Newport News Sets Heaviest Module Yet Aboard Aircraft Carrier

Press Release
Sunday, October 07, 2012
Lifting the Module: Photo credit HII

Huntington Ingalls Industries' Newport News Shipbuilding places a record 1,026-metric ton unit —aboard aircraft carrier 'Gerald R. Ford' (CVN 78).

The modular unit, — roughly the weight of six Boeing 747 commercial airplanes, is one of the nearly 500 total structural lifts needed to complete the ship, of which 435 have been completed. The lifts are accomplished using the shipyard's 1,050-metric-ton gantry crane, one of the largest in the Western Hemisphere.

"This is the heaviest unit to be moved during the ship's construction and the largest lift our crane has ever made," said Rolf Bartschi, NNS' vice president of CVN 78 carrier construction. "This lift represents the strategic construction improvements of the Ford-class carriers. The concept during design of the ship was to build larger units than were built on the Nimitz-class carriers, resulting in fewer crane lifts to the dry dock. This lift is a significant achievement for our shipbuilding team on this first-of-class ship and reflects the pride and capability of the entire team."

At 128 feet wide and 128 feet long, the gallery deck to flight deck bridge assembly comprises 14 steel sections and includes firefighting, jet fuel and catapult systems, jet blast deflectors and electrical servicing stations. Construction of the gallery deck to flight deck bridge assembly began in October 2011.

Gerald R. Ford represents the next-generation class of aircraft carriers. The first-in-class ship features a new nuclear power plant, a redesigned island, electromagnetic catapults, improved weapons movement, an enhanced flight deck capable of increased aircraft sortie rates, and growth margin for future technologies and reduced manning. Ford has been under construction since November 2009. The ship is more than 88 percent structurally complete and is scheduled to launch in 2013 and deliver to the U.S. Navy in 2015.
 

Maritime Reporter May 2015 Digital Edition
FREE Maritime Reporter Subscription
Latest Maritime News    rss feeds

Shipbuilding

ERMA Bullish on Ballast Water Treatment

After having delivered several BWTS systems in Kita Nihon shipyard in Japan, one more ERMA FIRST BWTS was successfully installed onboard the Bulk Carrier M/V SCARABÉ(DWT: 60,

USS Freedom (LCS 1) Completes Rough Water Trials

The littoral combat ship USS Freedom (LCS 1) completed Seakeeping and Structural Loads Trials, commonly referred to as Rough Water Trials (RWT) in late March the Navy reported May 21.

Conrad Announces Management Team Changes

Conrad Industries, Inc. announced the appointment of Scott J. Theriot as Executive Vice President and Chief Operating Officer.   Johnny Conrad, President and Chief Executive Officer,

Navy

DMW Marine Takes the Lead in Military Cranes

DMW Marine Group, LLC. has completed a number of projects for the U.S. Navy and foreign Navies in recent years, claiming a place as a go-to supplier for Navy departments globally.

Myanmar Finds 200 Bangladeshis in Offshore Boat

Myanmar's navy found a boat carrying more than 200 Bangladeshis, the government said on Friday, after the military chief said some migrants landing in Malaysia

HMAS Anzac Visits Portsmouth, UK

The Royal Australian Navy’s helicopter frigate HMAS Anzac has arrived in Portsmouth, England, as part of her NORTHERN TRIDENT 2015 deployment.   Anzac departed Sydney in March 2015,

 
 
Maritime Security Maritime Standards Pod Propulsion Salvage Ship Electronics Ship Repair Ship Simulators Shipbuilding / Vessel Construction Sonar Winch
rss | archive | history | articles | privacy | contributors | top maritime news | about us | copyright | maritime magazines
maritime security news | shipbuilding news | maritime industry | shipping news | maritime reporting | workboats news | ship design | maritime business

Time taken: 0.1362 sec (7 req/sec)