Rowan Companies plc gives an update on notable events.

  • EXL I:  Changed day rate to mid $220s (previously mid $210s) due to amortization adjustment.
  • J.P. Bussell:  Rig is expected to be off rate for five days in 1Q 2013.
  • Scooter Yeargain:  Rig is expected to enter the shipyard in January 2013 (previously March 2013) for 105 days (previously 135 days) for customer-required equipment upgrades.
  • Gorilla VI:  Off rate time in 4Q 2012 was eight days instead of the previously expected 25 days.
  • Cecil Provine:  Off rate time in 4Q 2012 was 49 days instead of the previously expected 57 days.
  • Rowan Norway:  Rig is currently in the shipyard for contract requirements and is expected to commence operations early January 2013 (previously mid December 2012).  Rig is expected to be in the shipyard for approximately 80 days (previously 60 days) in 4Q 2012, part of which may be compensated.  If necessary, the day rate will be adjusted to reflect compensated shipyard days in a subsequent fleet status.  Changed day rate to the mid $350s (previously mid $360s) due to downward revision in expected reimbursement for modifications.
  • Rowan Stavanger: Off rate time in 4Q 2012 was 25 days instead of the previously expected 16 days.  Following completion of the well for Talisman in Norway in March 2013, the rig will operate in the U.K. sector of the North Sea at a day rate in the mid $240s through November 2013.  While the rig is working in the U.K. sector of the Rowan Viking:  Rig will enter the shipyard in February 2014 for equipment modifications and inspections for approximately 105 days (previously 30 days) prior to commencing its contract with Lundin for 15 wells in the Norwegian sector of the North Sea estimated to start in 2Q 2014.

The Company states it will not realize any day rate revenue during periods of off rate time, and crew costs will be capitalized during rig modifications and/or upgrades.

 

Maritime Reporter September 2014 Digital Edition
FREE Maritime Reporter Subscription
Latest Maritime News    rss feeds

Contracts

Wärtsilä, Diesel United Renew Pact

Wärtsilä and Diesel United Ltd in Japan have signed a ten-year renewal of their co-operation agreement for the sale, manufacturing and servicing of Wärtsilä low-speed marine engines.

Delta "T" Hooks for Offshore Customer

Gaining further ground into the offshore crane market, Delta "T" Systems supplied Cranston Eagle hooks to crane manufacturer Appleton Marine, Inc.   These cranes

China to Import 335 MT of Naphtha, Wants More

China is set to import more than 335,000 tonnes of naphtha and diesel, rare moves for the world's no. 2 oil consumer given it has been self-sufficient at meeting domestic oil product demand,

Offshore

U.S. Drillers Cut Rigs to Lowest since August

Energy companies have reduced the number of rigs drilling for oil in the United States to the lowest since August, shifting more rigs in favor of natural gas as crude prices dive,

Arctic Oil: Bourbon to Enter Arctic Market in 2016

Bourbon plans to enter the growing Arctic Offshore market in 2016 with a new Anchor Handling Tug Supply (AHTS) vessel built by the Vard shipyard. This AHTS (Anchor

Total CEO: EU Must Fight US Crude Export Law

First major public appearance of new Total head; he challenges European politicians to fight US ban. The new head of French energy major Total challenged Europe to fight Washington over the U.

Offshore Energy

U.S. Drillers Cut Rigs to Lowest since August

Energy companies have reduced the number of rigs drilling for oil in the United States to the lowest since August, shifting more rigs in favor of natural gas as crude prices dive,

Total CEO: EU Must Fight US Crude Export Law

First major public appearance of new Total head; he challenges European politicians to fight US ban. The new head of French energy major Total challenged Europe to fight Washington over the U.

Ensco plc Reports 3Q, 2014 Results

Ensco plc  today reported earnings per share from continuing operations of $1.93 in third quarter 2014, up 16% from $1.66 in third quarter 2013. Adjusted for a $0.

 
 
Maritime Careers / Shipboard Positions Maritime Security Maritime Standards Offshore Oil Pod Propulsion Port Authority Salvage Ship Simulators Shipbuilding / Vessel Construction Winch
rss | archive | history | articles | privacy | terms and conditions | contributors | top maritime news | about us | copyright | maritime magazines
maritime security news | shipbuilding news | maritime industry | shipping news | maritime reporting | workboats news | ship design | maritime business

Time taken: 0.1528 sec (7 req/sec)