Low Water Mississippi: USACE Outlines Action Plans

Press Release
Tuesday, December 25, 2012

The U.S. Army Corps of Engineers Mississippi Valley Division Commander discusses Corps' plans with state & local representatives.

The U.S. Army Corps of Engineers Mississippi Valley Division Commander Maj. Gen. John Peabody and St. Louis District Commander Col. Chris Hall met with state and local representatives yesterday in Alton, Ill., to discuss current and future actions the Corps will take to maintain a safe and reliable navigation channel during low water.

The meeting, which was led by Sen. Dick Durbin (D-Ill.), was also attended by Capt. Byron Black, U.S. Coast Guard commander of the Upper Mississippi River Sector, Rep. Jerry Costello (D-Ill.), Rep. John Shimkus (R-Ill.), Lt. Gov. Sheila Simon (D-Ill.) and river industry representatives.

"We've been preparing for this since early summer, which means continuous collaboration with our partners the U.S. Coast Guard and the navigation industry to help provide a safe and reliable channel on the greatest, navigable watershed in the world," Peabody said.

Peabody explained the removal of 890 cubic yards of limestone that began this week near Thebes, Ill., is just one phase of the action the Corps is taking to improve the navigation channel for the river industry. With the removal of the rock, Peabody said, the Corps' expects that restrictions on barges will not be necessary at this time.

"We remain cautiously optimistic that if we do have any interruptions, it will be short in duration as we continue to maintain a safe and reliable navigation channel," Peabody said.

The Corps also began increasing releases from Carlyle Lake December 15 to help provide the depth necessary for river commerce to pass Thebes before the rocks can be removed. The full extent of the releases is expected to reach Thebes by Dec. 24. This will provide an additional six inches of depth in this critical reach of the river. Releases will continue if needed until the river level increases through precipitation, or until Carlyle Lake reaches its winter pool elevation. With the additional release schedule, Carlyle Lake is expected to reach its winter pool level in approximately three weeks.

Peabody said the Corps is also looking at the possibility of additional releases from other reservoirs, if that becomes necessary.

During the meeting, Hall explained the dredging actions the Corps is undertaking and plans to continue through the low water. "The Dredge Potter has dredged more than 6 million cubic yards of material on the Upper and Lower Mississippi since it began operations in June."

"We will continue dredging problem areas, conducting channel patrols and surveys to keep commerce safely moving on the Middle Mississippi," Hall said.


 

Maritime Reporter February 2015 Digital Edition
FREE Maritime Reporter Subscription
Latest Maritime News    rss feeds

Technology

Interview: Nakilat's Samir Bailouni

SGMF Membership - Uncovered: An interview with Samir Bailouni, Nakilat The Society for Gas and Marine Fuel (SGMF) recently interviewed one of its members, Samir

First Deep Sea Exploration of the Perth Canyon Begins Today

The first deep-sea exploration of the Perth Canyon, Australia's largest undersea valley, will launch today, Phys.org is reporting. The 12-day expedition is backed

Eniram to Provide Boil-off Management for LNG Sector

Eniram Limited, the Finnish provider of energy management technology and data analytic services to the shipping industry, announced that it is releasing an onboard

Workboats

Mariner Medevaced in Alaska

An ailing mariner was medevaced from a fishing vessel in Beaver Inlet, approximately 13 miles southeast of Dutch Harbor, Sunday, the U.S. Coast Guard reported.   The

Editorial: Gettin’ Crabby with Deadliest Catch

As February is our traditional cruise shipping edition, naturally we’ve selected a fishing boat and two crabs for the cover. But as many of you may already know,

Haven Marine Bags Back To Back Dockings

Despite a slow start to the year, Haven Marine Services reports it is now seeing a change in fortunes with two dockings for Svitzer in quick succession, with one

Barges

Crowley Ships Massive Electrical Equipment

Crowley Maritime Corporation’s liner services group recently transported two massive electrical equipment enclosures with a combined weight of 196,000 pounds to San Juan, Puerto Rico.

Strip Club Barge Accused of Dumping Sewage into Harbor

Owners of floating Kodiak strip club indicted by Federal Grand Jury; Wild Alaskan operators accused of dumping raw sewage into Kodiak Harbor, Alaska   A federal

Conrad Shipyard Bags LNG Order

Energy infrastructure and LNG solutions provider WesPac Midstream and its subsidiary Clean Marine Energy (CME) have awarded a contract to Conrad Orange Shipyard

Government Update

Zeroing in on Zukunft

The U.S. Coast Guard Commandant addresses a packed Passenger Vessel Association meeting and outlines both the challenges and opportunities facing his organization.

Brazil Truckers Continue Roadblocks After Crackdown

Striking truck drivers resumed some roadblocks in Brazil on Monday even as the government cracked down on protesters and promised to implement a law to lower toll

Italy to Begin Naval Exercises off Libya

Italy will begin annual naval exercises this week near the coast of Libya, where a breakdown in order has allowed tens of thousands of migrants to try to reach

 
 
Maritime Careers / Shipboard Positions Maritime Standards Navigation Offshore Oil Pod Propulsion Salvage Ship Repair Shipbuilding / Vessel Construction Sonar Winch
rss | archive | history | articles | privacy | terms and conditions | contributors | top maritime news | about us | copyright | maritime magazines
maritime security news | shipbuilding news | maritime industry | shipping news | maritime reporting | workboats news | ship design | maritime business

Time taken: 0.1997 sec (5 req/sec)