STATS Completes North Sea Platform Platform

press release
Wednesday, January 04, 2012
File North Everest Pipe Layout
North Everest Pipe Layout

Pipeline engineering experts, STATS Group, has completed an isolation project on behalf of AMEC to allow maintenance and replacement works on the North Everest platform in the central North Sea.

 

The workscope covered three maintenance valves and one ESD valve on a 20-inch gas import line onboard the BG-operated platform. After a detailed site survey and piggability study, STATS decided the best solution was to use a tethered Tecno Plug pushed by stem bar to location from a temporary launcher.  As the pipeline had no pigging history, this method was considered as the least risk laden option rather than pigging a remotely operated plug from the pig trap.

 

This alternative method was proposed based on detailed analysis during the Front End Engineering Design (FEED) process, including the piggability study which revealed potential issues for the route of the pigging run which could have prevented the Tecno Plug™ from reaching the desired set location. The FEED process included generation of a project design premise, pipe stress analysis, piggability study, FMECA, operational procedure and risk assessment. This package identifies and mitigates operational risk and reassures clients by providing detailed analysis of the internal conditions and geometry of the pipeline prior to carrying out the isolation.

 

Prior to carrying out the isolation the pipeline pressure was reduced to 6 barg, with the ESD closed and sealant injected, the maintenance valve was then closed to provided  temporary pipeline isolation. This allowed the temporary launcher to be installed inboard of the ESD valve and a team of STATS technicians to break out the piping.  A weld repair scope was also required and the STATS team removed the first 90o bend with clam shell cutting tools.

 

STATS also provided gas bags to act as a vapour barrier while a new 1500# flange was welded into the line. The new flange was then pressure tested using a STATS Flanged Weld Test Tool before reinstating the new bend and launcher valves. With the temporary launcher now in place and fully pressure tested, the valves were opened and the Tecno Plug™ was deployed into position outboard of the valves and hydraulically set to provide pipeline isolation.

 

Once set and monitored the stem bar was disconnected and the valves were replaced. As the pipeline pressure was only 6 barg, the Tecno Plug™ was installed in the reverse direction, providing full isolation while also providing a test boundary to pressure test the integrity of the reinstalled valves.

 

A full pressure test at 208 Barg was then conducted between the temporary launcher and the Tecno Plug™ before the plug was unset and recovered back into the launcher. The valves were then closed and temporary launcher removed allowing the pipeline to be reinstalled and returned to operation.
 

Email AddThis Feed Button
Maritime Reporter May 2012 Digital Edition
FREE Maritime Reporter Subscription
Latest Maritime News    rss feeds

People & Company News

USNS Comfort's Medical Treatment Facility Changes Command

Military Sealift Command hospital ship USNS Comfort's Medical Treatment Facility changed leadership May 25 as Navy Capt. Kevin J. Knoop assumed command from Navy Capt.

UASC Names 13,500 TEU Containership

United Arab Shipping Company increases its fleet with more 13,500 TEU vessels; The United Arab Shipping Company (UASC) names 13,500 TEU containership in Hamburg on 25 May.

Kvichak Names Kirby as Proposal Manager

Kvichak Marine Industries in Seattle Washington announces the appointment of Kevin Kirby as their new proposal manager.   Kevin has been with Kvichak for

Technology

KR Engineering Signs up for FORAN

Within merely three months from its establishment, SENER Korea Engineering and Systems Co., Ltd. (SKES) has won its first contract, a license agreement with KR Engineering Co.

First Operational Wave Energy Power Plant Installed

Israeli company, Eco Wave Power, has opened a medium-scale wave energy generation system in the Black Sea Eco Wave Power (EWP) has recently installed a medium-scale

Marlink Enhances Efficiency with C-Band on iDirect

New technology platform options for Marlink C-band users.   Marlink is expanding its portfolio with the introduction of new C-band services on the iDirect platform,

Offshore

Jumbo Heavylift Ship Installs at Offshore Wind Farm

'Jumbo Javelin' installs the first transition pieces for the Anholt Offshore Wind Farm International Cranes & Specialised Transport reports that Netherlands-based

Test of Floating Wind Turbine at US Site Next Year

The floating deep water wind turbine test installation 3 miles off Monhegan Island in the Gulf of Maine is held back until 2013 A report by Christine Parrish

OSV Ship of the Year 'North Sea Giant'

The 'Offshore Support Vessel of the Year Award' for 2012 was won by North Sea Shipping's 'North Sea Giant', built to DNV class at the Metalships & Docks shipyard in Vigo,

Energy

Jumbo Heavylift Ship Installs at Offshore Wind Farm

'Jumbo Javelin' installs the first transition pieces for the Anholt Offshore Wind Farm International Cranes & Specialised Transport reports that Netherlands-based

OSV Ship of the Year 'North Sea Giant'

The 'Offshore Support Vessel of the Year Award' for 2012 was won by North Sea Shipping's 'North Sea Giant', built to DNV class at the Metalships & Docks shipyard in Vigo,

First Operational Wave Energy Power Plant Installed

Israeli company, Eco Wave Power, has opened a medium-scale wave energy generation system in the Black Sea Eco Wave Power (EWP) has recently installed a medium-scale

 
 
Maritime Careers / Shipboard Positions Maritime Contracts Maritime Security Maritime Standards Naval Architecture Navigation Offshore Oil Salvage Shipbuilding / Vessel Construction Sonar
mobi | rss feeds | archive | history | articles | privacy | contributors | top news | about us | copyright

Time taken: 0.0575 sec (17 req/sec)