Huntington Ingalls Industries (NYSE:HII) announced today that its Newport News Shipbuilding (NNS) division has reached 90 percent structural completion in the building of the nuclear-powered aircraft carrier Gerald R. Ford (CVN 78).


Shipbuilders successfully added three units to the ship last week. Two of the units were sponsons, which are structures that project from the side of the aircraft carrier hull and provide the space needed for flight deck operations. One of the sponsons was 140 feet long and weighed 391 metric tons, making it one of the largest sponsons to be erected. In addition, shipbuilders installed 3 million feet of cable of the estimated total 10 million feet to be installed.


"The entire construction team has done a great job in reaching the 90 percent structural completion milestone," said Rolf Bartschi, NNS' vice president of CVN 78 carrier construction. "All of our shipbuilders take great pride in seeing the flight deck take shape and in the work they have accomplished to build the systems and spaces within the ship. The lifts we have accomplished are massive, which is in keeping with our larger-unit build strategy. Our electricians have installed 3 million feet of cable to date and install on average 10,000 feet of cable a day. Our shipbuilders continue to demonstrate their capabilities and commitment to a quality product."


Gerald R. Ford is being built using modular construction, a process where smaller sections of the ship are welded together to form large structural units, equipment is installed, and the large units are lifted into the dry dock. Of the nearly 500 total structural lifts needed to complete the ship, 446 have been accomplished. The lifts are accomplished using the shipyard's 1,050-metric ton gantry crane, one of the largest in the Western Hemisphere.


Gerald R. Ford represents the next-generation class of aircraft carriers. The first-in-class ship features a new nuclear power plant, a redesigned island, electromagnetic catapults, improved weapons movement, an enhanced flight deck capable of increased aircraft sortie rates, and growth margin for future technologies and reduced manning. Ford has been under construction since November 2009. The ship is scheduled to launch in 2013.

Maritime Reporter August 2014 Digital Edition
FREE Maritime Reporter Subscription
Latest Maritime News    rss feeds

People & Company News

Sri Lanka Port Project: China Merchants, CHEC Invest $601-M

Two of China's largest port operators and engineering firms have agreed to invest in a $601 million terminal in Sri Lanka's Hambantota port, part of a series of

Viking Supply Ships Sell PSV 'SBS Cirrus'

Rederi AB TransAtlantic subsidiary Viking Supply Ships says it has sold the 1985 built platform supply vessel SBS Cirrus. The vessel has been delivered to its new owners,

UK Chamber Stance Neutral on Scottish Independence

The UK Chamber of Shipping is taking a neutral position in the Scottish independence debate and has given both the Yes and Better Together sides space on its website

Shipbuilding

Scorpio Tankers Receive 7 More Newbuildings

Scorpio Tankers Inc. say it has recently taken delivery of seven newbuilding vessels as follows: STI Madison and STI Park, LR2 product tankers, were delivered

LHA 6 'America' Maiden Voyage Completes at San Diego

The Navy informs that the soon to-be-commissioned amphibious assault ship 'USS America' (LHA 6) arrived at its homeport of San Diego after completing its two-month

Austal Delivers Fourth JHSV to the US Navy

The U.S. Navy accepted delivery of USNS Fall River (JHSV 4) from Austal USA yesterday, a week shy of six months from the date they took delivery of JHSV 3. This

Navy

Simmons Assumes Command of USS James E. Williams

Capt. Anthony L. Simmons relieved Cmdr. Curtis B. Calloway as commanding officer of the guided-missile destroyer USS James E. Williams (DDG 95) at sea on Sept.

LHA 6 'America' Maiden Voyage Completes at San Diego

The Navy informs that the soon to-be-commissioned amphibious assault ship 'USS America' (LHA 6) arrived at its homeport of San Diego after completing its two-month

Today in U.S. Naval History: September 16

Today in U.S. Naval History - September 16 1854 - Cdr. David G. Farragut takes possession of Mare Island, the first U.S. Navy Yard on the Pacific. 1917 -

News

Bangladeshi Albedo Survivors Helped by their Govt.

Yesterday, 16th September 2014, Chirag Bahri, MPHRP's Regional Director for South Asia, attended a ceremonial event organised by the Ministry of Shipping, Bangladesh

Simmons Assumes Command of USS James E. Williams

Capt. Anthony L. Simmons relieved Cmdr. Curtis B. Calloway as commanding officer of the guided-missile destroyer USS James E. Williams (DDG 95) at sea on Sept.

CEVA Opens European Center of Logistics Excellence

CEVA Logistics, a leading global supply chain management company, today announced the opening of its first Center of Logistics Excellence in Europe. Situated in Ashby de la Zouch,

Eye on the Navy

Simmons Assumes Command of USS James E. Williams

Capt. Anthony L. Simmons relieved Cmdr. Curtis B. Calloway as commanding officer of the guided-missile destroyer USS James E. Williams (DDG 95) at sea on Sept.

Austal Delivers Fourth JHSV to the US Navy

The U.S. Navy accepted delivery of USNS Fall River (JHSV 4) from Austal USA yesterday, a week shy of six months from the date they took delivery of JHSV 3. This

Washington Navy Yard Remembers Shooting One Year Later

It was a day no one who worked on the Washington Navy Yard will ever forget. Shortly after 8 a.m., on Sept. 16, 2013, Navy contractor Aaron Alexis entered the Naval

Vessels

Fifth Jackup Contract for Keppel from Gulf Drilling

Keppel FELS Limited, a wholly owned subsidiary of Keppel Offshore & Marine, has secured a contract from Gulf Drilling International Ltd. of Qatar to build a

Fugro Takes Delivery of 2nd Coastal Survey Vessel from Damen

Fugro yesterday took delivery of its second of the three Fugro Offshore Coastal Survey Vessels (FOCSV) being built by Damen. The Fugro Pioneer is a compact,

Austal Delivers Fourth JHSV to the US Navy

The U.S. Navy accepted delivery of USNS Fall River (JHSV 4) from Austal USA yesterday, a week shy of six months from the date they took delivery of JHSV 3. This

 
 
Maritime Careers / Shipboard Positions Maritime Contracts Maritime Standards Naval Architecture Navigation Port Authority Ship Simulators Shipbuilding / Vessel Construction Sonar Winch
rss | archive | history | articles | privacy | terms and conditions | contributors | top maritime news | about us | copyright | maritime magazines
maritime security news | shipbuilding news | maritime industry | shipping news | maritime reporting | workboats news | ship design | maritime business

Time taken: 0.2662 sec (4 req/sec)