04 Sep 2019

Freeport Ships First LNG Commissioning Cargo

Texas-based LNG terminal operator Freeport LNG Development announced that it has shipped the first LNG commissioning cargo for Train 1 from its liquefaction facility located on Quintana Island in Freeport, Texas.Approximately 150,000 cubic meters of LNG were loaded aboard the LNG Jurojin, which departed from the Freeport LNG terminal on September 3."This first cargo loading is another significant step that gets us one step closer towards our start of commercial operations which is anticipated later this month," said Michael Smith, Founder, Chairman and CEO, Freeport LNG."We are very pleased that it took less than 45 days to load our first cargo since gas was first introduced to our liquefaction facilities…

20 Aug 2019

First Production for Freeport LNG

Freeport LNG has reached a new milestone - it has become the sixth major US liquefaction facility to start up, with the operator confirming that production had begun at the Texas facility."McDermott International along with its partners, Chiyoda International Corporation and Zachry Group, announced that Train 1 of the Freeport LNG project on Quintana Island in Freeport, Texas, has begun producing liquefied natural gas (LNG)," said a press release.The American multinational engineering, procurement, construction and installation company said that while production is in the initial phases, this significant project milestone is a precursor to first cargo…

23 Jul 2019

Freeport LNG Reaches Milestone

Freeport LNG has reached final commissioning on Train 1 of its liquefaction project on Quintana Island in Freeport, Texas, following months of construction delays.American multinational engineering firm McDermott International along with its partners, Chiyoda International Corporation and Zachry Group, announced that crews have introduced feed gas into Train 1 of the liquefied natural gas export terminal.When fully operational, Train 1 will produce more than 5M metric tons/year of LNG, said a joint press release."We are extremely proud of the Freeport LNG project team for reaching this major milestone at this unique LNG production facility…

26 Jun 2018

Trafigura Strikes 3-year LNG Deal from U.S. Project

Commodity trader Trafigura on Tuesday said it agreed to buy 0.5 million tonnes of liquefied natural gas (LNG) annually over three years from the Freeport LNG export plant in the United States.   Deliveries from Freeport LNG Marketing will begin in 2020 from its facility on Quintana Island near Freeport, Texas, Trafigura said.   The deal builds on Trafigura's 15-year, 1 million tonne per annum agreement with Cheniere Energy for supply from its Sabine Pass plant in Louisiana, which was announced in January.   Reporting by Oleg Vukmanovic

19 Apr 2018

Freeport LNG Delays Start of Texas Export Terminal

(Photo: Freeport LNG)

Freeport LNG, a privately held U.S. liquefied natural gas company, said on Thursday it pushed back the projected start date for its $13 billion export terminal under construction in Texas by about nine months to around Sept. 1, 2019.Freeport LNG now expects the first liquefaction train to enter service around Sept. 1, 2019, with the second and third trains seen in service around Jan. 1 and May 1, 2020, respectively, said Zdenek Gerych, a spokesman at Freeport.Previously, the three…

07 Jul 2017

Aqualis Lands Audit Work for LNG Carrier

Offshore marine and engineering consultancy Aqualis Offshore, part of Oslo-listed Aqualis ASA, said it has been contracted by Hyundai Samho Heavy Industries Co. Ltd to provide an engineering study of a new-build liquefied natural gas (LNG) carrier the yard is constructing for Teekay LNG. Aqualis Offshore’s work scope is to provide failure modes and effects analysis (FMEA), hazard dentification (HAZID) and hazard and operability (HAZOP) studies for the boil-off gas handling system and fuel gas system on board the vessel. Aqualis Offshore will also provide FMEA-studies of the vessel’s propulsion redundancy and steering system as well as…

15 Jun 2015

Teekay, BP Enter Deal for Newbuild LNG Tankers

Teekay LNG Partners L.P. announced that it has entered into a 13-year time-charter contract with BP Shipping Limited (BP) for one liquefied natural gas (LNG) carrier newbuilding, plus an option exercisable by BP by the end of the third quarter of 2015 for one additional LNG carrier under similar terms. The vessels, including the optional vessel if exercised, will primarily provide LNG transportation services for BP’s LNG volumes from the Freeport LNG project located on Quintana Island near Freeport, Texas, which consists of three LNG trains with a total capacity of 13.2 metric tons per annum, scheduled for start-up in 2018. In connection with signing the contracts with BP…

28 Mar 2015

JV Wins $2bln Freeport LNG Contract in US

A joint venture (JV) between CB&I, Chiyoda International and Zachry Industrial has won a contract worth over $2bn from FLNG Liquefaction 3 for a liquefied natural gas (LNG) train at Freeport LNG in Texas, US. Upon completion, the three-train facility will have a total export capacity of more than 13.9 million tons per year of liquefied natural gas. The deal requires the JV to provide engineering, procurement and construction services for the third of the three-train natural gas liquefaction and export facility on Quintana Island, near Freeport. The contract's scope also includes a double-walled, full-containment 165,000 cubic metre LNG storage tank, which will be delivered by CB&I. Zachry built Freeport LNG’s original regasification terminal on Quintana Island.

14 Nov 2014

US Gives Final Approvals to Freeport for LNG Exports

Proposed liquefaction facilities (Image courtesy of Freeport LNG)

The U.S. Department of Energy gave two final approvals on Friday to Freeport LNG Development LP to export liquefied natural gas, or LNG, from its project in Texas to any country. The planned project in Quintana Island, Texas, would have the capacity to export up to 1.8 billion cubic feet a day of LNG once constructed. With domestic gas production booming, U.S. companies have lined up to ship the nation's abundant shale gas to energy- hungry consumers in Europe and Asia. The companies need special approval to export LNG to countries with which Washington does not have free trade agreements.

17 Mar 2014

FERC Drafts EIS on Freeport LNG Project

Image: Freeport LNG

The staff of the Federal Energy Regulatory Commission (FERC) has prepared a draft environmental impact statement (EIS) for the Phase II Modification Project and the Liquefaction Project. The Projects are proposed by Freeport LNG and are located in Brazoria County near the city of Freeport, Texas. The proposed Phase II Modification Project includes: modification to the previously authorized liquefied natural gas (LNG) vessel berthing dock, LNG transfer pipelines, LNG unloading arms, and the access road system at Freeport LNG’s existing Quintana Island terminal.

18 Nov 2013

Freeport Facility to be Authorized to Export More U.S. LNG

Freeport LNG terminal: Photo courtesy of the operators

The Energy Department has conditionally authorized Freeport LNG Expansion, L.P. and FLNG Liquefaction, LLC (Freeport) to export additional volumes of domestically produced liquefied natural gas (LNG) to countries that do not have a Free Trade Agreement (FTA) with the United States from the Freeport LNG Terminal in Quintana Island, Texas. Freeport previously received approval to export 1.4 billion cubic feet of natural gas a day (Bcf/d) of LNG from this facility to non-FTA countries on May 17, 2013.

20 Sep 2013

FMC Commissioner Gives Keynote on Panama Canal

Commissioner Doyle: Photo in public domain

Commissioner William P. Doyle of the Federal Maritime Commission, has given the keynote address at the Eno Center for Transportation Forum on the Panama Canal entitled: Lessons Learned and Implications for World Commerce. His comments on the future of the canal's LNG trade are also extracted below. Commissioner Doyle noted that the Obama Administration, members of Congress and state and local officials support the tremendous economic, business, job-supporting, energy and transportation related opportunities the expanded Canal will bring to the United States.

08 Aug 2013

DOE Authorizes Third Proposed Facility to Export LNG

The Energy Department announced it has conditionally authorized Lake Charles Exports, LLC (Lake Charles) to export domestically produced liquefied natural gas (LNG) to countries that do not have a Free Trade Agreement (FTA) with the United States from the Lake Charles Terminal in Lake Charles, Louisiana. Lake Charles previously received approval to export LNG from this facility to FTA countries on July 22, 2011. Subject to environmental review and final regulatory approval, the facility is conditionally authorized to export at a rate of up to 2 billion cubic feet of natural gas a day (Bcf/d) for a period of 20 years. The Department granted the first authorization to export LNG to non-FTA countries in May 2011 from the Sabine Pass LNG Terminal in Cameron Parish…

14 Jun 2011

Alternative Fuel: Defrosting LNG

As Cargo, Fuel or both; LNG is emerging as the clear and clean way forward for the maritime industry. The use of LNG as a marine fuel is not new. Vessels trading cryogenic LNG have burned boil-off natural gas in steam boilers for many years as a simple solution to maintaining necessary temperatures and pressures within cargo spaces. The use of the fuel varied according to the size of the ship and a boil off rate ranging between 0.10 to 0.18 percent of the total cargo. As a result of the variable quantities…

10 Jun 2011

LNG Gains Traction as Alternative Fuel

As Cargo, Fuel or both; LNG is emerging as the clear and clean way forward for the maritime industry. The use of LNG as a marine fuel is not new. Vessels trading cryogenic LNG have burned boil-off natural gas in steam boilers for many years as a simple solution to maintaining necessary temperatures and pressures within cargo spaces. The use of the fuel varied according to the size of the ship and a boil off rate ranging between 0.10 to 0.18 percent of the total cargo. As a result of the variable quantities…

12 Aug 2003

Technip USA Announces Contract Award for the Freeport LNG Terminal

Freeport LNG Development, L.P. and Technip USA Corporation, a subsidiary of Technip have signed a contract for the Front End Engineering Design (FEED) leading to the finalization of the EPC (engineering, procurement and construction) contract for its LNG receiving terminal to be located on Quintana Island near Freeport, Texas. The FEED is expected to be completed by the end of December with the EPC phase of the project beginning in the first quarter of 2004. Michael Smith, CEO of Freeport LNG Development, L.P., said, "Technip has considerable experience in LNG facility design and this contract continues the relationship established with Technip during their assistance in the preparation of the FERC filing documents for our terminal.

22 Jun 2004

FERC authorizes Freeport LNG project

The Federal Energy Regulatory Commission (FERC) issued an Order granting authorization for construction and operation of a liquefied natural gas (LNG) terminal on Quintana Island, near Freeport, Texas. The facility is to include, among other things, an LNG ship maneuvering area, a protected single-berth unloading dock, and a storm protection levee. Plans call for the facility to be in operation for the 2006-2007 winter heating season. Docket No. CP03-75-000 (HK Law).