Panama Canal Work Three-quarters Complete

MarineLink.com
Friday, April 25, 2014
Photo courtesy Panama Canal Authority

The Panama Canal Authority has reported that the expansion of the waterway is 74.2% complete. The news released yesterday, April 24, came on the second day of a construction workers' union strike, GAC said in its daily Hot Port News report.

As of March 31, dredging of the Pacific and Atlantic entrances had been completed, and work to widen Gatun Lake and the Culebra cut was 86% complete. Design and construction of the third set of locks, the most important part of the expansion program, recorded an advance of 68%.

gac.com
 

Maritime Reporter August 2015 Digital Edition
FREE Maritime Reporter Subscription
Latest Maritime News    rss feeds

News

USCG Respopnds to Sunken Vessel Near Sitka, Alaska

The Coast Guard is responding to the sinking of a fishing vessel in Kelp Bay near Sitka Friday. Coast Guard personnel from Sector Juneau, the Coast Guard

Next LCS to be Named USS Minneapolis/St. Paul

Secretary of the Navy Ray Mabus announced today that the next Freedom-variant littoral combat ship will be named USS Minneapolis/St. Paul (LCS 21). The future Minneapolis/St.

MSC Upgrades Europe-West Africa Service

As part of our objective to continually improve our services to customers, MSC is delighted to announce an upgrade to its Angola Express service with a first

 
 
Maritime Contracts Maritime Standards Offshore Oil Pipelines Pod Propulsion Port Authority Ship Repair Ship Simulators Shipbuilding / Vessel Construction Sonar
rss | archive | history | articles | privacy | contributors | top maritime news | about us | copyright | maritime magazines
maritime security news | shipbuilding news | maritime industry | shipping news | maritime reporting | workboats news | ship design | maritime business

Time taken: 0.1912 sec (5 req/sec)