Japan Floating Offshore Wind Turbine Project Update

SeaDiscovery.com
Friday, June 28, 2013
Floater & floating sub-station: Image credit MHI

The construction of the floating power facility consisting of a 2MW downwind-type wind turbine and a 4 Column Semi-Sub as part of Phase I has been successfully completed and their delivery to Fukushima is uderway.

Background
A consortium made up of Marubeni Corporation (project integrator), the University of Tokyo (technical advisor), Mitsubishi Corporation, Mitsubishi Heavy Industries, Ltd, Japan Marine United Corporation, Mitsui Engineering & Shipbuilding Co., Ltd, Nippon Steel & Sumitomo Metal Corporation, Hitachi, Ltd., Furukawa Electric Co., Ltd., Shimizu Corporation and Mizuho Information & Research Institute, Inc. has been participating in an experimental offshore floating wind farm project sponsored by the Ministry of Economy, Trade and Industry since March 2012. 

 
The following work has been accomplished:
    •    Mounting wind turbine on floating compact semi-sub at Mitsui Engineering & Shipbuilding Co., Ltd. Chiba Works.
    •    Setting up of the anchor chains.     
    •    Construction of the 66kV floating power sub-station at Japan Marine United Corporation, Yokohama Works.
    •    Setting up of the anchor chains.     
    •    Delivery of the undersea cable from Furukawa Electric Co., Ltd Chiba Works to Onahama port, Fukushima.
    •    Laying and burying the undersea cable (in progress)

The consortium plans to commence the first trial run in early September 2013.

Maritime Reporter June 2014 Digital Edition
FREE Maritime Reporter Subscription
Latest Maritime News    rss feeds

Technology

There’s Still Time for SHIPPINGInsight Award Entries

Entry submissions for the first SHIPPINGInsight Award are due Friday, Aug. 1, but organizers said they will continue to accept nominations through following week to provide some extra time.

Joint Project Studies Condition-based Engine Monitoring

Classification society ClassNK announced that it will participate in a joint project together with Mitsui Engineering & Shipbuilding Co., Ltd. and MES Technoservice Co.

Resolve Maritime Academy's New Wet Trainer Facility

Resolve Maritime Academy informed it has started building a new, two-story wet trainer, larger and more expansive than its original, the L/V Gray Manatee. “We

Offshore

Transocean Prices Initial Public Offering

Transocean Partners LLC, a Marshall Islands limited liability company formed by Transocean Ltd., has announced  the pricing of its initial public offering of 17,

Refurbished Seajacks Vessels Leave Shipdock Amsterdam

Seajacks Leviathan and Seajacks Kraken are prepared for their coming assignments, following a series of repair and renewal jobs by Shipdock Amsterdam. The shipyard,

Kurdish Crude Lightered, Destination Unknown

Part of a Kurdish oil cargo has been offloaded from a Greek-managed tanker into another tanker in the South China Sea, but mystery surrounds the identity of the

Wind Power

Refurbished Seajacks Vessels Leave Shipdock Amsterdam

Seajacks Leviathan and Seajacks Kraken are prepared for their coming assignments, following a series of repair and renewal jobs by Shipdock Amsterdam. The shipyard,

Westermeerwind Wind Farm Construction Begins

Mammoet announced today that Westermeerwind BV has reached financial close on July 25 for the turnkey construction of the Westermeerwind wind farm in Ijsselmeer,

6 MW Offshore Wind Turbine of Siemens Certified

Siemens Energy has obtained type certification of DNV GL for the company's innovative D6 offshore wind turbine. The model Siemens SWT-6.0-154 is equipped with a modern direct drive generator,

 
 
Maritime Contracts Maritime Security Maritime Standards Navigation Pod Propulsion Salvage Ship Repair Ship Simulators Sonar Winch
rss | archive | history | articles | privacy | terms and conditions | contributors | top maritime news | about us | copyright | maritime magazines
maritime security news | shipbuilding news | maritime industry | shipping news | maritime reporting | workboats news | ship design | maritime business

Time taken: 0.1581 sec (6 req/sec)