Marine Link
Thursday, April 18, 2024
SUBSCRIBE

Raytheon Electronic Systems News

28 Feb 2002

Lead LPD 17 Ship Makes Progress

Plagued by delays and a project management team shake-up, the LPD 17 program has "turned the corner" said Philip Dur, president of Northrop Grumman Corp. Ship Systems, when speaking earlier this week at a Washington, D.C. conference on raising FY '03 Navy procurement funding. This would seem to be the case, as the company announced that it achieved an integral milestone in the construction of San Antonio, when it completed early landing of all four main propulsion engines and three of five power generators on their foundations. In addition, 55 of the 210 units have been erected on San Antonio, the lead ship in the Navy's new LPD 17 Class of amphibious transport dock ships. The ship is scheduled for delivery in November 2004.

02 Apr 2002

LPD 17 Construction on Course

The steel profile of San Antonio, the first ship of the LPD 17 class, can now be seen rising along the banks of the Mississippi River at Northrop Grumman Ship Systems in Avondale, La. technologies that will enhance the amphibious fleet's operational flexibility. Osprey. The San Antonio construction program enjoyed some recent successes, thanks to a new incentive program established by NAVSEA's LPD-17 program office. The program provides incentives to the shipyard to enhance efficiencies and complete construction phases on schedule and within budget. San Antonio construction achieved its 10 percent completion milestone in February 2002 and is quickly nearing its 20 percent production objective. schedule. There is significant progress in other areas as well.

30 Apr 2002

Raytheon to Lead Systems Integration for DD(x)

Raytheon Company (NYSE:RTN) won a cost plus award fee contract to be the systems integrator for the DD(X), the U.S. Navy's next-generation surface combatant ship. The contract is expected to total $1.36 billion over the next three years. Raytheon is a partner on the industry "Gold Team" that was selected by the Navy to design, develop, build, and conduct at-sea tests of Engineering Development Models (EDMs) and then apply the results of the testing to a comprehensive DD(X) ship system design. The "Gold Team" is being lead by Northrop Grumman Ship Systems. "This is a very important win for Raytheon in an area that provides great potential for growth for our company," said Daniel P. Burnham, Raytheon Company's chairman of the board and chief executive officer.

01 Jun 2000

Litton Awarded $477.7M Contract

Litton Avondale Industries, a division of Litton Industries, has been awarded a $477.7 million contract by the U.S. Navy for the construction of an additional ship in the Navy's newest class of amphibious assault ships. The cost reimbursable contract is for the construction of LPD 20, the fourth ship in a planned 12-ship program. The follow-on eight ships in the LPD 17 San Antonio Class program will be awarded over the next four years. As prime contractor for the LPD 17 program, Litton Avondale leads a team comprised of Bath Iron Works, Raytheon Electronic Systems and Intergraph Corporation. Design of the lead ship of the class is underway at Litton Avondale with actual production scheduled to begin this summer.

02 Jun 2000

Litton Awarded $477.7M Contract

Litton Avondale Industries, a division of Litton Industries, has been awarded a $477.7 million contract by the U.S. Navy for the construction of an additional ship in the Navy's newest class of amphibious assault ships. The cost reimbursable contract is for the construction of LPD 20, the fourth ship in a planned 12-ship program. The follow-on eight ships in the LPD 17 San Antonio Class program will be awarded over the next four years. As prime contractor for the LPD 17 program, Litton Avondale leads a team comprised of Bath Iron Works, Raytheon Electronic Systems and Intergraph Corporation. Design of the lead ship of the class is underway at Litton Avondale with actual production scheduled to begin this summer.

18 Aug 2000

Contracts

Bollinger Shipyards, Inc., Lockport, La., has signed a contract to build two, 250-ft., double hull, jumbo coastwise service, single rake hopper barges for Tide Leasing, LLC, Birmingham, Ala. Construction has begun on the first barge and building of the second vessel will begin in August. Both are scheduled for delivery in November 2000. Overall, each barge will be 250 ft. in length, with a 52.5-ft. beam and 14-ft. depth and 11.5 ft. maximum draft. They will be built with .75-in. steel at the hopper bottoms and .625-in. steel at the hopper sides plus .5-in. T-1 liner plates on the bottom and upper sides of the hopper. Each will be able to carry up to 3,000 metric tons of coal and will operate out of Santa Marta, Colombia. Shearer and Associates, Inc., Metairie, La.

23 Jul 2003

Northrop Grumman Christens San Antonio

Saturday, July 19, 2003, at the company's Avondale operations near New Orleans. Hundreds of guests and employees attended the traditional dockside ceremony. transport dock ships being built for the U.S. Navy by Northrop Grumman. Gen. Michael W. Hagee, commandant of the U.S. principal address at the ceremony. San Antonio. The ship's sponsor was U.S. from Texas who christened the vessel. Hutchison. Currently, the ship is more than 75 percent complete. and start powering up the ship's systems. commissioned for U.S. Marines. mission. major components and large assemblies for the ship. on San Antonio," said Dr. Ronald D. president of Northrop Grumman Corporation. and LST 1179 classes of amphibious ships. Intergraph Corporation and vendors in 36 states.

20 Jul 2001

Northrop Grumman Gets Advance Money Fo LPD 21, LPD 22

Northrop Grumman Corporation announced that the Avondale Alliance, led by Northrop Grumman Avondale, has been awarded $113.2 million for advance procurement of long lead materials for ships five and six in the SAN ANTONIO Class LPD 17 Program. "This advance procurement award demonstrates the importance of the LPD 17 Program and the Navy's commitment to it," said Tom Kitchen, president of Northrop Grumman Avondale. Long lead materials consist of items such as the main engines, generators, controllable pitch propellers, and reduction gears. Advance procurement is necessary for these critical long lead items in order to exercise vendor option rates.

11 Nov 2002

Northrop Grumman, U.S. Navy Commemorate Keel Laying For USS New Orleans

(NYSE: NOC) and the U.S. Northrop Grumman's Ship Systems sector. Louisiana's largest city and to honor one of the world's major ports. Orleans. Nagin, the principal speaker for the traditional Navy ceremony. Coulon. beginning of a ship's construction. as well as initial prefabrication work. Southeast Louisiana," said U.S. Rep. Congressional District. expected lifetime in the fleet. and our nation," said Mitchell B. Secretary of the Navy (Ships). world. ship," said Dr. Philip A. president and president of the company's Ship Systems sector. international terrorists wherever they lurk and wherever they hide. and land elements of a U.S. amphibious warfare mission. transport up to 700 Marines. 113- and LDT 1179-classes of amphibious ships. part of our sea base," said Lt. Gen. Dennis M.