Kazakhstan "Disappointed" Over Kashagan Setback

Posted by Michelle Howard
Thursday, April 17, 2014
Caspian Sea (Photo: Wiki Commons)

Kazakhstan's oil and gas minister said on Thursday he was disappointed over the slow development of the giant Kashagan oilfield, but he saw no legal reasons to put pressure on the consortium which oversees the offshore project.

The Central Asian nation of 17 million relies heavily on oil exports, and the setback in development of the huge Kashagan field could be a drag on state coffers.

Delayed output at Kashagan has unsettled Kazakh authorities, which have already sued the consortium operating the field for 134 billion tenge ($737 million) over ecological damage, but on Thursday they signalled the possibility of no further penalties.

"We can't push (the consortium). This is a huge and dangerous field, and we can't pressure legally," Uzakbai Karabalin said after meeting members of the North Caspian Operating Company (NCOC) consortium, which include Eni, Exxon Mobil, Royal Dutch Shell and Kazakh state-run KazMunaiGas.

"I said that we are hugely disappointed by the way the project is progressing," the minister said.

NCOC also includes Japan's Inpex with 7.56 percent and China National Petroleum Corp (CNPC) with 8.33 percent, which it bought from ConocoPhillips last year.

The consortium said last month it would challenge the fine, potentially raising tensions with the government, which in recent years has become more assertive in dealing with foreign investors and has used legal action as leverage to increase participation in some energy projects.

Production at the offshore deposit, the world's biggest oil find in 35 years, started in September but was halted in early October after the detection of gas leaks in the $50 billion project's pipeline network.

The government had great expectations for Kashagan to start producing oil last year and officials had said they hoped to see it produce 22 million barrels of crude by the end of the year.

The minister didn't comment about the possible costs of the repair work, reiterating that the authorities expect the results of the pipeline examination by the end of May.

"If it is confirmed that there are cracks in the sea part of the pipeline, then it will indicate the situation is getting worse as the sea section of the pipe should also be replaced. Then, there will be no output this year," Karabalin said.

(Reporting by Raushan Nurshayeva; writing by Vladimir Soldatkin, editing by Megan Davies and David Evans)

Maritime Reporter June 2014 Digital Edition
FREE Maritime Reporter Subscription
Latest Maritime News    rss feeds

Energy

Nation’s Vessel Operators Join EPA as SmartWay Affiliate

The American Waterways Operators, a 350-member trade association representing the U.S. tugboat, towboat and barge industry, announced today that it joined the SmartWay Transport Partnership,

Iraqi Kurdish Oil Nears US Port Despite Concern in Washington

A tanker carrying crude oil from Iraqi Kurdistan is just two days away from arriving at a U.S. port, according to ship tracking satellites, despite Washington's

New Crewboat Design for Offshore O&G Market

Upgraded crewboat design employs carbon-reinforced composite materials and is lighter, faster and more fuel-efficient than alternatives. Marine Oil Transportation

News

House Subcommittee Hearing Highlights “Dismal State” of U.S. Icebreaking Capability

At the July 23, 2014, hearing of the House Subcommittee on Coast Guard and Maritime Transportation on “Implementing U.S. Policy in the Arctic” the committee chairman, Rep.

Iraqi Kurdish Oil Nears US Port Despite Concern in Washington

A tanker carrying crude oil from Iraqi Kurdistan is just two days away from arriving at a U.S. port, according to ship tracking satellites, despite Washington's

Phillips 66 Marine Fueling Facility Nears Completion

Phillips 66’s previously announced marine over-the-water fueling facility at its Richmond, Calif. terminal is nearing completion. The facility, located on Canal Boulevard, and known as Pier No.

Offshore Energy

New Crewboat Design for Offshore O&G Market

Upgraded crewboat design employs carbon-reinforced composite materials and is lighter, faster and more fuel-efficient than alternatives. Marine Oil Transportation

2,545 Candidates Vie for 11 Positions at Maersk Drilling

Maersk Drilling reported 2,545 applicants for the 11 MITAS engineer positions available within the company in 2014. The Maersk International Technology and Science Program,

GDI Awards N-KOM US$110-M Contracts

Gulf Drilling International (GDI) Limited, a subsidiary of Gulf International Services (GIS), the largest oilfield service company in Qatar, has awarded two contracts

 
 
Maritime Careers / Shipboard Positions Maritime Contracts Maritime Security Maritime Standards Naval Architecture Navigation Salvage Ship Repair Shipbuilding / Vessel Construction Sonar
rss | archive | history | articles | privacy | terms and conditions | contributors | top maritime news | about us | copyright | maritime magazines
maritime security news | shipbuilding news | maritime industry | shipping news | maritime reporting | workboats news | ship design | maritime business

Time taken: 0.5038 sec (2 req/sec)