N.Sea Oilfield Plans 25 Days Maintenance

March 7, 2014

Reuters - Britain's biggest oilfield Buzzard will undergo 25 days of planned maintenance starting in late July, its operator Nexen confirmed on Friday.

During this period production will be offline but the outage coincides with the planned 14-day shutdown of the Forties Pipeline System (FPS), which is scheduled to begin at the end of July, Nexen said.

Buzzard is the largest single contributor to the Forties crude stream, which is one of the four benchmark crudes underpinning the price of dated Brent and Brent crude oil futures.

Previously Suncor Energy (SU), which has a 29.9 percent stake in the Buzzard field, indicated that Buzzard would also undergo maintenance in May and September. Nexen said some of this information was "incorrect".

It added that third-party constraints on gas export might not prevent oil production in the second quarter and that it was working on a solution.

The St Fergus gas terminal, which processes the gas exported from Buzzard, has a planned shutdown for 28 days, beginning at the end of May.

Maritime Reporter Magazine Cover Oct 2016 - Marine Design Annual

Maritime Reporter and Engineering News’ first edition was published in New York City in 1883 and became our flagship publication in 1939. It is the world’s largest audited circulation magazine serving the global maritime industry, delivering more insightful editorial and news to more industry decision makers than any other source.

Maritime Reporter E-News subscription

Maritime Reporter E-News is the subsea industry's largest circulation and most authoritative ENews Service, delivered to your Email three times per week

Subscribe for Maritime Reporter E-News