Japan Floating Offshore Wind Turbine Project Update

SeaDiscovery.com
Friday, June 28, 2013
Floater & floating sub-station: Image credit MHI

The construction of the floating power facility consisting of a 2MW downwind-type wind turbine and a 4 Column Semi-Sub as part of Phase I has been successfully completed and their delivery to Fukushima is uderway.

Background
A consortium made up of Marubeni Corporation (project integrator), the University of Tokyo (technical advisor), Mitsubishi Corporation, Mitsubishi Heavy Industries, Ltd, Japan Marine United Corporation, Mitsui Engineering & Shipbuilding Co., Ltd, Nippon Steel & Sumitomo Metal Corporation, Hitachi, Ltd., Furukawa Electric Co., Ltd., Shimizu Corporation and Mizuho Information & Research Institute, Inc. has been participating in an experimental offshore floating wind farm project sponsored by the Ministry of Economy, Trade and Industry since March 2012. 

 
The following work has been accomplished:
    •    Mounting wind turbine on floating compact semi-sub at Mitsui Engineering & Shipbuilding Co., Ltd. Chiba Works.
    •    Setting up of the anchor chains.     
    •    Construction of the 66kV floating power sub-station at Japan Marine United Corporation, Yokohama Works.
    •    Setting up of the anchor chains.     
    •    Delivery of the undersea cable from Furukawa Electric Co., Ltd Chiba Works to Onahama port, Fukushima.
    •    Laying and burying the undersea cable (in progress)

The consortium plans to commence the first trial run in early September 2013.

Maritime Reporter August 2014 Digital Edition
FREE Maritime Reporter Subscription
Latest Maritime News    rss feeds

Technology

Fraunhofer Researchers Improve Underwater Images

Videos and images of the submarine world are important for the maritime industry. Researchers from Fraunhofer IGD will show how underwater images can be improved

NavStation to Launch at SMM

Touch screen technology has transformed everyday life and now, thanks to Norwegian e-navigation specialist NAVTOR, it is set to revolutionize operations onboard busy vessel bridges.

SENER Announces the FORAN V70R3.0

SENER announces the new FORAN V70R3.0, available from July 31, 2014. With more than 45 years in the market, FORAN takes advantage of SENER´s innovative development

Offshore

N-KOM Lays Keel for Qatar’s First Liftboat

Nakilat-Keppel Offshore & Marine (N-KOM) has achieved another milestone with the keel laying of its first liftboat newbuild project, awarded in July 2014 by long-time

Master Fined After Wind Farm Collision

The master of a wind farm support vessel has today been made to pay £3,000 in fines and costs after pleading guilty to breaches of maritime collision regulations.

Bureau Veritas Diversifies with MatthewsDaniel Acquisition

Bureau Veritas announced today that it has acquired MatthewsDaniel Ltd, a global provider of loss adjusting and risk assessment services for the offshore industry.

Wind Power

Master Fined After Wind Farm Collision

The master of a wind farm support vessel has today been made to pay £3,000 in fines and costs after pleading guilty to breaches of maritime collision regulations.

CWind Launches New Vessel

CWind, a provider of integrated services to the offshore wind industry, has launched its new vessel CWind Fulmar in a naming ceremony in Brightlingsea. The CWind Fulmar, built by CTruk Ltd.

Policy Uncertainty Threatens to Slow Renewable Energy Momentum

IEA forecast sees renewable power as a cost-competitive option in an increasing number of cases, but facing growing risks to deployment over the medium term. The

 
 
Maritime Careers / Shipboard Positions Maritime Security Maritime Standards Navigation Offshore Oil Pod Propulsion Port Authority Salvage Ship Repair Shipbuilding / Vessel Construction
rss | archive | history | articles | privacy | terms and conditions | contributors | top maritime news | about us | copyright | maritime magazines
maritime security news | shipbuilding news | maritime industry | shipping news | maritime reporting | workboats news | ship design | maritime business

Time taken: 0.2129 sec (5 req/sec)