BOEMRE Report of Platform Fire Investigation

Press Release
Thursday, May 26, 2011

The Bureau of Ocean Energy Management, Regulation and Enforcement (BOEMRE) today released the findings of its investigation into a fire that occurred Sept. 2, 2010, on Mariner Energy Inc.’s, Vermilion 380 A oil and natural gas production platform located approximately 102 miles off the coast of Louisiana.  

A BOEMRE Accident Investigation Panel concluded that the fire was caused by the collapse of a fire tube located inside of the platform’s Heater-Treater. The Heater-Treater, a nearly 30-year-old piece of equipment, used heat from a fire tube as well as chemicals and electricity to separate oily water emulsions into oil and water. The fire tube had been weakened over time due to a variety of factors, including heat, corrosion and pitting. Investigators also found that after the platform lost primary power because of the fire, the emergency generator failed to start and supply power to the firewater pump, leaving the 13-member crew without a firewater system to aid them in trying to fight the fire. Ultimately, the crew was forced to evacuate the platform, and all were later transported to safety. 

“This report reflects a careful and comprehensive investigation by the BOEMRE Accident Investigation Panel, led by the Investigations and Review Unit,” said BOEMRE Director Michael R. Bromwich. “The report underscores the need for offshore operators to maintain their equipment consistent with existing standards, to protect the safety of personnel working onboard and to protect the environment.” 

The investigation included interviews of the Vermilion 380 A crew, review of documentary and physical evidence, examination of equipment onboard the platform, and consultation with an expert in oil production platforms and Heater-Treaters.      

In addition to its investigative findings, the BOEMRE panel recommended several Incidents of Non-Compliance be issued to Mariner Energy, Inc., which may be used as the basis for future civil penalties. BOEMRE will now consider the panel’s recommendations before taking further action in this case. Production from the platform remains shut-in until BOEMRE personnel approve all safety and structural corrections.

 

Source: BOEMRE

Maritime Reporter June 2014 Digital Edition
FREE Maritime Reporter Subscription
Latest Maritime News    rss feeds

Offshore

New Standard gets Revised Program for Cooper Basin Approved

New Standard Energy Limited (New Standard) advises that it has received approval for amendments to its five year work program in PEL570 in the Cooper Basin. As part of the revised program,

Floating Production: $1.2b Speculative FLNG Ordered

The floating production business continues to be very strong, particularly in the LNG gas processing sector.  Last month saw a speculatively ordered floating liquefaction plant – a $1.

FLNG Prelude: A New Dawn in the Age of Maritime & Energy

Longer than four football fields, as big as six Nimitz-class aircraft carriers and almost as tall as the Taipei 101 skyscraper, Royal Dutch Shell PLC is hoping that its record-setting,

Casualties

Company Fined for Oil Spill Near Anacortes

Ecology issues $112,500 penalty for sunken vessel.   American Gold Seafoods faces a $112,500 penalty for an oil spill caused by the accidental sinking of its vessel,

Grounded Freighter Refloated in Lake St. Clair

The Federal Rideau, a 656-foot freighter that had been hard aground in the downbound shipping channel of Lake St. Clair since early Sunday morning, was refloated

S.Korea Ferry Boss's Driver Turns Self In

The driver of a South Korean businessman wanted over the sinking of a ferry that killed 304 people turned himself in on Tuesday, potentially unlocking the mystery

Maritime Safety

Resolve Maritime Academy's New Wet Trainer Facility

Resolve Maritime Academy says it has started on the construction of a new, two-story wet trainer, larger and more expansive than its original, the L/V Gray Manatee.

Bollinger Fourchon: 13 Years Without a Lost Time Accident

Bollinger Shipyards, Inc. announced that their Bollinger Fourchon, L.L.C. facility has worked 13 years without a lost time accident. Building on a philosophy that starts at the top,

Charter Boat Crew Rescued in Gulf of Mexico

U.S. Coast Guard search and rescue crews worked throughout the night to find a missing charter boat with four people aboard as far as 70 miles off Galveston. A

 
 
Maritime Careers / Shipboard Positions Maritime Contracts Offshore Oil Pipelines Port Authority Salvage Ship Repair Shipbuilding / Vessel Construction Sonar Winch
rss | archive | history | articles | privacy | terms and conditions | contributors | top maritime news | about us | copyright | maritime magazines
maritime security news | shipbuilding news | maritime industry | shipping news | maritime reporting | workboats news | ship design | maritime business

Time taken: 0.1140 sec (9 req/sec)