23 Apr 2019

NextDecade Receives EPC Bid Packages

NextDecade Corporation, a liquefied natural gas (LNG) development company focused onLNG export projects and associated pipelines in the State of Texas, announced that it has received bid packages from each of Bechtel Oil, Gas, and Chemicals, Inc. and Fluor Corporation.Both the companies are two of the global LNG market’s leading engineering, procurement, and construction (EPC) contractors.The technical and commercial bid packages, which were received on-schedule, are for fully wrapped lump-sum turnkey (LSTK) EPC contracts for NextDecade’s Rio Grande LNG export project in Brownsville, Texas.Following detailed evaluations of the Bechtel and Fluor bid packages…

11 Mar 2019

Cheniere Completes 5th LNG Train at Sabine Pass

Texas-based Cheniere Energy Partners said that that Substantial Completion of Train 5 of the Sabine Pass liquefaction project in Cameron Parish, Louisiana (the "SPL Project") was achieved on March 7, 2019."Commissioning has been completed and Cheniere Partners’ EPC partner Bechtel Oil, Gas and Chemicals has turned over care, custody, and control of Train 5 to Cheniere Partners," it said.Under sale and purchase agreements (SPAs) with Centrica plc and Total Gas & Power North America, Inc., the date of first commercial delivery is expected to occur in August 2019, upon which the term of each of these SPAs commences.Cheniere Partners and…

05 Mar 2019

Cheniere's First LNG Train Almost Complete

Cheniere Energy and Bechtel Oil, Gas and Chemicals said that they have achieved substantial completion of Train 1 of the Corpus Christi LNG Project.Commissioning is wrapped up and Bechtel has turned over care, custody, and control of Train 1 to Cheniere Energy.Jack Fusco – President and CEO of Cheniere said: “Train 1 at Corpus Christi has achieved Substantial Completion, becoming the first liquefaction train placed into operation at a greenfield liquefaction facility in the lower 48 states.Bechtel won the engineering, procurement, and construction (EPC) contract for three liquefied natural gas trains and related facilities of the Corpus Christi LNG Project.The three LNG trains will have a production capacity of nearly 4.5 million tonnes per annum of LNG.

15 Nov 2018

Bechtel, Cheniere Fires Up Corpus Christi LNG Production

The the largest construction company in the United States Bechtel has joined its customer Cheniere Energy to announce production of the first liquefied natural gas (LNG) from the Corpus Christi Liquefaction project in Texas.The leader in project management, engineering, procurement, and construction said in a press release that this production train at the Corpus Christi project is the latest of six trains that Bechtel has delivered with Cheniere at two sites on the U.S. Gulf Coast.The Sabine Pass Liquefaction project in Louisiana produced the first LNG from that site’s fifth train last week, it said.“These achievements further highlight the value this ongoing successful partnership with Cheniere brings for both of us…

14 Oct 2017

Cheniere Partners Completes Train 4 at the Sabine Pass LNG

Cheniere Energy Partners has announced that Substantial Completion of Train 4 of the Sabine Pass liquefaction project in Cameron Parish, Louisiana (SPL Project) was achieved on October 9, 2017. Commissioning has been completed and Cheniere Partners' EPC partner Bechtel Oil, Gas and Chemicals has turned over care, custody, and control of Train 4 to Cheniere Partners. Under a sale and purchase agreement (SPA) with GAIL (India) Limited, the date of first commercial delivery for Train 4 of the SPL Project is expected to occur in March 2018, upon which the SPA's 20-year term commences. Over the last 17 months, Cheniere Partners and Bechtel have declared Substantial Completion on four liquefaction trains at Sabine Pass.

06 Aug 2015

Bechtel to Design America's First FLNG

The first U.S.-based  floating liquefied natural gas vessel (FLNGV) moved closer to reality after engineering giant Bechtel agreed to design and engineer the project. Bechtel has been selected by Delfin LNG, a wholly-owned subsidiary of Fairwood Peninsula Energy, to perform front-end engineering and design for the floating FLNGV to go into service at Port Delfin. Port Delfin is a proposed deepwater port and floating LNG facility that will be located approximately 50 miles off the coastline of Cameron Parish, Louisiana. Delfin LNG’s project will be the first offshore floating natural gas liquefaction facility in the United States, Bechtel said in a statement on Tuesday.

05 Aug 2015

Bechtel Wins Contract for US' First FLNG Facility

Bechtel announced it has been selected by Delfin LNG, a wholly-owned subsidiary of Fairwood Peninsula Energy Corporation, to perform front-end engineering and design for the first U.S.-based floating liquefied natural gas vessel (FLNGV) to go into service at Port Delfin. Port Delfin is a proposed deepwater port and floating LNG facility that will be located approximately 50 miles off the coastline of Cameron Parish, La. Delfin LNG's project will be the first offshore floating natural gas liquefaction facility in the United States. Upon the final investment decision, Bechtel is expected to design, build and commission the FLNGV. Frederick Jones…

25 Jul 2014

Gulf Island Fab Sign Bechtel Offshore Cooperation Agreement

Gulf Island Fabrication, Inc. says it has signed a cooperative agreement with Bechtel Oil, Gas, and Chemicals, Inc. to work together to pursue opportunities for offshore projects for the U.S. Gulf of Mexico and abroad. “Gulf Island is excited about the cooperation agreement signed with Bechtel which couples our fabrication expertise and specialized capabilities with one of the most respected EPC companies in the world. Together we offer a new approach to deliver offshore projects which incorporates innovative solutions and flexibility to meet and exceed client expectations and requirements,” said Kirk Meche, President and CEO of Gulf Island Fabrication, Inc.