Drilling Rig Status Update from Rowan

Press Release
Sunday, December 23, 2012

Rowan Companies plc gives an update on notable events.

  • EXL I:  Changed day rate to mid $220s (previously mid $210s) due to amortization adjustment.
  • J.P. Bussell:  Rig is expected to be off rate for five days in 1Q 2013.
  • Scooter Yeargain:  Rig is expected to enter the shipyard in January 2013 (previously March 2013) for 105 days (previously 135 days) for customer-required equipment upgrades.
  • Gorilla VI:  Off rate time in 4Q 2012 was eight days instead of the previously expected 25 days.
  • Cecil Provine:  Off rate time in 4Q 2012 was 49 days instead of the previously expected 57 days.
  • Rowan Norway:  Rig is currently in the shipyard for contract requirements and is expected to commence operations early January 2013 (previously mid December 2012).  Rig is expected to be in the shipyard for approximately 80 days (previously 60 days) in 4Q 2012, part of which may be compensated.  If necessary, the day rate will be adjusted to reflect compensated shipyard days in a subsequent fleet status.  Changed day rate to the mid $350s (previously mid $360s) due to downward revision in expected reimbursement for modifications.
  • Rowan Stavanger: Off rate time in 4Q 2012 was 25 days instead of the previously expected 16 days.  Following completion of the well for Talisman in Norway in March 2013, the rig will operate in the U.K. sector of the North Sea at a day rate in the mid $240s through November 2013.  While the rig is working in the U.K. sector of the Rowan Viking:  Rig will enter the shipyard in February 2014 for equipment modifications and inspections for approximately 105 days (previously 30 days) prior to commencing its contract with Lundin for 15 wells in the Norwegian sector of the North Sea estimated to start in 2Q 2014.

The Company states it will not realize any day rate revenue during periods of off rate time, and crew costs will be capitalized during rig modifications and/or upgrades.

 

Maritime Today


The Maritime Industry's original and most viewed E-News Service

Maritime Reporter July 2016 Digital Edition
FREE Maritime Reporter Subscription
Latest Maritime News    rss feeds

Contracts

Baltic Index Falls on Weak Freight Rates

The Baltic Exchange's main sea freight index, tracking rates for ships carrying dry bulk commodities, fell on Monday due to weaker rates across all segments, except handysizes.

As Market Sours, LPG Tankers Anchor off Singapore

Record U.S. LPG exports to Asia flip market into a glut. Last year, liquefied petroleum gas (LPG) supplied to Asia was being snapped up by petrochemical makers.

Eni Cancels Vessel Deal with Viking Supply Ships

Viking Supply Ships A/S (VSS) has received an early termination notice of the contract for the Ice-class 1A AHTS “Njord Viking”. The vessel has been working for

Offshore

MOL Signs Long-Term Charter with Uruguayan JV for FSRU

Japanese shipping company Mitsui O.S.K. Lines, has, through its wholly-owned subsidiary Lakler S.A., agreed to conclude a charter contract with Gas Sayago, for

Migrants Survivors Tell of Struggle at Sea

The bodies of 21 women and one man were brought ashore to Sicily on Friday as fellow migrants described scenes of panic and violence when water poured into their dinghy.

Three Keppel Dredgers for Jan De Nul

Keppel Offshore & Marine Ltd (Keppel O&M)'s wholly owned subsidiary Keppel Singmarine Pte Ltd (Keppel Singmarine) has secured contracts from Jan De Nul Group to

Offshore Energy

Eni Cancels Vessel Deal with Viking Supply Ships

Viking Supply Ships A/S (VSS) has received an early termination notice of the contract for the Ice-class 1A AHTS “Njord Viking”. The vessel has been working for

MOL Signs Long-Term Charter with Uruguayan JV for FSRU

Japanese shipping company Mitsui O.S.K. Lines, has, through its wholly-owned subsidiary Lakler S.A., agreed to conclude a charter contract with Gas Sayago, for

Ithaca’s FPF-1 platform to be moved to Stella field

Ithaca Energy Inc. reports that the "FPF-1" floating production facility has completed the required inclination test as planned and departed the Remontowa shipyard in Gdansk, Poland.

 
 
Maritime Careers / Shipboard Positions Maritime Standards Naval Architecture Navigation Pipelines Pod Propulsion Salvage Ship Electronics Ship Repair Sonar
rss | archive | history | articles | privacy | contributors | top maritime news | about us | copyright | maritime magazines
maritime security news | shipbuilding news | maritime industry | shipping news | maritime reporting | workboats news | ship design | maritime business

Time taken: 0.1051 sec (10 req/sec)