Divers Replace USS Taylor CPP Hub, Avoid Dry-Docking

Posted by George Backwell
Tuesday, May 06, 2014
USS Taylor: USN photo

The Controllable Pitch Propeller (CPP) Hub of the 'USS Taylor' (FFG 50) was replaced underwater in Souda Bay, Greece, the warship having earlier suffered significant damage to its propeller blades while underway in the Black Sea, apprises Norfolk Ship Support Activity (NSSA).

"NSSA RMC Quality Assurance (QA) Department dispatched Non-Destructive Testing (NDT) technicians overseas to perform an NDT examination of the Main Reduction Gear, to assess its capabilities after the sustaining damages," said NSSA Hydraulics and Ship's Controls Branch Head Richard Krewinghaus.


Inspections of the CPP system by NSSA's Hydraulics and Ship's Controls Branch in conjunction with NSSA's QA Department and Steam and Main Propulsion Branch, indicated that the damage was isolated to the CPP hub and propeller blades.

"Underwater replacement of the hub created several unforeseen challenges, which our guys had to overcome on the fly. It was a tremendous learning experience," said Krewinghaus.

NSSA, working with NAVSEA and the original equipment manufacturer, were given guidance during removal of the damaged hub and installation of the replacement hub. 

NSSA's dive locker also provided assistance, logging 221 dives (equating to more than 41,000 minutes of bottom time assessments and repairs).


"NAVSEA provided our team with guidance and procedures on the hub change out via their engineering technicians and we performed the work as quickly as we could," said NSSA Master Diver Kelly Polk. "We went out there to solve a problem, got in the middle of the job and we were able to complete it. This repair hopefully set the standard for completing waterborne hub repairs."



To aid in a quicker repair, assets were removed from a decommissioned FFG and transported to NSSA headquarters in Norfolk where they were disassembled, repaired, cleaned and packed for shipping.

"Within one hour of the valves' arrival in Souda Bay, they were installed and the system was adjusted and operating properly. This allowed the pier side portion of testing to be completed that night and the ship was then prepared for underway testing," said Krewinghaus.



Taylor made all required preparations to get underway in parallel with the repair effort. Underway testing included a full power run with a hull vibration survey, and an emergency crash back - all of which the ship successfully completed - thereby ensuring she was fully capable of resuming her mission in support of the U.S. 6th Fleet.


Maritime Reporter August 2014 Digital Edition
FREE Maritime Reporter Subscription
Latest Maritime News    rss feeds

People & Company News

Specialised Reefer Container Operators can Thrive: DMR

Despite growing competition from container lines, specialised reefer operators can still thrive, according to Drewry’s latest Reefer Shipping Market Annual Review & Forecast,

HERCULES-2 Phoenix Rises from the Ashes

Wärtsilä Corporation advises that the HERCULES R&D programme to develop large engine technologies, which was initiated in 2004 as a joint vision by the two major European engine manufacturing groups,

Short-Term Perils of Lower Oil Prices: DW Monday

At present we are seeing lower oil prices as a function of softer demand growth in both Europe and China combined with recent output increases from OPEC, particularly Libya,

Ship Repair & Conversion

ONR Funds UW Oceanographic R/V Refit Contract

The US Department of Defense informs that the University of Washington (UW), Seattle, Washington, is being awarded a $12,776,050 cost reimbursement contract for

Two WSFs Due Back in Service

Washington State Ferries (WSF) inform in its latest newsletter that the ferries 'Kitsap' and 'Yakima' are expected to return to service next week. Commercial

Jet Edge Celebrates 30 Years in Waterjet Industry

Waterjet systems manufacturer Jet Edge, Inc. celebrated its 30th anniversary Sept. 3 with a special open house celebration. Jet Edge’s anniversary event included

Navy

ONR Funds UW Oceanographic R/V Refit Contract

The US Department of Defense informs that the University of Washington (UW), Seattle, Washington, is being awarded a $12,776,050 cost reimbursement contract for

Navy, Other Agencies, Award Bio-refinery Contracts to 3 Firms

As part of a 2011 Presidential directive, the Departments of Navy, Energy, and Agriculture have announced that three companies have been awarded contracts to construct

AN/SPY-1 SSSA Completes Critical Design Review

The Critical Design Review (CDR) stage for AN/SPY-1 radar Solid-State Switch Assembly (SSSA)'s high voltage modulator completed Aug. 26, confirming that the

Underwater Engineering

Seadrill Chairman Reassures Investors as Director Leaves

Seadrill Limited informs that Tor Olav Trøim has decided not to stand for re-election to the Board of Directors in order to focus his efforts on developing Golar LNG.

Significant Progress on Perth Wave Energy Project

Wave energy developer Carnegie Wave Energy Limited has provided an update on the recent progress of the Perth Wave Energy Project. Carnegie has made significant

EMGS - New Contract in the Norwegian Sea

Electromagnetic Geoservices ASA (EMGS) announced an agreement from Statoil Petroleum AS for the Norwegian Sea. EMGS has now received a new contract from another oil and gas company worth USD 1.

 
 
Maritime Careers / Shipboard Positions Maritime Security Maritime Standards Naval Architecture Navigation Offshore Oil Port Authority Ship Electronics Ship Simulators Winch
rss | archive | history | articles | privacy | terms and conditions | contributors | top maritime news | about us | copyright | maritime magazines
maritime security news | shipbuilding news | maritime industry | shipping news | maritime reporting | workboats news | ship design | maritime business

Time taken: 0.7197 sec (1 req/sec)