Boskalis, TKF Ink Baltic Offshore Wind Cable Installation Deal

February 26, 2026

Dutch offshore services provider Boskalis, in consortium with TKF Subsea Solutions, has signed a contract with OWP Gennaker, as developed by Skyborn Renewables, for the supply and installation of inter-array cables for the Gennaker offshore wind farm in the German Baltic Sea.

The contract for around 140 kilometers of 66 kilovolt inter-array cables has been classified by Boskalis as sizable, carrying a value between $58 million and $177 million (€50 million and €150 million).

(Credit: Boskalis)
(Credit: Boskalis)

Under the agreement, Boskalis and TKF will deliver the complete inter-array cable system connecting 63 wind turbine generators planned for the project.

The cables will be manufactured in the Netherlands by TKF, after which Boskalis’ cable laying vessel (CLV) Boka Ocean will install them starting at the end of 2027.

With a planned capacity of 976.5 MW, Gennaker is set to become the largest offshore wind farm in the German Baltic Sea, supplying about one million households with renewable energy. Commissioning is scheduled for 2028.

Boskalis is already involved in the project through its subsidiary Heinrich Hirdes EOD Services, which is carrying out an identification and clearance campaign for unexploded ordnance within the wind farm area. The company has deployed its dedicated UXO vessel Kamara for the work.

Related News

DEME Names Norse Energi as Offshore Wind Installation Fleet Expands Petronas Signs 20-year Charter Deal with MISC for Five LNG Carrier Newbuilds Global Oil Supply to Fall Short of Demand as Iran War Goes On, IEA Says TMC, Allseas Ink Deal for First Commercial Deep-Sea Nodule Recovery System Equinor's Gullfaks Field Reaches 5,000 Oil Cargo Milestone in North Sea