Data Convincing for Container Ship Noise Replacement

MarineLink.com
Wednesday, June 05, 2013

DNV gathered before and after operational-performance data which indicate that redesigning the bulbous bow of slow-steaming container ships can produce fuel savings of 5% or above. These “nose jobs” can have a payback time of less than a year, DNV said.

Hyundai Merchant Marine (HMM) operates a series of 8,600 TEU container vessels which were designed and built for high speed. These vessels are actually able to operate at 27 knots. However, today the vessels are “slow steaming”, operating in the range of 15 to 18 knots. At these speeds, the existing bulb is not efficient.

To quantify the possible savings potential, DNV carried out a comprehensive study to develop a new bulbous bow shape optimized for the expected trading conditions. A cost-benefit assessment was conducted based on the estimated savings and this created the basis for HMM to go ahead with a conversion.

Based on input from DNV, Daewoo Ship Engineering Company (DSEC) carried out the structural design work. The conversion of the first vessel, the Hyundai Brave, was completed in March 2013.

Onboard measurements have shown that the $680,000 modification has reduced fuel consumption by almost 1,000 tons per year.

“The performance of the new bulbous has carefully been evaluated as part of verification over about 2 months period after delivery and fuel saving in operation so far has been found to be around 5% or above. The payback period is expected to be much shorter than the 1 year originally estimated,” said Taeg-Gyu Lee executive vice president of HMM.

“Close cooperation between DNV, the structural designer and the yard ensured the timely execution of the design and installation work,” said Jost Bergmann, DNV’s Business Director for Container Ships. “Improvements in fuel economy have now been demonstrated in loaded, light and full capacity operations.”

The project, starting with the initial planning phase, was completed in 14 weeks and, with pre-fabrication, the yard erection work was completed in only two weeks during the vessel’s regular docking cycle.

DNV developed a series of potential bulb shapes, made to suit the new operating profile of the Hyundai Brave, that where all tested by use of computational fluid dynamics. The new bulb does not add to the vessel’s overall length and is five tons lighter than the original.

DNV said it is confident that the recorded success of this project will assist other owners looking to improve the competitiveness of older vessels.

“Existing ships have to compete with a new breed of efficient and flexible designs,” Mr. Bergmann said. “One result of the high design speed of many existing container ships is that the bulb is highly tuned to reach the maximum speed. The new reality for much of the existing fleet is that this affects efficiency at lower speeds. DNV’s bulb optimization service now has hard data to demonstrate.”

www.dnv.com

Maritime Reporter February 2015 Digital Edition
FREE Maritime Reporter Subscription
Latest Maritime News    rss feeds

Ship Repair & Conversion

More MERUS Rings for MS Rotterdam

Pronomar has installed two additional MERUS rings on board Holland America Line’s MS Rotterdam, this time in the wellness area for the steam generators.   The

Wärtsilä, CME Offer ‘Scrubber Finance’

Funding concept promotes installation of scrubber systems by offering financing to shipowners, with returns taken from fuel price spread   In a move intended

Alphatron Marine VSAT Systems for 11 Workboats

Alphatron Marine has signed a lease contract with Seacontractors for no less than 11 vessels to provide satellite hardware and data solution packages.   Alphatron

Container Ships

IACS Comments on MOL Comfort Report

The International Association of Classifications Societies (IACS) informs it will study the final report issued in Japan by the Committee on Large Container Ship Safety (CLCSS),

Are Megaships Game Changers?

Bragging rights for the world’s largest container ship have changed hands four times in as many months and keep on shifting again, says a report in the Bloomberg.

Port of San Pedro Seeks to Fund Upgrades with European Roadshow

Ivory Coast's second largest port of San Pedro will hold a roadshow in France and Britain next month as it seeks to raise 180 billion CFA francs ($300 million) to fund upgrades,

Vessels

More MERUS Rings for MS Rotterdam

Pronomar has installed two additional MERUS rings on board Holland America Line’s MS Rotterdam, this time in the wellness area for the steam generators.   The

First LNG-powered EcoLiner Launched

Europe’s greenest inland vessel debuts Damen group innovations   Damen Shipyards Group launched the first LNG-powered Damen EcoLiner inland shipping tanker

Zamakona to Deliver Tuna Freezer Vessel

Zamakona Yards to deliver tuna freezer vessel Jai Alai to the Echebastar Group   This Saturday, March 7, Zamakona Shipyards in Santurce will deliver its construction number 737,

 
 
Maritime Careers / Shipboard Positions Maritime Security Navigation Offshore Oil Pipelines Pod Propulsion Port Authority Shipbuilding / Vessel Construction Sonar Winch
rss | archive | history | articles | privacy | terms and conditions | contributors | top maritime news | about us | copyright | maritime magazines
maritime security news | shipbuilding news | maritime industry | shipping news | maritime reporting | workboats news | ship design | maritime business

Time taken: 0.1716 sec (6 req/sec)