GAO Critical of Navy Flat-top Program

MarineLink.com
Friday, September 06, 2013
Artist's rendering of CVN 78

In a new report, the US Government Accountability Office (GAO) states that the Navy faces technical, design, and construction challenges to completing 'Gerald R. Ford' (CVN 78) that have led to significant cost increases and reduced the likelihood that a fully functional ship will be delivered on time. The GAO finds:

The Navy has achieved mixed progress to date developing CVN 78's critical technologies, such as a system intended to more effectively launch aircraft from the ship. In an effort to meet required installation dates aboard CVN 78, the Navy has elected to produce some of these systems prior to demonstrating their maturity--a strategy that GAO's previous work has shown introduces risk of late and costly design changes and rework, and leaves little margin to incorporate additional weight growth in the ship.

In addition, progress in constructing CVN 78 has been overshadowed by inefficient out-of-sequence work, driven largely by material shortfalls, engineering challenges, and delays developing and installing critical technology systems. These events are occurring in a constrained budget environment, even as lead ship costs have increased by over 22 percent since construction authorization in fiscal year 2008--to $12.8 billion. Additional increases could follow due to uncertainties facing critical technology systems and shipbuilder underperformance.

The Navy's strategy for providing timely demonstration of CVN 78 capabilities is hampered by post-delivery test plan deficiencies, Joint Strike Fighter aircraft delays, and reliability shortfalls affecting key ship systems. Additional risk is introduced due to the Navy's plan to conduct integration testing of key systems with the ship at the same time as initial operational test and evaluation (IOT&E). This strategy will constrain opportunities to implement timely, corrective actions if problems are discovered with key ship systems. In addition, significant discoveries during IOT&E could delay demonstration of ship capabilities. The Joint Strike Fighter, intended to operate with the carrier, has faced delays, and there is the likelihood of costly retrofits to the ship to accommodate the aircraft after CVN 78 is delivered to the Navy. But even after the ship commissions, several key ship systems will continue to face significant reliability shortfalls that will likely increase costs to the government and limit the ship's mission effectiveness. The extent of these limitations will not be known until after IOT&E. GAO contemplated making a recommendation to delay CVN 78 commissioning until the ship successfully completes IOT&E. However, based on additional information provided by DOD, GAO decided not to include this recommendation in the report.

Why GAO Did This Study
The Navy plans to spend over $43 billion to produce three Ford-class aircraft carriers. The lead ship, CVN 78, is under construction, and preparation work is underway for the second, CVN 79. These ships will feature new technologies designed to increase capability and reduce crew size. GAO was asked to evaluate the progress of the Ford class. This report examines (1) technical, design, and construction challenges to delivering the lead ship within budget and schedule estimates; (2) the Navy's test strategy for demonstrating CVN 78's required capabilities; and (3) actions the Navy is taking to improve CVN 79 cost outcomes. GAO analyzed documents related to mission requirements, acquisition plans and performance, and testing strategies, and interviewed Department of Defense (DOD) and contractor officials.

What GAO Recommends
GAO recommends the Secretary of Defense take several actions aimed at ensuring Ford-class carrier acquisitions are supported by sound requirements and a comprehensive testing strategy, including conducting a cost-benefit analysis of required capabilities and associated costs. GAO is also recommending actions to improve the Navy’s knowledge about CVN 79 capabilities and costs before beginning contract negotiations. DOD concurred with one recommendation, partially concurred with three others, and did not concur with the recommendation to defer CVN 79’s detail design and construction contract award. GAO maintains that DOD’s current schedule for awarding this contract undermines the government’s negotiating position.
 

Maritime Reporter June 2014 Digital Edition
FREE Maritime Reporter Subscription
Latest Maritime News    rss feeds

Shipbuilding

Kleven Shipbuilding Wins IES Pioneer Contract

Norway’s Kleven announced it has signed a shipbuilding contract with Malaysian based joint venture company IES Pioneer Ltd. The vessel is of Norwegian design

Eastern to Build Offshore Vessel for Harvey Gulf

Eastern Shipbuilding announced that on, Wednesday July 16, 2014, Harvey Gulf International Marine, Inc. (HGIM) and Eastern Shipbuilding Group, Inc. (ESG) entered

FORAN Users Meeting (FORUM 2014)

The Eighth FORAN Users Meeting (FORUM 2014) took place June 11-13, 2014 in the Parador de la Granja, Segovia, and when it was over the organizers proclaimed it a great success,

Navy

Sunken WW II Ship Oil Leak Plugged

Atlantic Coast Marine Group, Inc. successfully responds to World War II era motor tanker leaking massive cargo of oil into the Atlantic Ocean's waters. Beaufort,

Maritime Reporter @ 75: The Daily Cartoon

Maritime Reporter & Engineering News was founded by John J. O'Malley (1905-1980) in 1939, and today ranks as the world's largest audited trade publication in the world serving the maritime industry,

Today in U.S. Naval History: July 22

Today in U.S. Naval History - July 22 1802 - Frigate Constellation defeats nine Corsair gunboats off Tripoli. 1905 - Body of John Paul Jones moved to Annapolis, Md.

Finance

Suicide Attack Escalates Libya Violence, Oil Output Slips

Crude output slips for first time since port deal; fresh clashes in Tripoli and Benghazi. Brega oil port seen open in few days. A twin suicide bombing at a Libyan

Pier Damaged at Port Canaveral

Undergoing Repairs While Coast Guard Investigates   The U.S. Coast Guard is investigating a weekend incident that caused pier damage and scattered concrete debris in the harbor on Sunday.

APM Terminals to Sell Container Terminal in Virginia

Port operator APM Terminals, a unit of Denmark's A.P. Moller-Maersk, said it would sell a big U.S. container terminal to infrastructure investor Alinda Capital

Eye on the Navy

Russia Doubts France Will Cancel Warships Sale

A senior Russian official said on Monday he doubted France would cancel its sale of warships to Russia, despite coming under pressure from other Western leaders

Cameron Questions France's Sale of Warships to Russia

British Prime Minister David Cameron on Monday questioned France's plan to sell Mistral helicopter carriers to Russia, saying fulfilling such an order would be

Australian LCHs Bid Farwell

The Australian Navy’s three remaining Landing Craft Heavy auxiliary vessels put on a proud display of thanks to the Cairns community, sailing in formation from the city’s harbor this morning.

 
 
Maritime Careers / Shipboard Positions Maritime Contracts Maritime Security Naval Architecture Port Authority Salvage Ship Electronics Ship Simulators Sonar Winch
rss | archive | history | articles | privacy | terms and conditions | contributors | top maritime news | about us | copyright | maritime magazines
maritime security news | shipbuilding news | maritime industry | shipping news | maritime reporting | workboats news | ship design | maritime business

Time taken: 0.2080 sec (5 req/sec)