, rudders, sea valve overhauls, and anode renewals
• Fabrication and installation of stainless steel pipework for new hydraulic pressure unit and upgrade of ancillary equipment
• Steel renewals and modifications in all relevant areas such as sponson tanks, main deck, rig floor, ballast tanks, flume tanks and accommodation modules
• Piping fabrication and renewals/installation of high pressure piping systems, and sea water cooling systems
• Accommodation refurbishment of the mess room, cabins, and alleyways
• HVAC (heating, ventilation, air conditioning) upgrades that included the removal of old, and installation of new, air handling units
• Management and co-operation with 3rd party suppliers

 

Originally built by Mitsubishi in 1977, Ocean Clipper has a rated drilling depth of 25,000ft and, in 1999, made a name for herself by setting a new record in the Gulf of Mexico in more than 7,200ft of water – she is rated to 7,900ft.  She currently has a five-year commitment to Petrobras.
 

Maritime Reporter August 2014 Digital Edition
FREE Maritime Reporter Subscription
Latest Maritime News    rss feeds

People & Company News

Newport International Boat Show Award Winners

Newport Exhibition Group, owners and producers of the Newport International Boat Show, announced today the results of this year’s Newport For New ProductsTM (NFNP) Awards.

China Merchant Boosts Efficiency of VLCCs with Jotun HP

China Merchant Energy Shipping Co., Ltd (CMES) will upgrade the antifouling solution on their VLCCs New Builds at Dalian Shipbuilding Industry Co., Ltd. (DSIC)

ESAB Boasts Over a Century of Technological Innovation

September 2014 marks the 110th anniversary of ESAB Welding & Cutting Products. A world leader in welding and cutting technology, with the broadest, most complete

Ship Repair & Conversion

DNV GL: Beyond Condition Monitoring in the Maritime Industry

Moving from a regime of scheduled rule-based maintenance to a data-driven risk-based regime can lead to more accurate and timely maintenance resulting in increased safety,

I-Tech’s Selektope Approved in China

I-Tech informed that Selektope, a marine biocide used to improve ship hull performance and reduce maintenance, has been approved for use in China. Selektope

Bollinger Shipyard Stalwart VP Dave Marmillion to Retire

Bollinger Shipyards, Inc. headquartered in Lockport, La., inform of the upcoming retirement of its Vice President Repair, Eastern Division, Dave Marmillion, after 46 years in the shipyard industry.

Offshore

Vard Orders Rolls-Royce Equipment for Rem OCV/AH

Rolls-Royce has won a £19m contract with the Norwegian shipbuilding group Vard to deliver deck machinery, propulsion and engines to a new offshore construction

First Havyard WE Design Delivered to Fafnir Offshore

Havyard Ship Technology's build 120 'Polarsyssel', a Havyard 832 L WE design, was delivered to Fafnir Offshore yesterday. It will go straight on assignment for

Brazil's Óleo e Gas, OSX Renegotiate FPSO Contract

Óleo e Gas Participações SA, the Brazilian oil producer that is under bankruptcy protection, and former sister company OSX Brasil SA completed on Friday a plan

Energy

Gazprom Scraps Plan to Cut Gas Deliveries

Russia's Gazprom scrapped a plan to cut gas exports to Romania by 9 percent on Saturday and by 5 percent on Sunday, Romania's Energy Minister Razvan Nicolescu said.

Poland Received Less Gas Than Requested from Gazprom

Poland's gas pipeline operator Gaz-System said the country received about 20 million cubic metres of natural gas on Friday from the eastern direction, less than

China Aug Power Output Falls First Time in 4 yrs

China's power output, a bellwether for economic activity, posted its first annual decline in more than four years in August, adding to evidence that the world's

Naval Architecture

MN 100: Robert Allan Ltd.

230-1639 West 2nd Avenue Vancouver, BC V6J 1H3, Canada Tel: (604) 736-9566    Email: info@ral.ca Website: www.ral.ca President: Ken Harford Executive Chairman of the Board: Robert G.

New SENER Asia & Pacific Directors Appointed

Alfonso Cebollero has been appointed as SENER's Regional Director for Asia and Pacific, while Guangwu Liu has become SENER's new Country Manager in China. Both

Vard Marine Obtains US Dual-Fuel Vessel Patent

Vard Marine says it has been awarded a US Patent for their design and engineering of a Dual Fuel Vessel. Later this year; the first of six 5100 dwt vessels to be built under this patent,

 
 
Maritime Contracts Maritime Security Naval Architecture Navigation Offshore Oil Pipelines Pod Propulsion Port Authority Ship Electronics Shipbuilding / Vessel Construction
rss | archive | history | articles | privacy | terms and conditions | contributors | top maritime news | about us | copyright | maritime magazines
maritime security news | shipbuilding news | maritime industry | shipping news | maritime reporting | workboats news | ship design | maritime business

Time taken: 0.2363 sec (4 req/sec)