Panama Canal: New Lock Gates Transferred to Atlantic Side

July 21, 2014

Panama Canal lock gates arrival: Photo courtesy of ACP

Panama Canal lock gates arrival: Photo courtesy of ACP

ACP informs that the Panama Canal Expansion has reached another important milestone with the transfer of the first gates to the new locks complex in the Atlantic side.

"This is a very important operation because it involved the first movement of the gates from the special dock where they were unloaded to the lower chamber of the new locks," said Panama Canal Authority (ACP) Administrator Jorge L. Quijano.

The Administrator explained that the process was carried out following rigorous safety measures to ensure that the more than 3,000-ton steel structures could be moved to the dry lock chambers using the pavement ramp built for this purpose.

Eight of the 16 rolling gates that will be used for the new locks are already in Panama. The remaining eight will arrive in two separate shipments from its manufacturing site in Italy.

In the next couple of days, the other gates will be moved from the temporary unloading dock to the dry lock chambers to be able to use the area for the arrival of the remaining lock gates.
 
ACP adds that the Panama Canal Expansion Program is currently 77% complete.
 
 



 
Maritime Reporter Magazine Cover Nov 2016 - Workboat Edition

Maritime Reporter and Engineering News’ first edition was published in New York City in 1883 and became our flagship publication in 1939. It is the world’s largest audited circulation magazine serving the global maritime industry, delivering more insightful editorial and news to more industry decision makers than any other source.

Subscribe
Maritime Reporter E-News subscription

Maritime Reporter E-News is the subsea industry's largest circulation and most authoritative ENews Service, delivered to your Email three times per week

Subscribe for Maritime Reporter E-News