Costa Concordia Wreck Removal: Local Citizens Progress Update

MarineLink.com
Friday, December 27, 2013
Costa Concordia Dec. 2013: Image credit Costa Crociere

A  meeting of Giglio residents heard that the Condordia is stable: after the minor movements registered in the 15 days following the parbuckling operation the wreck has settled on the platform and seabed. Since then, the monitoring systems active 24/7 have not indicated any significant movement.

Present at the meeting with Giglio residents were Maria Sargentini, Chairman of the Observatory, Sergio Ortelli, Mayor of Giglio, and Franco Porcellacchia, coordinator of the Concordia wreck removal project for Costa Crociere.


The meeting also was informed that In the Livorno and Genoa shipyards, work is in progress to prepare the 15 sponsons that will be positioned on the starboard side (land side) and the remaining 4 on the right side (sea side) in order to proceed with the refloating phase and have the wreck ready for towing by the end of June 2014.

The sponsons will be completed with the installation of strand jacks in the shipyards and will be transported in vertical position to Giglio Island in the spring of 2014.

Finally, Costa informed that 405 safes have been removed from the dry cabins on board the wreck in agreement with judicial authorities; contents will be inventoried and handed back to their owners.
 
 

 

 

 

Maritime Reporter October 2014 Digital Edition
FREE Maritime Reporter Subscription
Latest Maritime News    rss feeds

People & Company News

Deepwater Semi-Sub COSL Prospector Delivered

COSLProspector, the fourth deep-water semi-submersible drilling rig built by CIMC Raffles for China Oilfield Services Limited (COSL), has been delivered in Yantai, Shandong Province.

Trelleborg Invests in High-Speed Fender Test Rig

Trelleborg’s marine operation is in the process of building and installing a custom-made high-speed test rig, capable of testing both rubber and foam fenders.   The

Asia Tanker, VLCC Rates Could Climb

Charterers to release 30 Middle East VLCC cargoes next week. VLCC market buoyed by upbeat Suezmax, Aframax sectors. Rates for very large crude carriers (VLCCs)

Technology

Video: Reefer RoRo Ship Design Rebooted

Expanding on the Reefer RoRo Ship design release in September last year, naval architects group Knud E. Hansen A/S has continued the development of the new Reefer RoRo Ship design with version II.

New Tidal Wave Energy Device Completes Sea Trials

In the continuing quest to harvest efficient, renewable energy from the power of the world’s tides, an organization called Sustainable Marine Energy’s announced

EMGS to Map Brazil's Gas Hydrates

Electromagnetic Geoservices ASA (EMGS) has received a contract worth USD 1.5 million for a research project in Brazil. The project will use 3D EM data to map

News

Cost to Fuel Ships Falls

For a ship that burns 24 tonnes of fuel per day while steaming, fuel costs are reduced by as much as $1 million a year if current price level stay put. Assuming

Video: Reefer RoRo Ship Design Rebooted

Expanding on the Reefer RoRo Ship design release in September last year, naval architects group Knud E. Hansen A/S has continued the development of the new Reefer RoRo Ship design with version II.

Deepwater Semi-Sub COSL Prospector Delivered

COSLProspector, the fourth deep-water semi-submersible drilling rig built by CIMC Raffles for China Oilfield Services Limited (COSL), has been delivered in Yantai, Shandong Province.

Underwater Engineering

EMGS to Map Brazil's Gas Hydrates

Electromagnetic Geoservices ASA (EMGS) has received a contract worth USD 1.5 million for a research project in Brazil. The project will use 3D EM data to map

Rosneft Completes Geological Survey

Rosneft reports on 100% completion of the geological survey program on Company's offshore license areas for 2014. In the current year geological survey covered

COSL Takes Delivery of New Semisub

China Oilfield Services Limited saw successful delivery of the deepwater semi-submersible drilling rig COSLProspector it invested in and commissioned to build in Yantai, Shandong today.

 
 
Maritime Careers / Shipboard Positions Maritime Security Maritime Standards Navigation Offshore Oil Pipelines Pod Propulsion Port Authority Shipbuilding / Vessel Construction Winch
rss | archive | history | articles | privacy | terms and conditions | contributors | top maritime news | about us | copyright | maritime magazines
maritime security news | shipbuilding news | maritime industry | shipping news | maritime reporting | workboats news | ship design | maritime business

Time taken: 0.1257 sec (8 req/sec)