GAO Critical of Navy Flat-top Program

MarineLink.com
Friday, September 06, 2013
Artist's rendering of CVN 78

In a new report, the US Government Accountability Office (GAO) states that the Navy faces technical, design, and construction challenges to completing 'Gerald R. Ford' (CVN 78) that have led to significant cost increases and reduced the likelihood that a fully functional ship will be delivered on time. The GAO finds:

The Navy has achieved mixed progress to date developing CVN 78's critical technologies, such as a system intended to more effectively launch aircraft from the ship. In an effort to meet required installation dates aboard CVN 78, the Navy has elected to produce some of these systems prior to demonstrating their maturity--a strategy that GAO's previous work has shown introduces risk of late and costly design changes and rework, and leaves little margin to incorporate additional weight growth in the ship.

In addition, progress in constructing CVN 78 has been overshadowed by inefficient out-of-sequence work, driven largely by material shortfalls, engineering challenges, and delays developing and installing critical technology systems. These events are occurring in a constrained budget environment, even as lead ship costs have increased by over 22 percent since construction authorization in fiscal year 2008--to $12.8 billion. Additional increases could follow due to uncertainties facing critical technology systems and shipbuilder underperformance.

The Navy's strategy for providing timely demonstration of CVN 78 capabilities is hampered by post-delivery test plan deficiencies, Joint Strike Fighter aircraft delays, and reliability shortfalls affecting key ship systems. Additional risk is introduced due to the Navy's plan to conduct integration testing of key systems with the ship at the same time as initial operational test and evaluation (IOT&E). This strategy will constrain opportunities to implement timely, corrective actions if problems are discovered with key ship systems. In addition, significant discoveries during IOT&E could delay demonstration of ship capabilities. The Joint Strike Fighter, intended to operate with the carrier, has faced delays, and there is the likelihood of costly retrofits to the ship to accommodate the aircraft after CVN 78 is delivered to the Navy. But even after the ship commissions, several key ship systems will continue to face significant reliability shortfalls that will likely increase costs to the government and limit the ship's mission effectiveness. The extent of these limitations will not be known until after IOT&E. GAO contemplated making a recommendation to delay CVN 78 commissioning until the ship successfully completes IOT&E. However, based on additional information provided by DOD, GAO decided not to include this recommendation in the report.

Why GAO Did This Study
The Navy plans to spend over $43 billion to produce three Ford-class aircraft carriers. The lead ship, CVN 78, is under construction, and preparation work is underway for the second, CVN 79. These ships will feature new technologies designed to increase capability and reduce crew size. GAO was asked to evaluate the progress of the Ford class. This report examines (1) technical, design, and construction challenges to delivering the lead ship within budget and schedule estimates; (2) the Navy's test strategy for demonstrating CVN 78's required capabilities; and (3) actions the Navy is taking to improve CVN 79 cost outcomes. GAO analyzed documents related to mission requirements, acquisition plans and performance, and testing strategies, and interviewed Department of Defense (DOD) and contractor officials.

What GAO Recommends
GAO recommends the Secretary of Defense take several actions aimed at ensuring Ford-class carrier acquisitions are supported by sound requirements and a comprehensive testing strategy, including conducting a cost-benefit analysis of required capabilities and associated costs. GAO is also recommending actions to improve the Navy’s knowledge about CVN 79 capabilities and costs before beginning contract negotiations. DOD concurred with one recommendation, partially concurred with three others, and did not concur with the recommendation to defer CVN 79’s detail design and construction contract award. GAO maintains that DOD’s current schedule for awarding this contract undermines the government’s negotiating position.
 

Maritime Reporter June 2014 Digital Edition
FREE Maritime Reporter Subscription
Latest Maritime News    rss feeds

Shipbuilding

Fincantieri to Build Third New Princess Cruises Ship

Fincantieri says it has signed an agreement with Carnival Corp. to build  the new cruise ship for its Princess Cruises brand at a cost of about 600 million euros.

ATB Barge Project for Murray & Associates

Murray & Associates, LLC has been commissioned to deliver a comprehensive design package for an 185,000 BBL Chemical Tank Barge new construction project. The

Gladding-Hearn Builds New Boat for Delaware Pilots

The Delaware pilots association has ordered its third pilot boat of the popular Chesapeake class from Gladding-Hearn Shipbuilding, Duclos Corporation. Delivery

Navy

Admiral on U.S. Navy & Asia Pacific Re-balancing Act

The commander of U.S. Pacific Command has briefed Pentagon reporters, discussing the U.S. rebalance to the Asia-Pacific region, successful engagement with partners

Hellfire Missile Firing a First for New Navy Helicopters

The Royal Australian Navy’s newest maritime combat helicopter, the MH-60R Seahawk ‘Romeo’, has successfully fired its first ‘Hellfire’ missile in the United States.

BAE Systems Awarded Two Navy Contract Modifications

The US Department of Defense informs it has awarded separate contracts to BAE Systems in Jacksonville and in Norfolk for ship repairs and modifications as follows: 1.

Finance

Asia Dry Bulk Capesize Rates Stay Flat

Rates for capesize bulk carriers on key Asian routes are set to remain in the doldrums next week, staying flat or gaining just a few cents as an oversupply of ships weighs on cargo availability,

ISC Profit Slip in Q2 2014 but Pay Dividend

International Shipholding Corporation (ISC) has announced financial results for the quarter ended June 30, 2014, summarized here: Net Loss he Company reported a net loss of $664,

Hornbeck Offshore Ride High on Q2 2014 Results

Hornbeck Offshore Services, Inc. has announced its financial results for the second quarter ended June 30, 2014.  Following are highlights for this period and excerpts

Eye on the Navy

Hellfire Missile Firing a First for New Navy Helicopters

The Royal Australian Navy’s newest maritime combat helicopter, the MH-60R Seahawk ‘Romeo’, has successfully fired its first ‘Hellfire’ missile in the United States.

The Martitime Security Focus Is Shifting

Former Vice-Admiral and Commander-in-chief of the German Navy Hans-Joachim Stricker, President of the German Maritime Institute (DMI), believes that in terms of

VSTEP Wins Mexican Navy Simulator Contract

The Mexican Navy selected VSTEP to supply a Class A NAUTIS Full Mission Bridge (FMB) Simulator and 24 NAUTIS desktop trainer stations for the Naval Academy in Veracruz.

 
 
Maritime Contracts Maritime Security Maritime Standards Naval Architecture Navigation Pod Propulsion Salvage Ship Repair Shipbuilding / Vessel Construction Sonar
rss | archive | history | articles | privacy | terms and conditions | contributors | top maritime news | about us | copyright | maritime magazines
maritime security news | shipbuilding news | maritime industry | shipping news | maritime reporting | workboats news | ship design | maritime business

Time taken: 0.1656 sec (6 req/sec)