Harris Pye Completes Brazilian Offshore Project

press release
Thursday, February 23, 2012

In just 90 days, the Harris Pye Group successfully completed the survey and upgrade of Diamond Offshore Drilling Inc’s (DODI) dynamically positioned drillship, the Ocean Clipper. All work was completed within schedule.

Totalling 247,235 man hours and utilising a 600-plus workforce, the contract was one of the largest offshore oil and gas projects for the South Wales headquartered company.  Despite the time-critical schedule, extraordinarily high man hours and large workforce, safety standards were superb and there were no serious accidents or injuries to any personnel. The upgrade encompassed accommodation, cranes, steelwork (for which 250 tons of steel were supplied); major pipe renewal in excess of 2 miles (3225metres) of piping); painting; and the removal and replacement of transformers and motors; and four major electrical tasks along with many other, not necessarily less complex, but smaller electrical tasks.  Activity was split between dry dock and alongside.

A highly comprehensive list of tasks successfully completed within a tight schedule:

• New watertight door status indication panels
• Power supplies to two new mud transfer pumps
• Change out of galley transformers (additional to other transformer tasks)
• Switchboard cleaning
• New power supply to bow crane
• New power supply and communications to Seatrax crane
• Power supply to new accommodation module
• Disconnection and re-connection of several HVAC units
• Installation of transformers and distribution boards for the new electrical room (again in addition to other transformer task)
• Installation of mud agitator panels, associated junction boxes, level sensors and all power and control cabling
• Modifications to wiring of A/C compressor and air handler cabling
• Disconnection and re-connection of all four propulsion motors
• And a number of smaller tasks to assist our client.


“In total we used upwards of 60 electricians, through day and night shifts to complete all tasks as required. We also had a small team of men who continuously maintained all of our temporary supplies to transformers, welding sets, lighting etc.”  Non-electrical tasks undertaken (some naturally overlap with the electrical) provide further insight into the complexity of the time-constricted contract:

• Hydro blasting and painting of the outside hull, sponson tanks ballast tanks, mud tanks and moonpool area, and various other areas around the vessel
• Structural conversion of the existing flume tanks to mud pits, including installation of agitators, mud mixing and transfer pumps, new mud pipelines; and fabrication and installation of a new mud gas separator
• Fabrication of new crane pedestals and crane boom rests, and the removal of old cranes and installation of replacements
• Hull removals of the sponson tanks in order to remove old electrical transformers, and install new transformers. This included removal, repair and re-installation of the main propulsion motors
• Removal, overhaul by 3rd party and re-installation of vessel thrusters motors
• General dry docking works such as propeller works, tail-shaft works, rudders, sea valve overhauls, and anode renewals
• Fabrication and installation of stainless steel pipework for new hydraulic pressure unit and upgrade of ancillary equipment
• Steel renewals and modifications in all relevant areas such as sponson tanks, main deck, rig floor, ballast tanks, flume tanks and accommodation modules
• Piping fabrication and renewals/installation of high pressure piping systems, and sea water cooling systems
• Accommodation refurbishment of the mess room, cabins, and alleyways
• HVAC (heating, ventilation, air conditioning) upgrades that included the removal of old, and installation of new, air handling units
• Management and co-operation with 3rd party suppliers


Originally built by Mitsubishi in 1977, Ocean Clipper has a rated drilling depth of 25,000ft and, in 1999, made a name for herself by setting a new record in the Gulf of Mexico in more than 7,200ft of water – she is rated to 7,900ft.  She currently has a five-year commitment to Petrobras.

Maritime Today

The Maritime Industry's original and most viewed E-News Service

Maritime Reporter November 2015 Digital Edition
FREE Maritime Reporter Subscription
Latest Maritime News    rss feeds

People & Company News

Crowley Opens Government Services Office

Crowley Maritime Corp. has opened a new government services office in downtown Norfolk, Va. to help the company better serve government agencies such as the Military Sealift Command (MSC) and the U.

Interview: Mike Petters - President & CEO, HII

Last month Mike Petters, president and CEO of Huntington Ingalls Industries (NYSE:HII), was honored by the Coast Guard Foundation at the 35th Annual Salute to the United States Coast Guard,

McAllister Towing – 150 Years of Family Business

“Early in 1864, a young man names James McAllister stood on board a sailing vessel where he served as a mate. The boat was about to set sail from the Red Bay of

Ship Repair & Conversion

Turbocharger Retrofits for Royal Caribbean

MAN PrimeServ informs it has won the contract from Royal Caribbean Cruises Ltd. (RCCL) to retrofit the turbochargers aboard four cruise liners from its fleet.   The

Adrift Cargo Ship Taken in Tow

The Barbados-registered cargo vessel Skog, which was adrift off Orkney after encountering engine problems, is now under tow, the U.K. Maritime and Coastguard Agency (MCA) reported.

MAN Selects Rud to Head PrimeServ Diesel

MAN Diesel & Turbo’s executive board has appointed Per Rud as the new head of PrimeServ Diesel.   Rud will assume his new role on January 1, 2016 and takes over from Wayne Jones,


Deepwater Downturn: Bump in the Road or Long-Term Slowing of Growth?

IMA/World Energy Reports has just completed a comprehensiveassessment of the five year outlook for the deepwater sector.  The new report – the 19th annual floater

Tidal Energy from Deep and Slow Waters

Deep Green, an underwater kite construction from the Swedish company Minesto, is set to be deployed in 2017 at the Holyhead Deep site off the coast of Anglesey, Wales.

RasGas to Waive $1bln Penalty on LNG Deal

Qatar-based natural gas producer RasGas will not penalise Petronet LNG for lower offtake of the fuel, says a report by PTI.   Qatar has agreed to waive $1 billion


Tidal Energy from Deep and Slow Waters

Deep Green, an underwater kite construction from the Swedish company Minesto, is set to be deployed in 2017 at the Holyhead Deep site off the coast of Anglesey, Wales.

Philippines Takes South China Sea Claim to Hague

Could bolster claims by other countries against China; China boycotting proceedings, rejects court's authority. The Philippines asked global judges on Tuesday

Fredriksen's Firms See Diverging Fortunes

Rig firm Seadrill sees tough market continuing in 2016. Firms in Norwegian-born billionaire John Fredriksen's empire saw contrasting fortunes on Tuesday, as rig firm Seadrill booked $1.

Naval Architecture

Fincantieri Launches Nuclear Waste Vessel for Russia

New semisubmersible floating platform will be used to transport special material decommissioned by the Russian Navy    Itarus, the new semisubmersible floating

ClassNK Drafts Amendments to Containership Rules

Classification society ClassNK has released draft amendments to its rules and guidance for container carriers, with the aim of implementing more comprehensive rules for increased ship safety.

Cadmatic Used for Alaska Ferry Design

The Alaska Marine Highway System (AMHS) has awarded the Alaska Class Ferry project to Vigor Alaska shipyard in Ketchikan, Alaska, where construction is currently underway.

Maritime Contracts Maritime Standards Naval Architecture Offshore Oil Pipelines Salvage Ship Electronics Ship Repair Sonar Winch
rss | archive | history | articles | privacy | contributors | top maritime news | about us | copyright | maritime magazines
maritime security news | shipbuilding news | maritime industry | shipping news | maritime reporting | workboats news | ship design | maritime business

Time taken: 0.1315 sec (8 req/sec)