Offshore Wind Floating TLP Model Tests Complete

MarineLink.com
Tuesday, July 16, 2013
PelaStar Model Testing: Photo courtesey of Glosten

US-based Glosten Associates (Glosten) announce that the 3-week scale-model testing of the PelaStar tension-leg platform (TLP) has been completed.

The three-week test program was conducted in support of the Offshore Wind Floating Platform Demonstration Project FEED Study awarded to Glosten by Energy Technologies Institute (ETI). The test results are being used to further demonstrate PelaStar’s technical feasibility and to calibrate state-of-the-art software used to design, analyze, and optimize the floating wind turbine system.

The 1:50-scale floating wind turbine model was tested in the world class offshore basin at the Maritime Research Institute Netherlands (MARIN). For this test, the PelaStar TLP was optimized for MARIN’s in-house test turbine, which models a 5MW turbine with a 126-meter rotor diameter.

The test model design was based on a full- scale platform designed in accordance with the new DNV standard for floating wind turbine structures (DNV-OS-J103) and optimized for the MARIN turbine. The simulated full-scale offshore conditions are representative of UK Round 3 conditions, and are characterized by a 55-meter water-depth, a 7.5-meter tide range, and an extreme significant wave height of 8.2 meters.

“We are excited about reaching this important milestone, advancing our technology, on schedule. When we complete the ETI FEED project by the end of the year we will be well positioned to execute the next phase of the project: building and installing the full scale 6MW floating turbine,” William Hurley, PelaStar Director and Glosten program lead, commented.

Andrew Scott, Programme Manager, Offshore Wind at ETI said: “Offshore wind must be affordable and cost competitive with alternative generation technologies. The ability of large floating turbines to access near-to-shore, high wind speed sites off the coast of the UK and elsewhere in the world could bring down the cost of electricity generation for the long term, helping to ensure that low carbon energy from offshore wind achieves costs comparable with other forms of low carbon generation. Our modelling and completed engineering design projects have shown that floating offshore wind farms could play a key role in providing affordable, secure and sustainable energy for the UK as part of a broader and balanced energy system.”

www. glosten.com

Maritime Reporter March 2014 Digital Edition
FREE Maritime Reporter Subscription
Latest Maritime News    rss feeds

Technology

At Hamburg port E-mobility Project, BESIC enters crucial phase

Ten battery-operated heavy goods vehicles now transport containers between ships and the yard at the highly automated handling facility in the HHLA Container Terminal Altenwerder (CTA).

Rolls-Royce Wins Heyerdahl Award

Rolls-Royce has been awarded the maritime Heyerdahl Award 2014. The award was presented by His Majesty King Harald at the Norwegian Shipowners’ Associations Annual Conference in Oslo March 31.

Imtech Extends VSAT Coverage Above Europe

Imtech Marine expanded its Global Ku-band VSAT network with additional coverage above Europe. Next to the Telstar 12 satellite and the Intelsat 21, the Eutelsat

Wind Power

Mammoet Uses World’s Biggest Crawler Crane to Install Legs on Ship

Mammoet, a global company in engineered heavy lifting and transport, said it is currently employing its LR13000, the biggest crawler crane in the world, to install

UK Subsidises 8 Renewable Energy Contracts

The British government on Wednesday awarded investment contracts under a new subsidy regime to eight renewable energy projects, including five offshore wind farms and three biomass plants.

POSH raises $311m in Singapore IPO

POSH prices IPO at S$1.15 per share, near bottom of indicative range. POSH focuses on service to production, maintenance and is keen on growing offshore accommodation business.

Offshore Energy

Diamond Offshore Shares on the Rise

Diamond Offshore Drilling Inc, one of the world's top five offshore rig contractors, reported a better-than-expected quarterly profit as it cut drilling costs and hiked prices,

Offshore O&G: Cuts, Delays in Norway as Costs Soar

More oil and gas projects in Norway could be put on hold because of rising costs, adding to a growing list of developments that have been delayed or called off,

Norway's Oil Sector May Face More Project Cuts, Delays

More oil and gas projects in Norway could be put on hold because of rising costs, adding to a growing list of developments that have been delayed or called off,

 
 
Maritime Careers / Shipboard Positions Maritime Contracts Maritime Standards Navigation Offshore Oil Pipelines Port Authority Salvage Ship Electronics Sonar
rss | archive | history | articles | privacy | contributors | top maritime news | about us | copyright | maritime magazines
maritime security news | shipbuilding news | maritime industry | shipping news | maritime reporting | workboats news | ship design | maritime business

Time taken: 0.2097 sec (5 req/sec)