Construction Engineering Work for OFSV Started At Vancouver Shipyards

Monday, March 18, 2013

Vancouver Shipyards (VSY) has started design work under the Construction Engineering Contract for the Canadian Coast Guard’s Offshore Fisheries Science Vessel (OFSV). This contract will take a total of ten months to complete and lead to a build contract in early 2014.

The work under this contract will be completed in three phases:

1. Initial Design Phase – elements of the design will be matured and an initial cost model developed.

2. Functional Design Phase – design for spaces and systems will be completed, equipment identified, suppliers engaged and regulatory approval for the design obtained.

3. Production Design Phase – a detailed 3D model of the ship will be started to define final requirements for material and layout of spaces and systems.

In addition to the construction engineering contract, a future contract will allow the completion of the 3D model, procurement of long lead time equipment prior to the start of the build of the ships, and development of manufacturing information to a production ready state.

Each of the three Offshore Fisheries Science Vessels will be 55 meters long; designed to operate in the Atlantic, Pacific and Arctic Oceans and built to conduct fishing and acoustic surveys of fish and invertebrates and collect physical, chemical and biological oceanographic data to monitor changes in the marine ecosystem.

Work on the OFSV construction engineering contract is being performed by an experienced team of engineers, program managers and supply chain specialists who collectively have over 1000 years of ship design and construction experience. Recognized industry leaders and experts in design from STX Canada Marine, Imtech Canada, Thales Canada and Computer Sciences Canada are bolstering the internal team at VSY.

The OFSV is the first in a series of Non-Combat ships to be built by VSY for Canada. Additional vessels include one Offshore Oceanographic Science vessel, two Joint Support Ships and a Polar Icebreaker.

The ships will be built at Vancouver Shipyards, which is currently undergoing a $200 million shipyard modernization to allow for the efficient build of Canada’s new Non-Combat ships. The new facilities will include seven fabrication, construction and painting shops, as well as a 300 ton gantry crane.

“This construction engineering contract further solidifies the revival of the shipbuilding industry on the west coast of Canada which will eventually see the production workforce at Vancouver Shipyards reach and sustain 1000 skilled trades workers,” said Brian Carter – President, Seaspan Shipyards.

The start of the design work on the OFSV follows the recent February 22 announcement of the contract by the Honourable Rona Ambrose, Minister for Public Works and Government Services.

 www.seaspan.com
 

Maritime Reporter October 2014 Digital Edition
FREE Maritime Reporter Subscription
Latest Maritime News    rss feeds

Technology

World’s First LNG-Ready Ultra Large Container Ship Named

The race is on in global maritime circles to be the “world’s first” in every aspect of environmental friendliness, particularly in regards to the incorporation of LNG as fuel onboard commercial ships.

Wärtsilä Integrated Solutions for Maersk's AHTS Vessels

A new series of six Anchor Handling Tug Supply vessels to be built at the Kleven Verft AS in Norway for the Danish based Maersk Supply Service A/S - part of the A.

ClassNK Approves Niigata Dual-fuel Engine Design

Classification society ClassNK has granted approval to the design of the new 28AHX-DF dual-fuel engine developed by Niigata Power Systems Co., Ltd. The new engine

Shipbuilding

World’s First LNG-Ready Ultra Large Container Ship Named

The race is on in global maritime circles to be the “world’s first” in every aspect of environmental friendliness, particularly in regards to the incorporation of LNG as fuel onboard commercial ships.

Wärtsilä Integrated Solutions for Maersk's AHTS Vessels

A new series of six Anchor Handling Tug Supply vessels to be built at the Kleven Verft AS in Norway for the Danish based Maersk Supply Service A/S - part of the A.

MacGregor Deck Equipment for Intership's Eco-bulkers

MacGregor, part of Cargotec, has secured a deck equipment contract from New Times Shipyard in China for Intership Navigation Co Ltd.'s three new 36,500 dwt laker-class bulk carriers.

Offshore

Wärtsilä Integrated Solutions for Maersk's AHTS Vessels

A new series of six Anchor Handling Tug Supply vessels to be built at the Kleven Verft AS in Norway for the Danish based Maersk Supply Service A/S - part of the A.

Fourth Rig Delivered to Perforadora Central

Keppel AmFELS LLC, a wholly owned US subsidiary of Keppel Offshore & Marine Ltd (Keppel O&M), has delivered the jackup rig, Coatzacoalcos, to Mexico’s Central Panuco S.

Woodside to Pick up Moroccan Acreage

Woodside advises that it has entered into a contract for an exclusive Reconnaissance Licence (RL) with the Office National des Hydrocarbures et des Mines, the

Vessels

MHI Completes Development of "Sayaringo STaGE"

Mitsubishi Heavy Industries, Ltd. (MHI) has completed development of the "Sayaringo STaGE," a next-generation LNG (liquefied natural gas) carrier. The Sayaringo

MacGregor Deck Equipment for Intership's Eco-bulkers

MacGregor, part of Cargotec, has secured a deck equipment contract from New Times Shipyard in China for Intership Navigation Co Ltd.'s three new 36,500 dwt laker-class bulk carriers.

From Security to Efficiency Modern Vessel Tracking

More so than many other fields of business, the maritime industry is focused on cost, which in turn gives the appearance of being conservative towards technology.

Arctic Operations

MSC Approves SOLAS Amendments

SOLAS amendments to make IGF Code mandatory approved by Maritime Safety Committee   The International Maritime Organization’s (IMO) Maritime Safety Committee (MSC),

Production Begins on Sovcomflot’s New MPSV

Arctech Helsinki Shipyard started production of the new icebreaking multipurpose supply vessel   The production of the icebreaking multipurpose supply vessel

Strategy Can Maximize UKCS potential

Companies operating in the North Sea require a cultural shift to make the most of the its potential, according to a new report from Deloitte, the business advisory firm.

 
 
Maritime Careers / Shipboard Positions Maritime Contracts Maritime Security Maritime Standards Naval Architecture Navigation Pipelines Ship Electronics Ship Simulators Winch
rss | archive | history | articles | privacy | terms and conditions | contributors | top maritime news | about us | copyright | maritime magazines
maritime security news | shipbuilding news | maritime industry | shipping news | maritime reporting | workboats news | ship design | maritime business

Time taken: 0.1317 sec (8 req/sec)