GAO Critical of Navy Flat-top Program

MarineLink.com
Friday, September 06, 2013
Artist's rendering of CVN 78

In a new report, the US Government Accountability Office (GAO) states that the Navy faces technical, design, and construction challenges to completing 'Gerald R. Ford' (CVN 78) that have led to significant cost increases and reduced the likelihood that a fully functional ship will be delivered on time. The GAO finds:

The Navy has achieved mixed progress to date developing CVN 78's critical technologies, such as a system intended to more effectively launch aircraft from the ship. In an effort to meet required installation dates aboard CVN 78, the Navy has elected to produce some of these systems prior to demonstrating their maturity--a strategy that GAO's previous work has shown introduces risk of late and costly design changes and rework, and leaves little margin to incorporate additional weight growth in the ship.

In addition, progress in constructing CVN 78 has been overshadowed by inefficient out-of-sequence work, driven largely by material shortfalls, engineering challenges, and delays developing and installing critical technology systems. These events are occurring in a constrained budget environment, even as lead ship costs have increased by over 22 percent since construction authorization in fiscal year 2008--to $12.8 billion. Additional increases could follow due to uncertainties facing critical technology systems and shipbuilder underperformance.

The Navy's strategy for providing timely demonstration of CVN 78 capabilities is hampered by post-delivery test plan deficiencies, Joint Strike Fighter aircraft delays, and reliability shortfalls affecting key ship systems. Additional risk is introduced due to the Navy's plan to conduct integration testing of key systems with the ship at the same time as initial operational test and evaluation (IOT&E). This strategy will constrain opportunities to implement timely, corrective actions if problems are discovered with key ship systems. In addition, significant discoveries during IOT&E could delay demonstration of ship capabilities. The Joint Strike Fighter, intended to operate with the carrier, has faced delays, and there is the likelihood of costly retrofits to the ship to accommodate the aircraft after CVN 78 is delivered to the Navy. But even after the ship commissions, several key ship systems will continue to face significant reliability shortfalls that will likely increase costs to the government and limit the ship's mission effectiveness. The extent of these limitations will not be known until after IOT&E. GAO contemplated making a recommendation to delay CVN 78 commissioning until the ship successfully completes IOT&E. However, based on additional information provided by DOD, GAO decided not to include this recommendation in the report.

Why GAO Did This Study
The Navy plans to spend over $43 billion to produce three Ford-class aircraft carriers. The lead ship, CVN 78, is under construction, and preparation work is underway for the second, CVN 79. These ships will feature new technologies designed to increase capability and reduce crew size. GAO was asked to evaluate the progress of the Ford class. This report examines (1) technical, design, and construction challenges to delivering the lead ship within budget and schedule estimates; (2) the Navy's test strategy for demonstrating CVN 78's required capabilities; and (3) actions the Navy is taking to improve CVN 79 cost outcomes. GAO analyzed documents related to mission requirements, acquisition plans and performance, and testing strategies, and interviewed Department of Defense (DOD) and contractor officials.

What GAO Recommends
GAO recommends the Secretary of Defense take several actions aimed at ensuring Ford-class carrier acquisitions are supported by sound requirements and a comprehensive testing strategy, including conducting a cost-benefit analysis of required capabilities and associated costs. GAO is also recommending actions to improve the Navy’s knowledge about CVN 79 capabilities and costs before beginning contract negotiations. DOD concurred with one recommendation, partially concurred with three others, and did not concur with the recommendation to defer CVN 79’s detail design and construction contract award. GAO maintains that DOD’s current schedule for awarding this contract undermines the government’s negotiating position.
 

Maritime Reporter March 2015 Digital Edition
FREE Maritime Reporter Subscription
Latest Maritime News    rss feeds

Shipbuilding

Largest All-Electric Pipe Bender Starts Operations at Newport News Shipbuilding

Unison has commissioned what is believed to be the largest all-electric tube bending machine ever produced. The machine has started operations at Newport News Shipbuilding,

SeaZip Takes Delivery of Damen Crew Suppliers

On 28 March, SeaZip Offshore Service named two new Damen Fast Crew Suppliers (FCS) 2610 at Damen Shipyards Gorinchem.   The two vessels, named SeaZip 3 and SeaZip 4,

Damen Delivers Stan Patrol Vessel to RBDF

The Royal Bahamas Defence Force (RBDF) has taken delivery of the fourth and final Stan Patrol 4207, named HMBS Rolly Gray. The four Stan Patrol 4207s form part of the six-year Sandy Bottom project.

Navy

Largest All-Electric Pipe Bender Starts Operations at Newport News Shipbuilding

Unison has commissioned what is believed to be the largest all-electric tube bending machine ever produced. The machine has started operations at Newport News Shipbuilding,

Damen Delivers Stan Patrol Vessel to RBDF

The Royal Bahamas Defence Force (RBDF) has taken delivery of the fourth and final Stan Patrol 4207, named HMBS Rolly Gray. The four Stan Patrol 4207s form part of the six-year Sandy Bottom project.

China's Artificial Islands in South China Sea Raises U.S. Concerns

China has been building artificial islands on reefs in the many disputed areas around the South China Sea. The unprecedented land reclamation currently being conducted

Finance

BMT Partners with Aage Hempel

BMT SMART (BMT),  has announced  that Aage Hempel has become an accredited service partner.  This agreement will provide both organizations with the opportunity

Tanker Backlog Builds at Basra

Ships face up to a three week wait; bad weather in February delayed loading, created backlog. * April intake to be reduced to clear backlog By Keith Wallis SINGAPORE,

U.S. Port Delay Boost February Air Freight

Global air freight volumes rose 11.7 percent year-on-year in February, driven by the Chinese New Year, the International Air Transport Association said on Wednesday.

Eye on the Navy

Navy Awards Austal $691M for Two Littoral Combat Ships

The U.S. Navy has ordered two new littoral combat ships from Austal, the shipbuilder said in a press release today. The two orders, worth $691 million, are part

Damen Delivers Stan Patrol Vessel to RBDF

The Royal Bahamas Defence Force (RBDF) has taken delivery of the fourth and final Stan Patrol 4207, named HMBS Rolly Gray. The four Stan Patrol 4207s form part of the six-year Sandy Bottom project.

China's Artificial Islands in South China Sea Raises U.S. Concerns

China has been building artificial islands on reefs in the many disputed areas around the South China Sea. The unprecedented land reclamation currently being conducted

 
 
Maritime Careers / Shipboard Positions Maritime Contracts Maritime Security Maritime Standards Offshore Oil Pipelines Pod Propulsion Ship Electronics Ship Repair Sonar
rss | archive | history | articles | privacy | terms and conditions | contributors | top maritime news | about us | copyright | maritime magazines
maritime security news | shipbuilding news | maritime industry | shipping news | maritime reporting | workboats news | ship design | maritime business

Time taken: 0.2381 sec (4 req/sec)