Costa Concordia One Step Closer to Refloating

MarineLink.com
Tuesday, April 29, 2014
Photo courtesy the Parbuckling Project

Operations for the installation of the first sponson completed

Operations to install the first of the 19 sponsons to be positioned for the refloating of the Concordia wreck concluded at 1 p.m. Monday, April 28 after 2.5 days of work, according to the Concordia wreck removal project informative website.

The sponson S13, noted as the biggest in weight and size, is now positioned on the starboard side at about 11 meters in depth from the artificial seabed on which the Concordia rests since the parbuckling completed in September.

The sponson reached Giglio Island via barge and was unloaded and placed into the water through rotating crane of pontoon Conquest. It was then completely filled with water so that it could be submerged and connected through a sophisticated automatic system of the chains that keep it anchored to the wreck. Technicians next partially emptied the sponson to make it lighter and give it the buoyancy needed to keep the chains tensioned.

Before refloating, another 14 sponsons need to be positioned on the starboard side and four on the port side of the Concordia. Sponsons will be completely emptied to provide the buoyancy needed to refloat the Concordia and prepare it for transportation.

theparbucklingproject.com
 

Maritime Reporter July 2015 Digital Edition
FREE Maritime Reporter Subscription
Latest Maritime News    rss feeds

Cruise Ship Trends

Cruise Industry Wins Key Norovirus Judgment

In what is being seen as a landmark decision, Hill Dickinson is the first law firm to have successfully defended a UK class action case involving a Norovirus outbreak onboard a cruise liner.

Royal Caribbean's Profit Rises 34 Percent

Royal Caribbean Cruises Ltd, the world's second-largest cruise operator by revenue, reported a 34 percent rise in quarterly profit as passengers spent more onboard

Long Beach Port Celebrates Environmental Successes

Shipping lines, environmental organizations, trucking companies, terminal operators and a railroad were honored today, July 29, by Long Beach Mayor Dr. Robert

Passenger Vessels

Thordon Bearings Secures AK Ferry Contract

Thordon Bearings has received an order to supply its COMPAC system to two Alaska Ferry newbuilds under construction at the Vigor Industrial shipyard in Ketchikan, Alaska.

Calais Port Blocked Again by Protesters

Protesting ferry-workers blocked road access to the northern French port of Calais with burning tyres on Friday, police said. The workers have in recent weeks

Royal Caribbean's Profit Rises 34 Percent

Royal Caribbean Cruises Ltd, the world's second-largest cruise operator by revenue, reported a 34 percent rise in quarterly profit as passengers spent more onboard

Casualties

Three Rescued on Lake Tahoe

The Coast Guard and multiple agencies rescued three people Wednesday evening after they were reported missing on Lake Tahoe. At 9:45 p.m., Coast Guard Sector

Fire-stricken Icebreaker Overhauled

SENER concludes the Almirante Irizar icebreaker engineering works for re-outfit and overhaul   SENER reports it has completed the engineering works relating to

WGMA Urges Participation in Menhaden Survey

The West Gulf Maritime Association (WGMA) is urging its members with ships arriving at any port in the western US Gulf to participate in the Menhaden survey.

 
 
Maritime Careers / Shipboard Positions Maritime Contracts Maritime Security Maritime Standards Navigation Pipelines Pod Propulsion Salvage Ship Electronics Ship Repair
rss | archive | history | articles | privacy | contributors | top maritime news | about us | copyright | maritime magazines
maritime security news | shipbuilding news | maritime industry | shipping news | maritime reporting | workboats news | ship design | maritime business

Time taken: 0.1631 sec (6 req/sec)