Costa Concordia Salvage: New Timeline

Press Release
Tuesday, August 28, 2012
Costa Condordia: Photo credit Wikimedia CCL

The stricken cruise ship will spend another winter partially submerged close off the coast of Giglio, Italy.

The consortium hired to re-float and remove the 114,500-ton ship presented this month a new timeline to the Osservatorio, the entity supervising the wreck salvage operations. Originally scheduled for completion by January 2013, the removal plan has been delayed until next spring.

The Italian-American Consortium, TITAN/Micoperi, presented the detailed engineering and design plan for the removal of the wreck Costa Concordia to representatives from Osservatorio recently, who issued the following statement:

The presentation confirmed the previously presented and shared phases of the plan. Activities in recent months have focused on the testing of the various technologies required to successfully execute the operation and the increasing need to prevent or contain any potential impacts to the surrounding environment. To date, all suppliers of the materials and work required have been secured.

The drilling techniques that will be used have been selected carefully and the seabed has been mapped, which will aid in minimizing the effects on the marine environment.  The marine environment (turbidity, sediments distribution, current patterns, sea mammals, etc ...), as well as the land environment (air quality, noise, vibrations, etc …), have been evaluated.

Diligent monitoring of these environments will be in place once the drilling begins to minimize the impact. As the plan progresses, the various phases will be confirmed with the Osservatorio team and the technicians who operate on site to ensure feasibility and well-being of the ecosystem surrounding the wreck.

Orders were recently placed for all the supplies, components and materials necessary for operations. These purchases will have a positive impact on Italy’s national industry and the local economy.

Finally, Osservatorio report that the wreck removal plan has a new predicted timeline that estimates the parbuckling and refloating to be complete by Spring of 2013. This time schedule is dependent in part upon subcontractor deliverables and schedules, and will preserve the upcoming summer season.


 


People & Company News

Kongsberg Performs Well in Q2

Norwegian defence and marine technology company Kongsberg Gruppen's second quarter 2016 (Q2) financial results shows sales performance broadly in line with recent trends,

Rickmers Holding, E.R. Capital Drop Merger Plan

Rickmers Holding AG and E.R. Capital Holding have jointly decided not to pursue the merger of their ship management activities.   For many years the companies

MN100: Conrad Shipyard

The Company: Conrad Shipyard was established in 1948 and is headquartered in Morgan City, Louisiana. The company designs, builds and overhauls tugboats, ferries,

Salvage

El Faro Captain Ordered Crew to Abandon Ship before Sinking

The captain of the doomed El Faro cargo ship sounded an alarm for his crew to abandon the vessel shortly before it sank last fall in a hurricane near the Bahamas, killing all 33 onboard, the U.

26 Hours of Information Recovered from El Faro's VDR

A group led by the U.S. National Transportation Safety Board (NTSB) has gathered information from the recovered voyage data recorder (VDR) of sunken cargo ship

The Economics of Ship Breaking & Scrapping

Sometimes being an industry supplier offers interesting insights – your business is touched by the ups and downs of the charter market, but you are never so involved

 
 
Maritime Careers / Shipboard Positions Navigation Offshore Oil Port Authority Salvage Ship Electronics Ship Repair Ship Simulators Shipbuilding / Vessel Construction Winch
rss | archive | history | articles | privacy | contributors | top maritime news | about us | copyright | maritime magazines
maritime security news | shipbuilding news | maritime industry | shipping news | maritime reporting | workboats news | ship design | maritime business

Time taken: 0.1034 sec (10 req/sec)