Concrete Work for Panama Canal Locks Begins

Wednesday, July 27, 2011

In yet another major milestone for the Panama Canal Expansion Program, permanent concrete work for the Atlantic and Pacific new set of locks recently began – marking one of the most important phases of the construction.

Last March, Grupo Unidos por el Canal S.A. (GUPCSA), the contractor in charge of this project, started pouring lean concrete at both lock sites to level the surface in preparation for the permanent concrete work.

This month, GUPCSA poured structural marine concrete to shape the floor of the upper chamber in Gatun, on the Atlantic side. The concrete was poured into specialized industrial formwork that included a significant amount of rebar (steel bars or rods used to reinforce concrete) to ultimately shape the 100 cubic meter blocks that make up the lock floor.

The concrete mix, designed to guarantee a minimum service life of 100 years of operation to the waterway, was transported to the site using agitator trucks lined with insulating material to ensure a maximum temperature of 12 degrees centigrade at the moment of the pouring. Fifteen of these truckloads are required to pour each one of the blocks.

On the Pacific side, concrete pouring activities also began with the construction of the pit for the first of three lock crossunders or tunnels. Through these crossunders, trays and pipes will carry communication and electricity wires, drinking water pipelines and other components needed to operate the lock complex. Of note, each set of locks will have three crossunders.

Each of the pits is built by stacking 16 blocks made of structural concrete and rebar. Twelve trucks, with capacity to carry 8 cubic meters of concrete, are required to pour each of the blocks. The pits, at a height comparable to that of a 10-story building, will include a series of steps and an elevator that will enable access to the crossunder. Once completed, the crossunders will allow maintenance personnel to conduct their tasks in a safe environment.

Maritime Reporter March 2014 Digital Edition
FREE Maritime Reporter Subscription
Latest Maritime News    rss feeds

News

Canaveral Tops State List for Sand Bypass Funding

The Canaveral Harbor Inlet Sand Bypass Project has earned the top state ranking for 2014/15 inlet management funding. As a result, Port Canaveral is expected to receive $100,

Rotterdam port's throughput almost stable

The Port of Rotterdam’s throughput in the first quarter of 2014, at 109 million tonnes, was 0.2% below the level for the corresponding period last year.Split up by goods type,

PetroVietNam Gas's Q1 gross profit falls 27.5%

PetroVietNam Gas's first-quarter gross profit fell 27.5 percent to 3.9 trillion dong ($185 million) from a year earlier, the Lao Dong (Labour) newspaper reported.

 
 
Maritime Standards Naval Architecture Offshore Oil Pipelines Pod Propulsion Salvage Ship Electronics Ship Repair Shipbuilding / Vessel Construction Sonar
rss | archive | history | articles | privacy | contributors | top maritime news | about us | copyright | maritime magazines
maritime security news | shipbuilding news | maritime industry | shipping news | maritime reporting | workboats news | ship design | maritime business

Time taken: 0.1192 sec (8 req/sec)