Toxics Dredging Resumes in the Hudson

Posted by Eric Haun
Monday, May 05, 2014
Photo: EPA

Dredging of toxics resumes in upper Hudson River for fifth season; PCB cleanup designed to restore Hudson River; created hundreds of new jobs

The U.S. Environmental Protection Agency (EPA) announced today that dredging operations are expected to resume on Wednesday in the Upper Hudson River. In 2014, dredging will begin south of Schuylerville, New York and proceed south towards Troy. Dredging will also occur in a two-mile section of river near Fort Miller that is not easily accessed by boat. Dredging is being conducted to remove sediment from the river bottom that is contaminated with polychlorinated biphenyls (PCBs). PCBs were used in the production of electrical equipment at two General Electric facilities located in Hudson Falls and Fort Edward, New York. Over a 30-year period, ending in the late 1970’s, an estimated 1.3 million pounds of PCBs entered the river from the two GE plants. PCBs are potentially cancer-causing chemicals that build up in the food chain.

The dredging project, which began in 2009, targets approximately 2.65 million cubic yards of PCB-contaminated sediment from a 40-mile stretch of river between Fort Edward and Troy, New York. To date, more than 1.9 million cubic yards - approximately 70 percent - has been removed. The dredging goal for 2014 is to remove 350,000 cubic yards of contaminated sediment. It is anticipated that dredging could be completed during the 2015 dredging season. The remaining in-river work associated with habitat reconstruction and the closing of the Fort Edward, New York sediment dewatering and processing facility will follow the dredging.

“The EPA is now at a point from which we can see the finish line for this momentous cleanup that was decades in the making,” said Regional Administrator Judith A. Enck. “With nearly two million cubic yards of toxic sediment already removed, the EPA has taken an important step toward a healthier Hudson River and healthier river communities.”

Some challenging areas remain, but EPA worked with GE to identify creative solutions to meet these challenges. For example, the original plan called for sediment that will be dredged from the section of the river that cannot be reached directly by boat to be moved through the community in trucks. With input from the EPA, the community and the state of New York, GE revised its original plan to instead transfer the material to barges for transport to the sediment processing facility.

As the project continues further south in 2014, dredging will occur in discrete locations spread across 20-30 miles. Transporting the dredged material north by barge to GE’s sediment dewatering and processing facility located on the Champlain Canal in Fort Edward, New York, will require longer travel times and passage through several locks. Several of the areas that remain to be dredged are also logistically challenging, including those near dams, shallow areas around islands and the landlocked section of river.

During the dredging season, mechanical dredges mounted on deck barges use environmental dredge buckets to place dredged sediment into barges. Tugboats push the loaded barges to GE’s Fort Edward dewatering and sediment-processing facility. In the land-locked section of river, where direct water-transport of loaded barges to the processing facility isn’t possible due to the presence of dams at its north and south end, the loaded barges will be pushed by tugboat to a trans-loading station on a narrow section of land on the east shoreline of the river, south of the Thompson Island Dam. Once there, the material in the barge will be off-loaded into a bin on land and then re-loaded into another barge in the Champlain Canal “land-cut.” From there the barges will be pushed by tugboat upriver to the Fort Edward processing facility.

Once the loaded barges arrive at the processing facility, debris and water are removed. The coarse material is then separated from the fine sediment that contains most of the PCB contamination. The coarse material is staged in a pile before it is transported off-site by train to a properly licensed landfill. The remaining sediment is pumped to the dewatering facility where large filter presses squeeze water from the sediment. The water is treated to meet water quality standards before it is released back into the Champlain Canal. The remaining sediment and debris are also loaded onto railcars and transported by train to the permitted, off-site disposal facilities out of state.

In 2014, two shoreline support properties will be used for placing equipment in the river and staging the clean sand and gravel that is used to cover previously dredged areas. The Saratoga Barge Loading Area, which was also used as a support property in 2013, is located on Route 4 in Northumberland, about a mile north of Schuylerville. For 2014, an additional shoreline support property is being constructed on the west side of the river in Northumberland, within the landlocked section of river, to support the dredging work there.

Approximately 160,000 cubic yards of PCB-contaminated sediment is targeted for removal from 29-acres of river bottom in the land-locked section of river. The work is expected to start in June once the site is constructed to allow mobilization of equipment into the river. Once the work is completed in this area the trans-loading station on the eastern shoreline and the facility in Fort Miller will be returned to their previous condition.

Water quality monitoring will continue to measure PCB levels at various downstream monitoring locations and to track the movement of dredged material downriver. Air monitors are also placed near dredging operations and around the processing facility while work is underway. The EPA also requires other monitoring to reduce the effects of dredging and dewatering operations on surrounding communities.

The EPA is overseeing the dredging project that is being conducted by GE under the terms of a 2006 legal agreement. The New York State Department of Environmental Conservation is supporting the EPA in overseeing the cleanup.

epa.gov
 


Environmental

Doing Business Differently to Meet Sustainability Targets: DNV GL

Pressure is mounting on the global oil and gas industry to reduce environmental footprint at the same time as the industry is under significant cost pressure.    Since

GoM Operators Evacuating Ahead of Storm

Offshore oil and gas operators in the Gulf of Mexico are evacuating platforms and rigs in the path of Tropical Depression No. 9.   The Bureau of Safety and Environmental

NParks, Keppel in S$2.08 mln Partnership for Restoring Singapore Forest Wetlands

The National Parks Board (NParks) and Keppel Corporation today unveiled plans for a partnership to restore the freshwater forest wetland ecosystem historically

Dredging

Royal IHC Upgrades TSHD Pump for Van Oord

Royal IHC informs it has completed the upgrade of the underwater pump and jet water system on trailing suction hopper dredger (TSHD) VOLVOX TERRANOVA for Van Oord.

Damen Repairs Two Van Oord Barges

Damen Shiprepair Vlissingen recently completed a broad scope of maintenance and repair works on the Van Oord-owned Split Hopper Barges Jan Blanken and Jan Leeghwater.

ROV Dredger Goes to Work in Singapore

Ellicott Dredge Technologies (EDT) announced the successful start up and installation of a state-of-the-art Mud Cat brand remotely operated vehicle (ROV) at the

News

Japanese Yards Mull Shipbuilding Alliance

Four major Japanese shipbuilders are in discussions to form an alliance in hopes of riding out the industry slump.   Mitsubishi Heavy Industries, Ltd. (MHI) announced

Another Tug Launched for Suderman & Young

Eastern Shipbuilding Group, Inc. said it launched on August 15, 2016 the final vessel in a series of four Z-Tech Class Terminal & Escort Tugs being constructed for Suderman & Young Towing Company.

OSV firm Farstad Continues Restructuring Talks

Supply firm Farstad Shipping's CEO Karl Johan Bakken repeats is in stand-still agreement with lenders until Oct. 1   Notable disclosures: * CEO says is talking

Government Update

India Shipping Ministry Enlarges Scope of Sagarmala

India's Ministry of Shipping has formulated a revised Central Sector Scheme to provide financial support to Major and Non-Major Ports as well as State Governments

California: A Strong Shipbuilding State

Fifth in the nation for direct employment, California shipbuilding and repair industry supports nearly 35,000 jobs; Maritime Administrator highlights economic importance

White House Sees a Path to Approval of Pacific Trade Deal

The White House on Monday said it was hopeful it could win congressional approval of the Trans-Pacific Partnership trade pact before President Barack Obama leaves office,

 
 
Maritime Careers / Shipboard Positions Maritime Contracts Maritime Standards Naval Architecture Navigation Pod Propulsion Ship Repair Shipbuilding / Vessel Construction Sonar Winch
rss | archive | history | articles | privacy | contributors | top maritime news | about us | copyright | maritime magazines
maritime security news | shipbuilding news | maritime industry | shipping news | maritime reporting | workboats news | ship design | maritime business

Time taken: 0.1411 sec (7 req/sec)