Port of Rotterdam Takes Steps to Stop Delays

By Joseph R. Fonseca
Thursday, August 07, 2014
Port of Rotterdam

 

The Port of Rotterdam is taking measures to eliminate congestion at the ECT Delta Terminal and the Euromax Terminal. Inland waterway vessels and feeder vessels have been experiencing delays at these terminals for some time. Improvements implemented at these terminals have not had the desired effect up until now.

The inconvenience experienced by the port's customers and users is of such magnitude that the Port of Rotterdam Authority has taken the initiative of developing solutions to this problem. It became clear that all parties involved wanted to cooperate in order to improve the situation.

Three potential measures were identified pursuant to meetings with ECT, LINC (inland container shipping sector), Uniport Terminal and the Kramer Group/RCT.
 
Part of the inland waterway vessels, particularly those vessels transporting smaller numbers of containers to and from the port will be handled at the Rotterdam Container Terminal (RCT) located adjacent to the Delta Terminal. ECT will decide which ships will be handled by RCT. The operator will then be in direct contact with RCT. RCT will organise various related aspects, such as a berth, the unloading of containers and the overland transport to the Delta Terminal. This will unburden the water side of the Delta Terminal. This approach has since been implemented and operations can be further scaled up.
 

Bundling of containers in the Port of Moerdijk (M.C.T.). Inland waterway vessels with a very high capacity will subsequently shuttle between Moerdijk and the Maasvlakte. Because the cranes on larger ships can operate more efficiently, the quay at the Maasvlakte will be used more efficiently. This option is currently already available, but can be further scaled up.

Bundling of inland shipping containers, and if necessary road containers, at the Uniport Terminal in the Waalhaven area. This is similar to the bundling in Moerdijk and results in greater efficiency at the Maasvlakte. This option is currently being worked out in further detail.

The three measures are primarily focused on handling inland shipping traffic. The expectation is that this will subsequently free up quay and labour capacity in favour of sea-going vessels.

 A key cause of the congestion is due to the arrival of large intercontinental container ships outside scheduled/planned times. Hundreds of hinterland movements (**) are connected with the mainland vessels, whose scheduling is consequently disrupted as well. Other ports are also faced with this problem.

 (*) In addition to measures over the short term, the container sector continues to work intensively in structural handling improvements for the longer term. For example by implementing Nextlogic for the inland shipping sector.

 (**) By way of illustration: a very large container ship can load and unload approximately 10,000 containers (TEU) during each call to port. On average, these containers are transported to and from the port by 1,560 trucks, 32 inland waterway vessels, 10 feeder ships (coasters) and 19 trains.

Maritime Reporter September 2014 Digital Edition
FREE Maritime Reporter Subscription
Latest Maritime News    rss feeds

Ports

First Damen ASD 2810 Leaves for Trinidad

First delivery of Damen ASD Tug 2810, ARC Towage signed four contracts total in Barcelona, Spain On July 31, 2013, ARC Towage signed four contracts at the Netherlands

Bridge Milestone Celebrated at Port of Long Beach

Port, City and Caltrans officials, along with an international team of builders and designers, celebrated a key milestone today in the Gerald Desmond Bridge

Hamburg Süd opens office in Gandhidham, India

Hamburg Süd announced opening of an office in Gandhidham, India, on 1st October 2014. It is the second branch office in the state of Gujarat. Hamburg Süd already has three offices in Mumbai,

News

First Damen ASD 2810 Leaves for Trinidad

First delivery of Damen ASD Tug 2810, ARC Towage signed four contracts total in Barcelona, Spain On July 31, 2013, ARC Towage signed four contracts at the Netherlands

TOTE Finalizes Charter for LNG Containerships

World’s first LNG powered containerships to serve Puerto Rico TOTE, Inc. announced an agreement today between its operating companies TOTE Shipholdings Inc.

Hamburg Süd Opens Office in India

Hamburg Süd announced the opening of an office in Gandhidham, India, on October 1, 2014. It is the second branch office in the state of Gujarat. Hamburg Süd already has three offices in Mumbai,

Logistics

TOTE Finalizes Charter for LNG Containerships

World’s first LNG powered containerships to serve Puerto Rico TOTE, Inc. announced an agreement today between its operating companies TOTE Shipholdings Inc.

Hamburg Süd Opens Office in India

Hamburg Süd announced the opening of an office in Gandhidham, India, on October 1, 2014. It is the second branch office in the state of Gujarat. Hamburg Süd already has three offices in Mumbai,

GAC Marine Logistics Shifts Central Office to Singapore

In a move that brings it closer to key Asian markets, ship spares logistics specialist GAC Marine Logistics (GML) has relocated its head office to Singapore. The

 
 
Maritime Contracts Maritime Security Maritime Standards Navigation Offshore Oil Pipelines Salvage Ship Repair Sonar Winch
rss | archive | history | articles | privacy | terms and conditions | contributors | top maritime news | about us | copyright | maritime magazines
maritime security news | shipbuilding news | maritime industry | shipping news | maritime reporting | workboats news | ship design | maritime business

Time taken: 0.1855 sec (5 req/sec)