Troll A Tie In Success for Pipeline Specialist STATS Group

(Press Release)
Thursday, June 28, 2012

Specialist engineering company, STATS Group, has completed an 18 month design, manufacturing and installation project to enable the tie-in of a fifth pipeline on Statoil’s Troll A Platform.

Statoil’s Troll A platform, located off the west coast of Norway, utilises a system of seal tubes to tie-in risers which are run down the inside of a dry concrete leg. The seal tubes were concreted in place at the base of the riser leg on the gravity base structure in 1991. There are seven seal tubes – four designed for large bore pipe up to 36” - and three designed for smaller diameter pipe up to 20”.

When the platform was commissioned in 1995, three pipelines were pulled-in through the seal tube system - two 36” pipes for the export to Kollsnes and one 20” for an import line. In 1997 a fourth pipeline was tied-in. This time the line was a 16” which utilised the second smaller seal tube, however the seal cartridge was revised to utilise a compression seal rather than the inflatable seal used in the first three operations.

Statoil approached STATS to perform an engineering study to identify the procedures and apparatus required to perform another pipeline tie-in utilising one of the remaining unused seal tubes. The pipeline is a new 62.5 km, 36” pipeline (P12) which is to be installed between Troll A and Kollsnes in Norway.

STATS primary role was to design, manufacture and install the bespoke engineering interfaces on Troll A to allow the new pipeline to be pulled-in through the existing seal tube arrangement in the gravity base structure 300 metres below sea level, whilst still providing full isolation between the inside of the platform leg (at ambient) and the seawater pressure outside (30 Barg).

Pete Duguid, STATS Group chief executive officer, said: “The project was challenging as many of the original interfaces no longer complied with current standards and risk assessments and we developed a range of new tools that would provide safe isolations for the pull-in. The biggest challenges were to provide a minimum of two independent isolations during all of the phases of the pull-in, whilst also being able to monitor the pressures between these isolations at all times to provide a safe working environment within the concrete leg 300m below sea level.”

STATS conducted a site survey of the seal tube, (S1), to determine the external and internal condition of the seal tube and associated pipework and valves. The TSU (an early version of STATS’ current Tecno Plug™) hydraulic circuits were function tested to confirm expected fluid returns during setting and unsetting operations, additionally the seals were tested to confirm their condition. The TSU had been stored inside the seal tube for the past 16 years in one atmosphere of nitrogen. STATS confirmed the TSU was fully operational while NDT testing on the associated pipework of the seal tube confirmed wall thickness prior to conducting pressure testing on the system to reduce any risks.

STATS designed a 36” Temporary Anchor as the mechanism by which any axial forces generated by the 36” pipeline was transmitted into the seal-tube and in turn into the gravity base structure. This system stops the differential loading from the water pressure acting on the pipeline forcing the pull head into the platform which in turn could damage the seal tube. The hydraulic cylinders contained sufficient stroke to ensure maximum eccentricity conditions between pipe and Temporary Anchor was accommodated.

The 36” Seal Cartridge is a unique and bespoke interface which provided the seal between the P12 pipeline and the seal tube outer casing. The Seal Cartridge contains two 1.2m diameter compression seals, each weighing in excess of 80kg. The elastomer seals provided a pressure testable barrier system to prevent seawater under pressure from entering the internal end-cap. It also provided an additional sealing function to prevent grout ingress into the internal end cap during the grouting operations. The considerable radial forces generated by the Seal Cartridge elastomers have the added benefit of assisting the pipeline to centralise within the seal tube without causing damage to the pipeline. .

STATS also designed and manufactured the Grout Bung, a subsea installed isolation tool, which provided an external seal between the 36” P12 pipeline and the 50” Troll A seal tube outer casing. The Grout Bung utilises a two part specialist seal, integrated into a large hydraulic clamp assembly with integral locks, which can be remotely closed around the pipeline then manoeuvred into its set location via an arrangement of adjustable hydraulic circuits. The whole assembly was remotely controlled via hydraulic control panels mounted on the deployment frame. The Grout Bung installation was controlled by ROV and supervised by STATS technicians and once installed the void between the Seal Cartridge and Grout Bung could be grouted, providing corrosion resistance, support and stability to the new pipeline prior to installing the internal riser components.

During the project STATS were approached by Allseas, who were responsible for the pipe lay campaign, to design and manufacture the pipeline Pull Head. STATS utilised an existing model from Allseas and modified it to interface with the de-watering isolation tool supplied by STATS.  A unique interface panel integrated in the Pull Head design, allowed the STATS technicians to communicate with the isolation tool in the event of a pipeline wet buckle. The isolation tool could then be used to dewater the repaired pipeline, saving weeks of downtime.

Mr Duguid added: “All stages were successfully completed to schedule by STATS, concluding with the removal of the pull head plug which was set inside the new pipeline to provide an isolation barrier during the final riser tie-in. Additionally, the pull head plug had the capability of being utilised as a dewatering plug in the event of a pipeline wet buckle during the pipe lay operation.

“The safety of people, assets, and the environment is the main focus on all STATS Group projects and our safety record on the P12 project is testimony to those objectives.”

 


People & Company News

MN100: MOPS Marine License Insurance

The Company: Since 1935, MOPS Marine License Insurance has defended the USCG licenses of mariners operating in every maritime sector in the United States. Its network of over 80 maritime law firms,

China Cosco Sinks into Red

Dragged by lackluster freight rates in the maritime transport market during the first half of 2016, China Cosco Holdings logged a 7.2 billion yuan ($1.07 billion) net loss for the January-June half,

DNV GL Backs John Laing on First Offshore Wind Investment

DNV GL successfully completed its due diligence work of the offshore wind farm “Nordergründe” in the North Sea, reviewing and quantifying the technical risks of the project.

Offshore

Esvagt Makes Vestdavit MissionEase First Choice for Mission Bay

Norway-based boat system and davit-handling specialist Vestdavit has secured a breakthrough order for its unique MissionEase multi-boat handling solution for mission Bays,

DNV GL Backs John Laing on First Offshore Wind Investment

DNV GL successfully completed its due diligence work of the offshore wind farm “Nordergründe” in the North Sea, reviewing and quantifying the technical risks of the project.

GoM Operators Evacuating Ahead of Storm

Offshore oil and gas operators in the Gulf of Mexico are evacuating platforms and rigs in the path of Tropical Depression No. 9.   The Bureau of Safety and Environmental

Energy

Jt Study by MOL, Yokohama University for Improving Ocean Shipping Market Forecast

Mitsui O.S.K. Lines, Ltd. today announced that the company and its subsidiary MOL Information Systems, Ltd. have signed a contract with Yokohama National University

DNV GL Launches New Approach to Manage Uncertainty in Risk Assessment

There is increasing emphasis from regulators on addressing uncertainty in risk assessments to improve safety. DNV GL’s new paper, ‘Enabling confidence – addressing uncertainty in risk assessments’,

Gasum, Wärtsilä Join Forces to develop Gas Value Chain

New joint co-operation between Gasum and Wärtsilä aims to develop the utilization and distribution of natural energy gases in marine and land markets. Gasum,

 
 
Maritime Careers / Shipboard Positions Maritime Security Navigation Offshore Oil Pipelines Pod Propulsion Salvage Shipbuilding / Vessel Construction Sonar Winch
rss | archive | history | articles | privacy | contributors | top maritime news | about us | copyright | maritime magazines
maritime security news | shipbuilding news | maritime industry | shipping news | maritime reporting | workboats news | ship design | maritime business

Time taken: 0.1443 sec (7 req/sec)