Drilling Rig Status Update from Rowan

Press Release
Sunday, December 23, 2012

Rowan Companies plc gives an update on notable events.

  • EXL I:  Changed day rate to mid $220s (previously mid $210s) due to amortization adjustment.
  • J.P. Bussell:  Rig is expected to be off rate for five days in 1Q 2013.
  • Scooter Yeargain:  Rig is expected to enter the shipyard in January 2013 (previously March 2013) for 105 days (previously 135 days) for customer-required equipment upgrades.
  • Gorilla VI:  Off rate time in 4Q 2012 was eight days instead of the previously expected 25 days.
  • Cecil Provine:  Off rate time in 4Q 2012 was 49 days instead of the previously expected 57 days.
  • Rowan Norway:  Rig is currently in the shipyard for contract requirements and is expected to commence operations early January 2013 (previously mid December 2012).  Rig is expected to be in the shipyard for approximately 80 days (previously 60 days) in 4Q 2012, part of which may be compensated.  If necessary, the day rate will be adjusted to reflect compensated shipyard days in a subsequent fleet status.  Changed day rate to the mid $350s (previously mid $360s) due to downward revision in expected reimbursement for modifications.
  • Rowan Stavanger: Off rate time in 4Q 2012 was 25 days instead of the previously expected 16 days.  Following completion of the well for Talisman in Norway in March 2013, the rig will operate in the U.K. sector of the North Sea at a day rate in the mid $240s through November 2013.  While the rig is working in the U.K. sector of the Rowan Viking:  Rig will enter the shipyard in February 2014 for equipment modifications and inspections for approximately 105 days (previously 30 days) prior to commencing its contract with Lundin for 15 wells in the Norwegian sector of the North Sea estimated to start in 2Q 2014.

The Company states it will not realize any day rate revenue during periods of off rate time, and crew costs will be capitalized during rig modifications and/or upgrades.

 

Maritime Reporter April 2015 Digital Edition
FREE Maritime Reporter Subscription
Latest Maritime News    rss feeds

Contracts

Double Order for Super Gloria Reachstacker

Kalmar, part of Cargotec, has gained an order for two Super Gloria reachstackers from Tadarsa Logistics S.L. in Aviles, Spain. The largest reachstackers ever built,

Algoma Central Orders New Great Lakes Ships

Algoma Central Corporation announces $160 million investment in fleet expansion and fleet renewal   Algoma Central Corporation announced that it has acquired

Russia, France Close to Deal on Mistrals

Russia and France are close to reaching an agreement for Paris to cancel a frozen contract on the sale of Mistral helicopter carriers and reimburse Moscow, a Russian

Offshore

Falklands' Oil Drilling at Isobel Deep Suspended

Oil explorers drilling in the waters north of the Falkland Islands have suspended work on the second well of their 2015 current six-well drilling campaign after a technical problem.

Arctic Nations to Fight Climate Change Despite Russia Tensions

The eight Arctic Council nations pledged on Friday to do more to combat climate change that is shrinking the vast frigid region, with countries trying to put

OSV Technology: Notable Designs & Deliveries

Though the market for Offshore Support Vessels (OSVs) is soft, advances in technology, fit and finish in  the sector is unrivaled in any other maritime niche over the past five years.

Offshore Energy

Falklands' Oil Drilling at Isobel Deep Suspended

Oil explorers drilling in the waters north of the Falkland Islands have suspended work on the second well of their 2015 current six-well drilling campaign after a technical problem.

Four Petrobras Platforms Halt Output Due to Oil Leak

Four Petrobras oil platforms off the northeast coast of Brazil have halted production after a leak of about 7,000 liters of oil was detected coming from a pipeline linking them,

Huat Retires as Non-Ex Dir. of ST Engineering

Singapore Technologies Engineering Ltd (ST Engineering) today announced the retirement of Mr Quek Poh Huat as non-executive Director of the Company at its Annual General Meeting on 23 April 2015.

 
 
Maritime Careers / Shipboard Positions Maritime Contracts Maritime Security Maritime Standards Navigation Offshore Oil Pipelines Salvage Ship Electronics Ship Repair
rss | archive | history | articles | privacy | contributors | top maritime news | about us | copyright | maritime magazines
maritime security news | shipbuilding news | maritime industry | shipping news | maritime reporting | workboats news | ship design | maritime business

Time taken: 0.1590 sec (6 req/sec)