Gibdock Completes Boluda Tug Overhaul

(Press Release)
Monday, October 17, 2011

Gibdock completed a complex propulsion system job, following the recent docking of the 57-ton bollard pull capacity Boluda group harbour tug Siroco.
The 2001-built Siroco, which operates in the port of Algeciras, arrived in Gibraltar in early June for a one month docking that included the complete removal and overhaul of the two Voith Schneider Propeller (VSP) units onboard.
As soon as the vessel was drydocked, it was jet washed with high pressure water and hand-scraped to remove marine growth in preparation for the VSP overhaul. The next task was to crop four access plates and two upright supports from the protective structure to allow access for Gibdock engineers so they could remove the VSP blades.
“This was a time consuming task and it took around two shifts to remove all ten blades and transport them to the mechanical workshop for overhaul," said John Taylor, Gibdock production director. "This included disassembling, cleaning, calibrating and remounting the bearing assembly with new spare parts and all the blades had to be inspected and polished.”
Gibdock engineers then removed the two rotor casings and transported them to the workshop. The main cover plate nuts were removed using a hydro torque, and all internal components, including pistons, gears, actuating rams and the thrust shaft were similarly transported to Gibdock’s mechanical workshop for overhaul. Using chain blocks the VSPs rotor casings were lowered from the vessel and, with the assistance of the yard’s shore cranes, these were lifted out from the bottom of the dock and transported to the workshop.
As part of the Siroco’s refit, Gibdock wet grit blasted and painted the tug’s hull and decks. This required considerable preparation work to ensure that exposed areas were unaffected. Mr Taylor said: “Once the Voith Schneider units and rotor casings had been removed, the main deck fixtures were completely protected and the two openings were blanked off before blasting.”
Throughout the wet grit blasting, the overhaul of the VSP equipment continued in the workshop. Following the dismantling and inspection of the rotor casing, the bearing flange assembly and protective ring was found to be extremely corroded. It was decided to fabricate and fit steel inserts to the two bearing flange assemblies.
Taylor said: “Although this was unexpected extra work, we incorporated a night shift to complete the repairs as soon as possible, in order not to affect the undocking date, which was crucial to the owners.” The new inserts were machined to an external diameter of 1,285mm, internal diameter of 1,065mm and a 60mm thickness. These inserts were then fitted to the existing bearing flange assembly.
While in the Gibdock workshop all the mechanical parts of the VSP units were cleaned, calibrated and the data recorded, and all the seals, packing and bushes were renewed, with Gibdock engineers working closely with service specialists from Voith Turbo Schneider. The reassembly of the VSP units in the workshop continued while a second full coat of paint was applied to the hull. Furthermore, Gibdock staff also applied a non-slip compound onto the tug’s main decks.
Once the Voith Schneider systems were completely reassembled onboard and the access plates refitted and welded, a final full topcoat of silicone paint was applied to the tug’s hull. After a 24 hour period to allow for the paint system to cure, the dock was flooded and the vessel left for sea trials.
 

Maritime Reporter April 2015 Digital Edition
FREE Maritime Reporter Subscription
Latest Maritime News    rss feeds

Marine Propulsion

1,000th Becker Mewis Duct to Be Presented at Nor-Shipping

Hamburg-based Becker Marine Systems will present its 1,000th Becker Mewis Duct in Oslo at Nor-Shipping 2015.   The use of all ducts previously delivered will have lowered CO2 by more than 1.

Modernization for Two Swedish Icebreakers

Protacon, a company based in Jyväskylä, Finland, informs it has received an order from Swedish Maritime Administration for the modernization of electric and automation systems of two icebreakers.

IMO’s MEPC Set to Adopt Polar Code Provisions

Polar Code environmental provisions set for adoption at IMO’s Marine Environment Protection Committee   The Marine Environment Protection Committee (MEPC) of

Shipbuilding

Keel Laid for SEA-Vista’s First ECO Tanker

General Dynamics NASSCO informs it has hosted a keel laying ceremony for the first Jones Act ECO tanker currently under construction for SEA-Vista LLC, at the company's shipyard in San Diego.

Blyth Workcats Delivers Aqualink

The first two-deck boat ever built by Blyth Workcats has recently been delivered to a customer in Belgium. The 18-meter Aqualink is the first Blyth Workcat to feature

Japan to Hand Over Data Ahead of Australia Submarine Bid

Japan will agree this month to give Australia classified submarine data, an unprecedented step signalling Tokyo's intent to join competitive bidding to sell Canberra a fleet of stealth subs,

 
 
Maritime Careers / Shipboard Positions Maritime Standards Navigation Offshore Oil Pipelines Pod Propulsion Port Authority Ship Repair Ship Simulators Shipbuilding / Vessel Construction
rss | archive | history | articles | privacy | contributors | top maritime news | about us | copyright | maritime magazines
maritime security news | shipbuilding news | maritime industry | shipping news | maritime reporting | workboats news | ship design | maritime business

Time taken: 0.1576 sec (6 req/sec)