Restoring the NY-NJ Harbor Estuary

By James D’Ambrosio
Thursday, August 28, 2014
A New York District U.S. Army Corps of Engineers' crew places mollusk shells into waters off Governors Island in New York Harbor October 6, 2010, creating an artificial oyster reef. The effort was part of an experiment examining the possibility of re-creating a healthy oyster population in New York and New Jersey waters. (Photo: Dan Desmet, New York District Public Affairs)

Significant challenges often require a team effort. Restoring the New York-New Jersey Harbor Estuary is one of them.

A group of professionals from the Army Corps of Engineers, New York District, joined 200+ scientists, engineers, academics and restoration professionals on June 3, 2014 at a major symposium in Manhattan discussing progress restoring the NY-NJ Harbor Estuary and initiatives to continue improving the area’s ecological health, contributing to the region’s coastal resiliency. The conference, “Restoring the New York-New Jersey Harbor Estuary: Ensuring Ecosystem Resilience and Sustainability in a Changing Future,” was hosted by the NY-NJ Harbor Estuary Program’s Restoration Workgroup.

State of the Estuary: Past & Present
The Estuary, where fresh water from the Hudson, Hackensack, Passaic, Rahway and Raritan Rivers meets salt water from the Atlantic Ocean, provides a rich environment for plant and animal life. Spanning a 25-mile radius encircling the Statue of Liberty, the area includes 1,000 miles of coastline, 1,600 miles of open water and 500+ species of birds and fish.

Over the years, shoreline development and industrialization has destroyed nearly 85 percent of wetlands; oyster reefs (a bed of oysters filtering water and reducing wave action) and eelgrass beds (submerged aquatic plants) have completely disappeared. Most damage occurred prior to passage of the Clean Water Act in 1978, when wetlands were filled in with hard surfaces and storm-water runoff went unchecked. While the Estuary has improved since the 1980s, it’s still plagued by degraded habitat, poor water quality, contaminated sediments and impediments to fish swimming upstream. In addition, Hurricane Sandy battered shorelines and damaged wastewater treatment plants releasing over 10 billion gallons of untreated and partially-treated sewage, negatively impacting habitats.

Comprehensive Restoration Plan
But things are improving. The District, agency partners and regional stakeholders have been making progress for a number of years. In 1999, Congress authorized the Corps to conduct a feasibility study to develop a long-term restoration plan for the Estuary. In the following years, the draft Hudson-Raritan Estuary Comprehensive Restoration Plan (CRP) was released and ultimately adopted by NY-NJ Harbor Estuary Program (NY-NJ HEP) in 2009. As part of the CRP outreach efforts it’s been updated to include stakeholder input and lessons learned from Sandy. An executive summary of the 2014 plan was showcased at the symposium.

The CRP ─ a collaboration with the Port Authority of New York and New Jersey, the NY/NJ HEP and 100+ regional partners ─ is a master plan guiding conservation and restoration efforts in the region, serving as a shared vision of a vibrant Estuary. Lisa Baron, New York District Project Manager, and Peter Weppler, Chief, Environmental Analysis Branch, were major contributors. “A great deal of effort and input from nearly 130 organizations helped shape the 2014 Comprehensive Restoration Plan,” noted Baron. “The symposium was an excellent venue to highlight the revisions to the plan ─ targets and objectives, achievements, future opportunities, and meeting implementation challenges.”

Restoration Targets
The plan focuses on 12 Target Ecosystem Characteristics (measurable objectives related to ecosystem restoration), each representing an important feature needed for a healthy estuary. There are both short-term (2020) and long-term (2050) goals for each. Targets include:

  • Wetlands: Create and restore coastal and fresh-water wetlands at a rate exceeding loss or degradation, resulting in a net gain in acreage.
  • Habitat for water birds: Restore and protect roosting, nesting and foraging habitat (inland trees, wetlands and shallow shorelines) for long-legged wading birds.
  • Coastal & maritime forests: Create a linkage of forests for migrant birds and plant communities.
  • Oyster reefs: Establish sustainable oyster reefs at several locations.
  • Eelgrass beds: Establish eelgrass beds at several locations.
  • Shorelines & shallows: Restore shoreline vegetation, create sloped areas in tidal zones, and clear shallows (the bottom is visible).
  • Habitat for fish, crab & lobsters: Create functionally-related habitats in each region of the Estuary.
  • Tributary connections: Reconnect and restore fresh-water streams to the Estuary, promoting quality habitats for aquatic organisms.
  • Enclosed & confined waters: Improve water quality in all enclosed waterways and tidal creeks, matching or exceeding receiving waters.
  • Sediment contamination: Remove areas with contaminated sediment until all are free of pollution.
  • Public access: Improve access to water and create linkages to recreational areas for swimming, boating and fishing.
  • Acquisition: Protect environmentally-sensitive coastal areas from development through land acquisition.

Symposium Activities
Baron, Chair of the Harbor Estuary Program’s Restoration Work Group, opened the conference with a presentation, “The Waters We Share: A Shared Vision for Restoring the Estuary,” outlining revisions to the plan, updates, and restoration progress. She also moderated a panel, “Progress and Next Steps for Comprehensive Restoration Planning and Actions in the Estuary,” with participants sharing progress towards the goals.

Restoration Progress
Significant progress has been made since the 2009 draft Comprehensive Restoration Plan, including:

  • Restoring 220+ acres of wetlands.
  • Implementing 15 oyster pilot sites totaling 1.38 acres.
  • Removing three dams on the Raritan River in New Jersey.
  • Improving 18+ miles of fish habitat.
  • Restoring 200+ acres of forest and 80 acres of dune and grassland habitat.
  • Establishing seven eelgrass test beds.
  • Acquiring 250+ acres for habitat preservation.
  • Restoring habitat and foraging habitat (ability to seek or obtain food) of an island for water birds.
  • Enhancing or acquiring 12 public access sites.
  • Developing assessment tools and programs to improve the ecology of urban shorelines.

Historically, restoration activities centered on improving the Estuary’s health and providing ecosystem benefits. After Sandy’s severe impact, regional stakeholders are referring to the CRP to incorporate ‘green’ strategies to better manage flood risk, attenuate wave energy, and create more sustainable and resilient shorelines. This expanded focus was addressed by two panels. Weppler served on one discussing integrating nature-based features into coastal storm risk management with wetlands, oyster reefs, dunes and upland forests. He spoke about the District’s Sandy Coastal Restoration Program, ongoing studies and resiliency practices.

Exploring Partnerships
A third panel discussed the need for partnerships. A potential partnership could be the U.S. Department of Housing and Urban Development’s “Rebuild by Design” ─ a year-long competition where teams of architects, engineers and restoration professionals developed proposals promoting resilience in Sandy-impacted areas. One winner, “Living Breakwaters,” is a design that plans to manage flood risk to Staten Island’s south shore through a series of breakwaters reducing wave energy. A second, “The New Meadowlands,” is a system of berms and marshes designed to reduce ocean surges and collect rainfall reducing risk of sewer overflows in nearby communities.

Breakout groups focused on one central question: What ingredients are needed to meet the region’s challenging restoration agenda? Feedback included the need to: a) secure resources (capital, management, monitoring); b) improve community engagement; c) consolidate information into a single data center; d) overcome regulatory hurdles; and e) develop an evaluation tool balancing and integrating the benefits of nature-based (soft) and man-made (hard) coastal storm risk reduction measures.

Moving Forward
The next steps include finalizing the 2014 Comprehensive Restoration Plan that is expected to be available on the District’s Web site (www.nan.usace.army.mil) in fall 2014, and a feasibility study seeking new construction authority (funding) for restoration projects. Until then, work continues through existing programs.
 

  • Lisa Baron, project manager, U.S. Army Corps of Engineers, New York District, displays an executive summary of the Draft 2014 Comprehensive Restoration Plan, a document guiding restoration efforts in the New York-New Jersey Harbor Estuary, during a conference in Manhattan. (Photo: James D'Ambrosio, New York District Public Affairs.)

    Lisa Baron, project manager, U.S. Army Corps of Engineers, New York District, displays an executive summary of the Draft 2014 Comprehensive Restoration Plan, a document guiding restoration efforts in the New York-New Jersey Harbor Estuary, during a conference in Manhattan. (Photo: James D'Ambrosio, New York District Public Affairs.)

  • Participants at a major environmental symposium in New York City study a display outlining salt marsh restoration. The symposium,

    Participants at a major environmental symposium in New York City study a display outlining salt marsh restoration. The symposium, "Restoring the New York-New Jersey Harbor Estuary: Ensuring Ecosystem Resilience and Sustainability in a Changing Future," was held June 3, 2014 in Manhattan, attracted more than 200 scientists, engineers, academics and restoration professionals discussing progress and new initiatives to restore the Estuary. (Photo: James D'Ambrosio, New York District Public Affairs)

  • Peter Weppler, chief, Environmental Analysis Branch, U.S. Army Corps of Engineers, New York District, presents an overview of nearly 60 coastal storm risk management projects along the New York and New Jersey coast during a presentation at an environmental conference. (Photo: James D'Ambrosio, New York District Public Affairs.)

    Peter Weppler, chief, Environmental Analysis Branch, U.S. Army Corps of Engineers, New York District, presents an overview of nearly 60 coastal storm risk management projects along the New York and New Jersey coast during a presentation at an environmental conference. (Photo: James D'Ambrosio, New York District Public Affairs.)

  • U.S. Army Corps of Engineers, New York District employees converse during a conference discussing the restoration of New York and New Jersey waters in the greater metro area. From Left to Right: Michael Morgan (lead geographer), Gail Woolley (hydraulic engineer), Steven Weinberg (lead civil engineer), and Danielle Tommaso (project planner). (Photo: James D'Ambrosio, New York District Public Affairs.)

    U.S. Army Corps of Engineers, New York District employees converse during a conference discussing the restoration of New York and New Jersey waters in the greater metro area. From Left to Right: Michael Morgan (lead geographer), Gail Woolley (hydraulic engineer), Steven Weinberg (lead civil engineer), and Danielle Tommaso (project planner). (Photo: James D'Ambrosio, New York District Public Affairs.)

  • Lisa Baron, project manager, U.S. Army Corps of Engineers, New York District, displays an executive summary of the Draft 2014 Comprehensive Restoration Plan, a document guiding restoration efforts in the New York-New Jersey Harbor Estuary, during a conference in Manhattan. (Photo: James D'Ambrosio, New York District Public Affairs.)
  • Participants at a major environmental symposium in New York City study a display outlining salt marsh restoration. The symposium,
  • Peter Weppler, chief, Environmental Analysis Branch, U.S. Army Corps of Engineers, New York District, presents an overview of nearly 60 coastal storm risk management projects along the New York and New Jersey coast during a presentation at an environmental conference. (Photo: James D'Ambrosio, New York District Public Affairs.)
  • U.S. Army Corps of Engineers, New York District employees converse during a conference discussing the restoration of New York and New Jersey waters in the greater metro area. From Left to Right: Michael Morgan (lead geographer), Gail Woolley (hydraulic engineer), Steven Weinberg (lead civil engineer), and Danielle Tommaso (project planner). (Photo: James D'Ambrosio, New York District Public Affairs.)
Maritime Reporter July 2015 Digital Edition
FREE Maritime Reporter Subscription
Latest Maritime News    rss feeds

Finance

Harper Government Invests in Naufrage Harbor

The Honorable Gail Shea, Minister of Fisheries and Oceans, announced today an investment to improve safety and working conditions for fishermen at Naufrage Harbor, Prince Edward Island.

Strategic Marine’s Stock Program Full Power Ahead

Strategic Marine, the specialist shipbuilder and fabricator, has confirmed its stock program of personnel transport vessels is market-ready. “Our stock program

Shift to Contract Labor in U.S. Maritime, Offshore Sectors Underway

Maritime and Offshore recruiter Faststream has reported a shift in attitude towards temporary, project and consulting work following a recent survey to over 1,000 candidates in North America.

Environmental

Canada's First LNG Ferry Launches with Bestobell Valves

Bestobell Valves is celebrating supplying cryogenic valves to Canada’s first LNG-fuelled ferry – the MV Armand-Imbeau II, which has recently been launched.   It

Harper Government Invests in Naufrage Harbor

The Honorable Gail Shea, Minister of Fisheries and Oceans, announced today an investment to improve safety and working conditions for fishermen at Naufrage Harbor, Prince Edward Island.

Fire Aboard USS Mount Whitney

A fire broke out on board USS Mount Whitney (LCC 20) while the ship was in Viktor Lenac Shipyard (Rijeka, Croatia) July 31, 2015. There were no personnel injuries in the fire,

News

BG Group Starts up Sixth FPSO in the Santos Basin

BG Group announced first oil from the Cidade de Itaguaí floating, production, storage and offloading (FPSO) vessel, the sixth unit to start production across the

Diana Charters Containership to Maersk

Container shipping company Diana Containerships Inc. announced that, through a separate wholly-owned subsidiary, it entered into a time charter contract with Maersk

GasLog Orders Two LNG Carriers

GasLog Ltd. today announced that it has ordered two new 174,000 cubic meter LNG carriers from Hyundai Heavy Industries Co., Ltd. ("Hyundai") in South Korea.

Government Update

ASEAN: China Shuns South China Sea Dialogue

Chinese Vice Foreign Minister Liu Zhenmin said on Monday the disputed South China Sea should not be discussed at a meeting of the Association of Southeast Asian Nations (ASEAN).

Contship Italia Signs Iran MoU

Contship Italia Spa, also on behalf of Eurogate GmbH & Co. KGaA, KG, recently signed a strategic Memorandum of Understanding (M.O.U.) with Sina Port & Marine Company (SPMCO),

Boxships Collide in Port Klang, Malaysia

The container ships MOL Empire and Northern Democrat collided at around 1430 LT Aug 1 in Westport harbor at Port Klang, Malaysia, reportedly while mooring.   Container or containers fell overboard,

 
 
Maritime Careers / Shipboard Positions Maritime Contracts Maritime Security Naval Architecture Navigation Pod Propulsion Ship Electronics Ship Repair Shipbuilding / Vessel Construction Sonar
rss | archive | history | articles | privacy | contributors | top maritime news | about us | copyright | maritime magazines
maritime security news | shipbuilding news | maritime industry | shipping news | maritime reporting | workboats news | ship design | maritime business

Time taken: 0.3163 sec (3 req/sec)