Underwater Repairs Keep 400m Containership in the Water

Posted by Eric Haun
Monday, July 14, 2014
Hydrex on-site, making preparations for operation on 400-meter container vessel.

At the end of June, a Hydrex team replaced the three leaking bow thruster shaft seals of a 400-meter container ship in Gdansk, Poland. The operation was performed on-site and underwater using the company’s flexible mobdocks. The vessel was able to continue its commercial activities without any hindrance or delay.

Together with all the necessary equipment, the diver/technicians mobilized from the Hydrex fast response center in Antwerp to the vessel’s location. After they set up a monitoring station on the quay, the divers started the operation by removing the rope guard covering the thruster seals. They could then perform a detailed inspection of the seal assembly and make a good assessment of the damage.

The Hydrex flexible mobdocks were installed at both ends of the thruster tunnel. Next the team evacuated all water from the tunnel. In this manner a working environment with drydock-like conditions was created. This is essential for any permanent seal replacement. The divers removed the first seal and replaced it with a new one which was then bonded. This procedure was repeated with the other two damaged seals. All seals showed cuts at the underside, which had caused the oil leak.

The operation ended with succesful leakage tests, the reinstallation of the rope guard and the removal of the flexible mobdocks.

During the operation representatives of both the manufacturer of the shaft seals and the bow thruster OEM were present. They followed the operation and gave their approval.

Ultra large container vessels like this 400-meter one have a corresponding large thruster tunnel. This was however no problem because the Hydrex flexible mobdocks can be easily adapted  to the circumstance. They can be used for a wide range of repair or maintenance work on all types and sizes of thrusters and vessels.

By performing the operation on-site and underwater, the divers made it possible for the owner to keep his vessel out of drydock. This was extremely important because the ship was only six months old. The Hydrex team worked in shifts around the clock. They finished the job well before the crew had concluded the cargo operations. This allowed the ship to sail perfectly on schedule.

hydrex.be
 

  • Hydrex diver/technician taking the plunge.

    Hydrex diver/technician taking the plunge.

  • The old seals had cuts at the bottom, causing the leak.

    The old seals had cuts at the bottom, causing the leak.

  • Hydrex team member supervising the underwater operation.

    Hydrex team member supervising the underwater operation.

  • Diver/technician working on the shaft seal assembly.

    Diver/technician working on the shaft seal assembly.

  • New seal positioned and bonded.

    New seal positioned and bonded.

  • Divers getting ready for underwater operation.

    Divers getting ready for underwater operation.

  • A monitoring station was set-up  next to the vessel.

    A monitoring station was set-up next to the vessel.

  • Hydrex diver/technician taking the plunge.
  • The old seals had cuts at the bottom, causing the leak.
  • Hydrex team member supervising the underwater operation.
  • Diver/technician working on the shaft seal assembly.
  • New seal positioned and bonded.
  • Divers getting ready for underwater operation.
  • A monitoring station was set-up  next to the vessel.
Maritime Reporter October 2014 Digital Edition
FREE Maritime Reporter Subscription
Latest Maritime News    rss feeds

Ship Repair & Conversion

Seaspan Shipyard's Prompt Response to Canadian Coast Guard

Seaspan Shipyard’s long-standing relationship with the Canadian Coast Guard was proudly showcased in recent days, with simultaneous repair and maintenance work

Energy Storage System Ordered for LNG Battery Hybrid Ferry

Norwegian hybrid to be the first LNG battery ferry to operate on commercial routes Corvus Energy, Siemens AS and Fjord1 have announced the award of the contract for the Fannefjord LNG hybrid ferry.

N-KOM Recognized for Shipyard Safety, Security

Nakilat-Keppel Offshore & Marine (N-KOM) received the Safety & Security Award at the inaugural edition of The Maritime Standard (TMS) Middle East & Indian Subcontinent Awards,

News

7 Rescued from Sinking Freighter Near Haiti

Seven crewmembers were rescued after their 100-foot coastal freighter began taking on water and sank approximately 45 miles north off of Cap Haitien, Haiti, Friday.

Gazprom Transgaz Ufa Organizes Arts Festival

Over 200 healthy children and children with disabilities from Bashkortostan as well as the Volga Region participated in the Breaking the Barriers second interregional children’s arts festival,

Time-out for Kwanza Drilling

Statoil has decided to cancel the Stena Carron rig contract after fulfilling the work commitments in the Statoil-operated blocks 38 and 39 in the Kwanza basin offshore Angola.

Underwater Engineering

Time-out for Kwanza Drilling

Statoil has decided to cancel the Stena Carron rig contract after fulfilling the work commitments in the Statoil-operated blocks 38 and 39 in the Kwanza basin offshore Angola.

EMGS to Map Brazil's Gas Hydrates

Electromagnetic Geoservices ASA (EMGS) has received a contract worth USD 1.5 million for a research project in Brazil. The project will use 3D EM data to map

Rosneft Completes Geological Survey

Rosneft reports on 100% completion of the geological survey program on Company's offshore license areas for 2014. In the current year geological survey covered

 
 
Maritime Security Maritime Standards Naval Architecture Navigation Offshore Oil Pod Propulsion Ship Electronics Ship Simulators Shipbuilding / Vessel Construction Winch
rss | archive | history | articles | privacy | terms and conditions | contributors | top maritime news | about us | copyright | maritime magazines
maritime security news | shipbuilding news | maritime industry | shipping news | maritime reporting | workboats news | ship design | maritime business

Time taken: 0.2874 sec (3 req/sec)