GAO Critical of Navy Flat-top Program

MarineLink.com
Friday, September 06, 2013
Artist's rendering of CVN 78

In a new report, the US Government Accountability Office (GAO) states that the Navy faces technical, design, and construction challenges to completing 'Gerald R. Ford' (CVN 78) that have led to significant cost increases and reduced the likelihood that a fully functional ship will be delivered on time. The GAO finds:

The Navy has achieved mixed progress to date developing CVN 78's critical technologies, such as a system intended to more effectively launch aircraft from the ship. In an effort to meet required installation dates aboard CVN 78, the Navy has elected to produce some of these systems prior to demonstrating their maturity--a strategy that GAO's previous work has shown introduces risk of late and costly design changes and rework, and leaves little margin to incorporate additional weight growth in the ship.

In addition, progress in constructing CVN 78 has been overshadowed by inefficient out-of-sequence work, driven largely by material shortfalls, engineering challenges, and delays developing and installing critical technology systems. These events are occurring in a constrained budget environment, even as lead ship costs have increased by over 22 percent since construction authorization in fiscal year 2008--to $12.8 billion. Additional increases could follow due to uncertainties facing critical technology systems and shipbuilder underperformance.

The Navy's strategy for providing timely demonstration of CVN 78 capabilities is hampered by post-delivery test plan deficiencies, Joint Strike Fighter aircraft delays, and reliability shortfalls affecting key ship systems. Additional risk is introduced due to the Navy's plan to conduct integration testing of key systems with the ship at the same time as initial operational test and evaluation (IOT&E). This strategy will constrain opportunities to implement timely, corrective actions if problems are discovered with key ship systems. In addition, significant discoveries during IOT&E could delay demonstration of ship capabilities. The Joint Strike Fighter, intended to operate with the carrier, has faced delays, and there is the likelihood of costly retrofits to the ship to accommodate the aircraft after CVN 78 is delivered to the Navy. But even after the ship commissions, several key ship systems will continue to face significant reliability shortfalls that will likely increase costs to the government and limit the ship's mission effectiveness. The extent of these limitations will not be known until after IOT&E. GAO contemplated making a recommendation to delay CVN 78 commissioning until the ship successfully completes IOT&E. However, based on additional information provided by DOD, GAO decided not to include this recommendation in the report.

Why GAO Did This Study
The Navy plans to spend over $43 billion to produce three Ford-class aircraft carriers. The lead ship, CVN 78, is under construction, and preparation work is underway for the second, CVN 79. These ships will feature new technologies designed to increase capability and reduce crew size. GAO was asked to evaluate the progress of the Ford class. This report examines (1) technical, design, and construction challenges to delivering the lead ship within budget and schedule estimates; (2) the Navy's test strategy for demonstrating CVN 78's required capabilities; and (3) actions the Navy is taking to improve CVN 79 cost outcomes. GAO analyzed documents related to mission requirements, acquisition plans and performance, and testing strategies, and interviewed Department of Defense (DOD) and contractor officials.

What GAO Recommends
GAO recommends the Secretary of Defense take several actions aimed at ensuring Ford-class carrier acquisitions are supported by sound requirements and a comprehensive testing strategy, including conducting a cost-benefit analysis of required capabilities and associated costs. GAO is also recommending actions to improve the Navy’s knowledge about CVN 79 capabilities and costs before beginning contract negotiations. DOD concurred with one recommendation, partially concurred with three others, and did not concur with the recommendation to defer CVN 79’s detail design and construction contract award. GAO maintains that DOD’s current schedule for awarding this contract undermines the government’s negotiating position.
 

Maritime Today


The Maritime Industry's original and most viewed E-News Service

Maritime Reporter May 2016 Digital Edition
FREE Maritime Reporter Subscription
Latest Maritime News    rss feeds

Shipbuilding

STX Sells Lorient Shipyard

The shipbuilding group STX France has offloaded its Lorient shipyard to a naval consortium.    The shipyard, which has produced civil and naval vessels, will be purchased by Kership,

FIO’s New Research Vessel Enters Build Phase

The 78’ research vessel designed and engineered by Boksa Marine Design (BMD) in 2015 is headed to the building phase beginning in June.   BMD contracted with

HII Secures Aircraft Carrier Planning Contract

Huntington Ingalls Industries (HII) was awarded a $152 million contract for advance planning for the construction of the third aircraft carrier in the Gerald R.

Navy

This Day In Naval History - May 24

1917 - The first U.S. convoy left Hampton Roads, Va. to cross the North Atlantic after entering World War I. During the 18 months of war while American vessels escort convoys through the war zone,

HII Secures Aircraft Carrier Planning Contract

Huntington Ingalls Industries (HII) was awarded a $152 million contract for advance planning for the construction of the third aircraft carrier in the Gerald R.

Ingalls Christens Amphibious Transport Dock Portland

Ingalls Shipbuilding, a division of Huntington Ingalls Industries (HII), christened the amphibious transport dock Portland (LPD 27) on May 21 in front of approximately 1,000 guests.

Finance

STX Sells Lorient Shipyard

The shipbuilding group STX France has offloaded its Lorient shipyard to a naval consortium.    The shipyard, which has produced civil and naval vessels, will be purchased by Kership,

DP World Launches $1.2 bln Sukuk Issue to Cover Tender

Dubai-based ports operator DP World launched a seven-year $1.2 billion sukuk issue on Tuesday, a document from lead managers showed.   The issue, structured to

Baltic Index Falls on Weaker Demand

The Baltic Exchange's main sea freight index, tracking rates for ships carrying dry bulk commodities, fell on Tuesday as demand for larger vessel segments declined.

Eye on the Navy

This Day In Naval History - May 24

1917 - The first U.S. convoy left Hampton Roads, Va. to cross the North Atlantic after entering World War I. During the 18 months of war while American vessels escort convoys through the war zone,

HII Secures Aircraft Carrier Planning Contract

Huntington Ingalls Industries (HII) was awarded a $152 million contract for advance planning for the construction of the third aircraft carrier in the Gerald R.

Ingalls Christens Amphibious Transport Dock Portland

Ingalls Shipbuilding, a division of Huntington Ingalls Industries (HII), christened the amphibious transport dock Portland (LPD 27) on May 21 in front of approximately 1,000 guests.

 
 
Maritime Contracts Maritime Security Maritime Standards Naval Architecture Pipelines Pod Propulsion Port Authority Salvage Ship Electronics Sonar
rss | archive | history | articles | privacy | contributors | top maritime news | about us | copyright | maritime magazines
maritime security news | shipbuilding news | maritime industry | shipping news | maritime reporting | workboats news | ship design | maritime business

Time taken: 0.1595 sec (6 req/sec)