Huntington Risks Losing $194 Million on Carrier’s Overrun

Thursday, April 05, 2012

Huntington Ingalls Industries Inc. stands to loss as much as $194.3 million, more than 40 percent of its potential fee, under the Navy’s latest estimate of overruns for the USS Gerald R. Ford aircraft carrier, according to Bloomberg.

Construction of the Ford, the Navy’s most expensive warship, is likely to exceed by $884 million the shipbuilder’s target contract cost of about $5.2 billion for detailed design and construction, according to Navy officials and the service’s Selected Acquisition Report, obtained after it was delivered to Congress on March 29.

The Ford is intended to be the first in a $40 billion, three-ship class of carriers. Its rising costs have brought questions from Republican Senator John McCain about the Navy program and the shipbuilder’s performance. McCain of Arizona, a member of the Senate Armed Services Committee, has asked the Government Accountability Office for a review.

Huntington’s performance on costs “has stabilized, but has a long way to go to turn it around,” said Sean Stackley, the Navy’s assistant secretary for acquisition. The company and Navy aren’t in agreement on what the carrier’s final construction cost will be, he said.

Under the carrier contract, the Navy would pick up $689.7 million of the overrun now projected as “most likely,” with the remaining $194.3 million subtracted from potential maximum construction fees of $467 million for Huntington Ingalls of Newport News, Virginia. The carrier is about 40 percent complete.

The company would earn 50 cents of every dollar it shaves from the $884 million projection, Stackley said. If costs rise still further, “they are at a point in the contract where they share 50/50,” he said.

“We continue to see improvements in our performance on the carrier,” Huntington Ingalls spokeswoman Beci Brenton said. “Although this is a ‘first-in-class’ ship with unique challenges, we anticipate that we will increase efficiencies and continue to retire risk in the three years remaining until delivery.”

The Ford’s total projected cost has increased 18 percent in four years to $12.3 billion, from $10.4 billion, according to Navy budget figures cited by the nonpartisan Congressional Research Service. That includes systems which won’t be provided by Huntington Ingalls, such as the nuclear reactor to power the ship, a dual-band radar from Raytheon Co., and an electromagnetic aircraft-launching system from General Atomics of San Diego.

The Navy already has taken action against the shipbuilder. Last year, it didn’t let the company bill $75 million in fees because of the overrun projections, and that money has been forfeited, Stackley said.

Other cost-control initiatives include designating a Huntington senior vice president and a superintendent to oversee costs, specifying labor-cost targets and intensely reviewing specifications for the vessel, according to the Navy.

The latest overrun estimate stems from “material cost growth, labor inefficiencies” and increases in one-time engineering costs, according to the Navy document.

The labor “inefficiencies are the result of ‘first of class’ challenges,” including production issues, such as the use of thin-plate steel and weld distortion, the Navy wrote.

Huntington Ingalls “has had 10 consecutive months of improvements in meeting cost targets,” Rear Admiral Tom Moore, the Navy’s program executive officer for carriers, said in an interview.

“If they continue the trend they are on, I’m comfortable we will come in under the ’most likely’ $884 million estimate,” he said.

Still, he said, the company won’t meet the original targets.

On labor, the company is moving closer to the goal of 40 million man-hours on the carrier, from an earlier estimate of 53 million, Moore said. A man-hour is the work one person does in an hour.

“I need to drive them down further,” he said.

The company would receive the minimum fee allowed, about $196 million, if its performance deteriorates and the construction exceeds a worst-case overrun of $1.1 billion by completion in mid-2015, according to Stackley, who called that an unlikely outcome.

The minimum covers “a couple percent of profit and allowable costs,” he said.

The Navy disclosed in February that it was adding $811 million to the Ford’s budget through 2017 to cover increases, including $273 million directly tied to the construction overrun (Bloomberg).


 

Maritime Reporter August 2015 Digital Edition
FREE Maritime Reporter Subscription
Latest Maritime News    rss feeds

Contracts

China Passes New Pollution Law, Will Cap Coal Consumption

Legislators have approved amendments to China's 15-year-old air pollution law that grant the state new powers to punish offenders and create a legal framework to cap coal consumption,

Gazprom, OMV Meet on Establishing Nord Stream JV

At a Meeting held at the Gazprom headquarters between Alexey Miller, Chairman of the Company's Management Committee and Rainer Seele, Chairman of the Executive Board of OMV,

DP World Profit Up 22%

Global marine terminal operator DP World today announced strong financial results from its global portfolio of marine terminals for the six months to 30 June 2015,

Shipbuilding

MN 100: ContainerTug B.V.

The Company: ContainerTug B.V. is a specialized Dutch naval design engineering and construction company with a strong focus on developing workboats and the evaluation

Oman Drydock Company Expands Rapidly

Oman Drydock Company (ODC) is growing fast. In January, the yard hit an important milestone - its 300th drydocking. Harnessing the power of its new $1.8 billion, 1.

NASSCO Invests in Facilities, Equipment and People

General Dynamics NASSCO has invested several hundred million in capital projects as part of its efforts to increase efficiencies via  modular shipbuilding, including:

Navy

Iranian Ship, Crew Escape Captivity off Somali Coast

An Iranian fishing vessel and its crew have escaped after being held captive for five months by Somali fishermen, maritime piracy experts said on Friday, but it

Migrant Boat Sinks off Libya; 200 Feared Dead

A boat packed with mainly African migrants bound for Italy sank off the Libyan coast on Thursday and officials said up to 200 might have died. A security official in the western town of Zuwara,

Russian-Chinese Naval Drills End

The second phase of the Russian-Chinese Joint Sea-2015 naval maneuvers has officially ended outside the port of Vladivostok in Russia’s Far East, says spokesman

 
 
Maritime Careers / Shipboard Positions Maritime Contracts Maritime Security Maritime Standards Offshore Oil Ship Electronics Ship Repair Ship Simulators Sonar Winch
rss | archive | history | articles | privacy | contributors | top maritime news | about us | copyright | maritime magazines
maritime security news | shipbuilding news | maritime industry | shipping news | maritime reporting | workboats news | ship design | maritime business

Time taken: 0.3982 sec (3 req/sec)