A project consortium that includes RWE Dea has signed a major contract for the construction of a natural gas processing plant and infrastructure in the Algerian Sahara for the Reggane Nord project. The contract is valued at US$976 million and represents an important step forward for the project.

Representatives of the Groupement Reggane of which RWE Dea is a partner signed the contract to construct the natural gas processing facilities and corresponding infrastructure including the gathering network and export pipeline on Thursday. The USDollar976 million contract was awarded to Petrofac International (UAE) LLC and stipulates completion of the facilities within 36 months.

After completion the plant will be operated with a gas troughput capacity of around 283 million cubic feet per day.

The Groupement Reggane partners are RWE Dea AG with its 19.5%-share, the Algerian enterprise Sonatrach (40%), Repsol from Spain (29.25%), and Edison from Italy (11.25%).

"With the construction start of these facilities, we've achieved a very important milestone in this development project. We are pleased to be moving this project forward into the execution phase," remarked Christoph Schlichter, Senior Vice President Production North Africa of RWE Dea AG. "We are concurrently driving ahead all project activities for start of production, which is scheduled for summer 2017."

A total of 26 development wells are planned to be completed during the first drilling campaign. The Groupement already awarded the rig contract in March this year to secure the necessary rig capacity for drilling and completion.

A successful 3D seismic campaign was also completed in the concession area in April this year. The seismic covered an area of 1,450 square kilometres. The acquired data, which is currently being processed and interpreted, will complement the extensive information already collected on previous seismic campaigns and enhance the detail and quality of information about subsurface structures of the various reservoirs.

“The project’s expected reserves will make a significant contribution to the growth of RWE Dea’s gas production in the years to come,” said Dirk Warzecha, Chief Operating Officer of RWE Dea AG.In 2002, RWE Dea started exploration activites in the concession area Reggane Nord together with partners Sonatrach, Repsol (operator) and Edison with corresponding gas discoveries. Capital expenditures will total approximately USDollar3 billion for the development project. The production phase of the project is expected to span more than 25 years.
 

Maritime Reporter September 2014 Digital Edition
FREE Maritime Reporter Subscription
Latest Maritime News    rss feeds

Contracts

GAC Starts Hull Cleaning Op'ns in Oman

GAC EnvironHull hull cleaning operations using the brush-and-diver-free HullWiper system starting at the port of Sohar, just outside the Gulf of Hormuz. This

Teekay Renews Hull and Propeller Monitoring for LNG Carriers

Canada-based shipping company Teekay Corporation has renewed its contract with Propulsion Dynamics for its hull and propeller performance monitoring system CASPER Service.

NAO Announces Financials, Declares Dividend

Nordic American Offshore Ltd. has declared a dividend of $0.45 per share for 3Q2014, as previously announced. This is the same dividend as for the previous two quarters.

Finance

Ensco plc Reports 3Q, 2014 Results

Ensco plc  today reported earnings per share from continuing operations of $1.93 in third quarter 2014, up 16% from $1.66 in third quarter 2013. Adjusted for a $0.

Chevron Announces Quarterly Dividend

The Board of Directors of Chevron Corporation today declared a quarterly dividend of one dollar and seven cents ($1.07) per share, payable December 10, 2014,

Exmar Optimistic About Gas Carrier Market into 2015

Belgian gas shipping group Exmar said on Thursday that the market for its very large and midsize gas carriers was at historically high levels in the third quarter

Energy

Ensco plc Reports 3Q, 2014 Results

Ensco plc  today reported earnings per share from continuing operations of $1.93 in third quarter 2014, up 16% from $1.66 in third quarter 2013. Adjusted for a $0.

Fukushima Offshore Floating Wind Farm Update

A consortium has been participating in an experimental offshore floating wind farm project sponsored by the Ministry of Economy, Trade and Industry since March 2012.

Wärtsilä Propulsion Equipment for 2 Fishing Vessels

Two new 78 metre purser/trawler fishing vessels being designed and built at Karstensen Shipyard in Denmark will feature Wärtsilä's main propulsion and control equipment.

LNG

Exmar Optimistic About Gas Carrier Market into 2015

Belgian gas shipping group Exmar said on Thursday that the market for its very large and midsize gas carriers was at historically high levels in the third quarter

US Natgas Exports Would Raise Energy Prices but Boost Economy

Expanded U.S. liquefied natural gas exports would mean a modest price increase for domestic consumers, but the higher costs would be offset by a boost to the economy, the U.

Korean Register to Drive LNG Fuelled Shipping

Korean Register (KR) will work alongside the Asia-Pacific Economic Cooperation Secretariat (APEC) to promote the use of LNG fuelled ships in the APEC region. APEC

News

Somali Pirates free Indian Sailors after 4 Years

Somali pirates have freed seven Indian sailors detained for close to four years in exchange for an undisclosed ransom, Somali officials and a maritime monitoring group said on Friday.

USCG Cutter Diligence Returns

The crew of Coast Guard Cutter Diligence returned to Wilmington following a 45-day patrol in the Caribbean Sea. While on patrol, Diligence served as the

Southern California Port Congestion

Hapag-Lloyd informs about the congestion at the ports of Los Angeles and Long Beach that has reached a critical point. I. Several container ships are anchoring

 
 
Maritime Contracts Maritime Security Maritime Standards Naval Architecture Navigation Offshore Oil Pipelines Ship Repair Ship Simulators Sonar
rss | archive | history | articles | privacy | terms and conditions | contributors | top maritime news | about us | copyright | maritime magazines
maritime security news | shipbuilding news | maritime industry | shipping news | maritime reporting | workboats news | ship design | maritime business

Time taken: 0.1298 sec (8 req/sec)