Marine Link
Friday, April 19, 2024
SUBSCRIBE

Ecosse Subsea Systems News

02 Jun 2016

Bibby Steers to Offshore Cable Installation

Bibby Offshore announced its decision to move into the offshore wind array cable installation market. The company has purchased a power cable lay carousel from Ecosse Subsea Systems (ESS), which will enable Bibby Offshore to lay power cables for offshore wind projects from its vessels. Bibby Offshore and ESS have also entered into strategic alliance by way of a framework agreement. Under this alliance, Bibby Offshore will provide commercial expertise supported by subsea project management and engineering experience, while ESS will provide innovation and in depth sector competence through its trenching expertise. Both companies will collaborate to develop other technologies and working methods which will benefit clients by reducing risk and lowering project costs.

25 Sep 2013

Baltic Wind Success Paves Way for Ecosse Subsea Systems

Preparing the SCAR subsea plough for deployment.

Ecosse Subsea Systems (ESS) has completed a £4.7 million boulder clearing and pre-lay trenching project which it claims has been one of the most successful ever conducted for the wind energy sector. As subcontractor to Siem Offshore Contractors (SOC), the Banchory-based subsea specialist completed 86 boulder clearing passes followed by 172 first and multi-passes over a 90km route during a 13-week boulder clearing and trenching campaign on the EnBW Baltic 2 offshore wind farm project.

15 Apr 2013

Cold SCAR Steel is Weapon of Choice on Baltic 2

Lewis Watt, project engineer. Photo: Ecosse Subsea Systems Ltd.

Ecosse Subsea Systems (ESS) reported a successful start to a 10-week boulder clearing and trenching campaign on the Baltic 2 offshore wind farm project. Mobilized onboard the Siem Topaz anchor handling vessel, Ecosse Subsea’s SCAR subsea plough system is engaged on route clearing and pre-lay trenching operations on behalf of Siem Offshore Contractors. Soils have varied from dense sands and hard clays to high boulder density ranging up to four meters, but the SCAR has demonstrated its versatility and capabilities in dealing robustly with challenging conditions.

05 Oct 2012

Ecosse Subsea Completes Total E&P Project

SCAR1 being deployed on Laggan-Tormore field, Shetland

Ecosse Subsea Systems has completed a major seabed clearance project on the Laggan-Tormore project west of Shetland on behalf of Total E&P Ltd and its partner Dong E&P (UK) Ltd. The Aberdeen subsea technology company deployed its SCAR1 trenching tool to remove up to 1000 boulders which were delaying progress on cable laying and umbilical installation work. The SCAR1 cut a 10 metre wide swathe over a 67km route, displacing boulders up to two metres in diameter and removing soil to leave a flat seabed for pipe laying to commence.

10 Sep 2012

Ecosse Subsea Systems’ Growing Engineering Division

Ecosse Subsea Systems managing director, Mike Wilson, flanked by David Hunt (left) and Faris Lutfy

Energy technology company, Ecosse Subsea Systems, (ESS) has increased the size of its engineering division in response to client demand for specialist engineering packages. Aberdeen-based ESS specialises in trenching, deepwater installation and subsea lifting technologies for the oil and gas, marine and renewable industries, and has a range of patented technologies in development. The new division will complement ESS’ well established consultancy service and will  be headed up by chartered engineers David Hunt and Faris Lutfy.